B09_Amd7_-_Q37_Attach_-_Pg1_Div01_Spec013_00_Project_Mgmt_0007.pdf

PDF 64 KB Posted

Attached to
DEVA 318717 - Rehab Furnace & Cow Creeks WTP/WWTP
Solicitation number
140P2025R0082
Issued by

About this file

This document is a Section 01 31 00 specification for Project Management and Coordination for a National Park Service construction project. The section outlines administrative provisions for coordinating construction operations, including key definitions and coordination requirements. Key definitions include "Agency with Jurisdiction" (an agency with legal authority over a location or action), "Construction Permits – Contractor Provided" (permits obtained by the contractor for specific work methods), and "Government Furnished Permits" (permits obtained by the National Park Service during the design process). The construction coordination section emphasizes the need to coordinate construction operations across different specification sections to ensure efficient and orderly installation of project components, with a focus on scheduling construction operations in a sequence that optimizes installation based on interdependencies between different work components.

View the file

Other files

File Type Posted
B09_Amd11_-_B08_Attach3_-_WD_CA20260020_Mod2_0011.pdf PDF
Sol_140P2025R0082_Amd_0011.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_42_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_38_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_40_Jan2026_0010.pdf PDF
B09_Amd10_QR_Tracker_-_DEVA_318717_Final_0010.xlsx XLSX spreadsheet
B09_Amd10_-_QR55_Attach_Drawing_01-C4_39_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_00-C8_27_Jan2026_0010.pdf PDF
B09_Amd10_-_QR86_Attach_Drawing_C1_40_0010.pdf PDF
B09_Amd10_-_Drawing_G1_22_0010.pdf PDF
B09_Amd10_-_QR86_Attach_Drawing_C1_40B_0010.pdf PDF
Sol_140P2025R0082_Amd_0010.pdf PDF
B09_Amd10_-_B08_Attach4_-_DetailedContractPriceSchedule_0010.xlsx XLSX spreadsheet
B09_Amd10_-_Drawing_G1_2_0010.pdf PDF
B09_Amd10_-_Drawing_Coversheet_00_DEVA_318717_Jan2026x_0010.pdf PDF
B09_Amd10_-_Drawing_G1_21_0010.pdf PDF
Sol_140P2025R0082_Amd_0009.pdf PDF
B09_Amd8_-_Drawing_02-C5_29_Jan2026_0008.pdf PDF
B09_Amd8_-_Spec_33_14_19_-_VALVES___HYDRANTS_FOR_WATER_UTILITY_SERVICE_0008.pdf PDF
B09_Amd8_-_Drawing_02-G1_16_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_08_33_22_-_ALUMINUM_ROLLING_OVERHEAD_DOORS_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_29_Jan2026_0008.pdf PDF
B09_Amd8_-_QR22_Attach_Drawing_00-C7_1_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C5_25_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_00-C8_30_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_01-C4_42_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C3_1_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_20_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_33_32_00_-_WASTEWATER_PUMPING_STATIONS_0008.pdf PDF
B09_Amd8_-_Spec_33_31_11_-_GRAVITY_SEWER_PIPELINE___MANHOLE_INSTALLATION_0008.pdf PDF
B09_Amd8_QR_Tracker_-_DEVA_318717_0008.xlsx XLSX spreadsheet
B09_Amd8_-_Drawing_Coversheet_00_DEVA_318717_Jan2026_0008.pdf PDF
Sol_140P2025R0082_Amd_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_31_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C6_7_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_15_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-G1_2_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C7_5_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_33_11_13_-_POTABLE_WATER_SUPPLY_WELLS_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_18_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_02-C5_33_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_42_Jan2026_0008.pdf PDF
B09_Amd8_-_QR56_Attach_Drawing_02-C2_20_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_33_31_05_-_MANHOLE_LINING___REHABILITATION_0008.pdf PDF
B09_Amd8_-_Drawing_01-G1_15_Jan2026_0008.pdf PDF
B09_Amd8_-_QR56_Attach_Drawing_02-C2_18_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_67_Jan2026_0008.pdf PDF
B09_Amd8_-_Spec_46_33_11_-_CHEMICAL_FEED_-_LIQUID_SYSTEMS_0008.pdf PDF
B09_Amd8_-_Drawing_02-C2_22_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-X1_2_Jan2026_0008.pdf PDF
Show 40 more

Latest 50 of 109 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEVA – 318717 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Requests for Information (RFIs).

5. Project meetings.

6. Environmental Coordination.

7. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction – An Agency that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document.

B. Construction Permits – Contractor Provided – Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service.

C. Government Furnished Permits – Obtained by National Park Service, usually through the Architect/Engineer or a consultant, during the design process.

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

http://www.nps.gov/dscw/definitionsdc_a.htm http://www.nps.gov/dscw/definitionsdc_c.htm http://www.nps.gov/dscw/definitionsdc_g.htm