10 L 12 SOW ATT 8 DB Schedule Detailed Small Project 07022018.pdf

PDF 416 KB Posted

Attached to
National Elevator Modernization & Construction IDIQ for Task Orders over $1 Million Federal contract opportunity
Solicitation number
47PM1124R0011
Issued by
General Services Administration Public Buildings Service

About this file

This document contains a draft request for proposal for an indefinite delivery/indefinite quantity contract for elevator construction and modernization task orders valued over $1 million.

The General Services Administration intends to award the IDIQ contract for a base year and four option periods with a maximum value of $650 million. Small businesses are eligible as defined by NAICS code 238290 with a size standard of $22 million. The government plans to award up to six IDIQ contracts.

The draft RFP and attachments for two initial task orders are provided. Responses are requested by April 11, 2024 with questions in an excel or word document sent to two specified contracting officials. The subject line should identify the solicitation number and vendor submitting the question. Questions should reference the applicable section or page of the solicitation.

The final RFP will be issued on or around April 19, 2024 with a pre-proposal conference and site visits planned. Proposals will be due approximately 30 days after RFP release.

View the file

Other files for this federal contract opportunity

Other files attached to National Elevator Modernization & Construction IDIQ for Task Orders over $1 Million, newest first.
File Type Posted
10 L 17 SOW ATT 13 LAFAYETTE HISTORIC STRUCTURE REPORT 7 1986.pdf PDF
10 L 10 SOW ATT 6 CD WasteMonthly Report TEMPLATE.pdf PDF
10 L 9 SOW ATT 5 CD Waste Mgmt Plan TEMPLATE.pdf PDF
10 L 6 SOW ATT 2 Section 02085 Asbestos Abatement .pdf PDF
10 L 5 SOW ATT 1 Section 01546_October_2007.pdf PDF
10 L 14 SOW ATT 10 GSA Affiliated Customer Account GACA.pdf PDF
10 H 09 Vol1 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
10 H 01 02085-Asbestos April 2013.pdf PDF
10 01 IDIQ attachment Section 01546 Safety and Health Specification.pdf PDF
10 H 12 HUD Elevator Modernization Draft Bid Sheet.xlsx XLSX spreadsheet
10 05 IDIQ attachment Section 02090 Control of Lead Based Paint Specification.pdf PDF
10 06 IDIQ attachment PIB 18 02 Attachment 6 File Naming.pdf PDF
10 H 08 SECTION 01546 SAFETY AND HEALTH.pdf PDF
10 11 IDIQ attachment GSA 527 Contractors Qualifications and Financial Information.pdf PDF
10 L 7 SOW ATT 3 Section 02090 REMOVAL AND DISPOSAL OF LEAD BASED PAINT.pdf PDF
10 L 19 Wage Determination.pdf PDF
10 L 15 SOW ATT 11 Key Sustaniable Products.pdf PDF
10 H 10 Vol2 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
10 H 07 Hazmat DC0092ZZ CONVERTERS ACM 1 23 07.pdf PDF
10 16 IDIQ attachment SF24 23a.pdf PDF
10 14 IDIQ attachment Bonding Insurance Geography Qualification Sheet.xlsx XLSX spreadsheet
10 00 IDIQ attachment NDA_Document_Security.pdf PDF
10 03 IDIQ attachment Section 02085 Roofing.pdf PDF
10 15 IDIQ attachment IDIQ Pricing Sheet_for eval purposes.xlsx XLSX spreadsheet
10 L 18 SOW ATT 14 PIB 21 06 PIV Card Management Training Final.pdf PDF
10 L 8 SOW ATT 4 Section 211313 GSA Guide Specification Wet Pipe Sprinkler.pdf PDF
10 H 06 Hazmat DC0092ZZ 2023 O M Inspection of Robert C Weaver.pdf PDF
10 L 0 SF18 Lafayette Elevator.pdf PDF
10 L 2 SOW 2023 10 11.pdf PDF
10 L 1 Table of Contents.pdf PDF
10 H 05 Hazmat Bulk Sampling Test Report Submittal_11 1 16.pdf PDF
10 09 ADM 2181 1 Homeland Security Presidential Directive 12 Personal Identity Verification for Contractor Employees.pdf PDF
10 02 IDIQ attachment Section 02085 Asbestos Abatement Procedures.pdf PDF
10 H 02 02090-ControlofLBP January_2013.pdf PDF
10 12 IDIQ attachment Past Performance.xlsx XLSX spreadsheet
10 National Elevator IDIQ RFP and Agreement 2024 03 17.pdf PDF
10 L 11 SOW AT 7 CIW Form.pdf PDF
10 L 16 SOW ATT 12 2019 REINSPECTION OF LAFAYETTE BLDG.pdf PDF
10 L 13 SOW ATT 9 Elevator Final Study DLR.pdf PDF
10 H 11 Weaver Building Elevator Study_100_ Submission_COMBINED_ALL.pdf PDF
10 H 04 Hazmat ASBESTOS-8987_FINAL CLEARANCE AIR MONITORING VISUAL INSPECTION REPORT_10 19 2015.pdf PDF
10 H 00 HUD Elevator Modernization Draft SOW.pdf PDF
10 H ZZ HUD Programatic Agreement signed.pdf PDF
10 10 IDIQ attachment Reps and Certifications.pdf PDF
10 INFORMATIONAL not official attachment GACA__GSAAffiliatedCustomerAccounts_May_2016v2.pdf PDF
10 04 IDIQ attachment Section 02087 Removal of Bird and Bat Droppings.pdf PDF
10 18 IDIQ attachment Task Order Pricing Sheet.xlsx XLSX spreadsheet
10 07 IDIQ attachment ADM 7002.1 GSA Smart Buildings.pdf PDF
10 H 03 CD Waste Mgmt Plan.xlsx XLSX spreadsheet
10 17 IDIQ attachment Small Business Participation Plan_SBPP_Template .docx DOCX document
Show all 50

National Elevator Modernization & Construction IDIQ for Task Orders over $1 Million has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Mode

Task Name Kahua Milestone Code

Duration Calendar Days

% Complete Scheduled Start

Scheduled Finish

1 Project Name (Design-Build Projects under Prospectus - federal or post occupancy lease)653 days 946 days 0% 2/1/2022 9/3/2024 2 Initiation 3 days 3 days 0% 2/1/2022 2/3/2022 3 Project Start-up 3 days 3 days 0% 2/1/2022 2/3/2022 4 Receive and Acknowledge Customer Request

(External or Internal) 1 day 1 day 0% 2/1/2022 2/1/2022

5 Kahua Milestone: Customer Request 1.011 0 days 0 days 0% 2/1/2022 2/1/2022 6 Create Project in System of Record (Kahua, GREX/REXUS) 2 days 2 days 0% 2/2/2022 2/3/2022 7 Kahua Milestone: Project Initiated 2.011 0 days 0 days 0% 2/3/2022 2/3/2022 8 Planning 208 days 301 days 0% 2/4/2022 12/1/2...

9 Draft and Validate Functional Requirements 19 days 28 days 0% 2/4/2022 3/3/2022

10 Schedule, prepare for, hold, and document Customer interview - Request specialized requirements.

12 days 19 days 0% 2/4/2022 2/22/2...

11 Draft Functional requirements (scope goals), create budgetary estimate, develop preliminary project duration

7 days 9 days 0% 2/23/2022 3/3/2022

12 Validate Project 3 days 5 days 0% 3/4/2022 3/8/2022 13 Confirm Functional Requirements, Duration, Funding

Schedule, Budget with customer (internal and external)

3 days 5 days 0% 3/4/2022 3/8/2022

14 Kahua Milestone: Initial Scope and Requirements Finalized with Customer

3.041 0 days 0 days 0% 3/8/2022 3/8/2022

15 Create PMP 13 days 17 days 0% 3/9/2022 3/25/2...

16 Schedule and hold kick off meeting and site visit 5 days 7 days 0% 3/9/2022 3/15/2...

17 Develop Project Management Plan (PMP) 13 days 17 days 0% 3/9/2022 3/25/2...

18 Finalize project planning documents 83 days 118 days 0% 3/4/2022 6/29/2...

19 Customer compiles specialized personal property requirements (IT/AV, furniture, etc) 60 days 84 days 0% 3/4/2022 5/26/2...

20 Finalize Scope, schedule and estimate, pricing policy check by Portfolio

10 days 14 days 0% 5/13/2022 5/26/2...

21 [Over SAT: Have estimate reviewed by Estimating Team] 10 days 15 days 0% 5/27/2022 6/10/2...

22 Confirm Scope/Schedule/Budget with Customer

(Internal and external) 3 days 3 days 0% 6/13/2022 6/15/2...

23 Kahua Milestone: Customer Concurrence on Final Scope, Schedule and Cost Estimate

3.081 0 days 0 days 0% 6/15/2022 6/15/2...

24 Final Signed Draft Occupancy Agreement 10 days 14 days 0% 6/16/2022 6/29/2...

25 Pre-Design Studies 126 days 183 days 0% 6/2/2022 12/1/2...

26 Space Planning/DIDs (delete if being done as part of

Design, or already complete by agency) 101 days 146 days 0% 6/2/2022 10/25/...

27 Funding/RWA for DID services 20 days 29 days 0% 6/30/2022 7/28/2...

28 Procure Study firm (delete if DIDs will be done in-house by GSA) 40 days 57 days 0% 6/2/2022 7/28/2...

29 DIDs 20 days 28 days 0% 7/29/2022 8/25/2...

30 GSA & Customer Review 15 days 22 days 0% 8/26/2022 9/16/2...

31 Customer Union Review 40 days 60 days 0% 8/26/2022 10/24/...

32 Consolidate DID review comments 1 day 1 day 0% 10/25/2022 10/25/...

33 Obtain Funding Commitment for [Design and

Construction] (Internal and/or Request and process

RWA)

25 days 37 days 0% 10/26/2022 12/1/2...

34 Kahua Milestone: Project Fully Authorized for Execution4.011 0 days 0 days 0% 12/1/2022 12/1/2...

35 Kahua Milestone: RWA Funds Received/Certifiied 4.201 0 days 0 days 0% 12/1/2022 12/1/2...

36 Customer, Personal Property 546 days 795 days 0% 5/27/2022 7/29/2...

Receive and Acknowledge Customer Request (External or Internal)

2/1

Create Project in System of Record (Kahua, GREX/REXUS)

2/3

Schedule, prepare for, hold, and document Customer interview - Request specialized requirements.

Draft Functional requirements (scope goals), create budgetary estimate, develop preliminary project duration

Project Manager,Customer,Asset Manager,Sponsor

3/8

Project Manager,Asset Manager,Contracting Officer,COR

Asset Manager,Contracting Officer,COR,Property Manager,Project Manager,Sponsor

Customer compiles specialized personal property requirements (IT/AV, furniture, etc)

Finalize Scope, schedule and estimate, pricing policy check by Portfolio

[Over SAT: Have estimate reviewed by Estimating Team]

Confirm Scope/Schedule/Budget with Customer (Internal and external)

6/15

Final Signed Draft Occupancy Agreement

Funding/RWA for DID services

Procure Study firm (delete if DIDs will be done in-house by GSA)

DIDs

Customer,Asset Manager,COR,Project Manager,Subject Matter Expert,Property Manager

Customer Union Review

Consolidate DID review comments

Obtain Funding Commitment for [Design and Construction] (Internal and/or Request and process RWA)

12/1

12/1

H1 H2 H1 H2 H1 H2 H1 H2 2022 2023 2024 2025

Task Name Kahua Milestone Code

Duration Calendar Days

% Complete Scheduled Start

Scheduled Finish

37 Security 405 days 589 days 0% 5/27/2022 1/5/2024 38 Security SOW and Estimate 40 days 60 days 0% 5/27/2022 7/25/2...

39 Security RWA (if being purchased through GSA) 20 days 28 days 0% 7/26/2022 8/22/2...

40 Security Plan/Design procurement/change order to design contractor 20 days 26 days 0% 7/31/2023 8/25/2...

41 Confirm requirements: Customer Interview 5 days 5 days 0% 8/28/2023 9/1/2023 42 Security Plan/Design 15 days 21 days 0% 9/5/2023 9/25/2...

43 GSA/Customer Review 10 days 15 days 0% 9/26/2023 10/10/...

44 Coordinate Security Infrastructure with Design firm

(delete if design done by prime AE) 10 days 14 days 0% 10/11/2023 10/24/...

45 Security Procurement/change order to Construction contractor 30 days 43 days 0% 10/25/2023 12/6/2...

46 Security Install 10 days 14 days 0% 12/7/2023 12/20/...

47 Security Contractor Evaluation, Payment 10 days 16 days 0% 12/21/2023 1/5/2024 48 Telephone/IT/AV 400 days 581 days 0% 5/27/2022 12/28/...

49 Telephone/IT/AV SOW and Estimate 40 days 60 days 0% 5/27/2022 7/25/2...

50 Telephone/IT/AV RWA (if being purchased through GSA) 20 days 28 days 0% 7/26/2022 8/22/2...

51 Telephone/IT/AV Plan/Design procurement/change order to design contractor 20 days 26 days 0% 7/31/2023 8/25/2...

52 Confirm requirements: Customer Interview 5 days 5 days 0% 8/28/2023 9/1/2023 53 Telephone/IT/AV Plan/Design 5 days 7 days 0% 9/5/2023 9/11/2...

54 GSA/Customer Review 10 days 14 days 0% 9/12/2023 9/25/2...

55 Coordinate Tele/AV/IT Infrastructure with Design firm

(delete if design done by prime AE) 10 days 15 days 0% 9/26/2023 10/10/...

56 Telephone/IT/AV Procurement/change order to Construction contractor

30 days 42 days 0% 10/11/2023 11/21/...

57 Telephone/IT/AV Install 10 days 15 days 0% 11/22/2023 12/6/2...

58 Inspection and Acceptance 5 days 7 days 0% 12/7/2023 12/13/...

59 Telephone/IT/AV Contractor Evaluation, Payment 10 days 15 days 0% 12/14/2023 12/28/...

60 Furniture 226 days 330 days 0% 8/28/2023 7/22/2...

61 Furniture SOW and Estimate 20 days 29 days 0% 8/28/2023 9/25/2...

62 Furniture RWA (if being purchased through GSA) 20 days 29 days 0% 9/26/2023 10/24/...

63 Furniture design procurement/change order to design contractor 20 days 28 days 0% 10/25/2023 11/21/...

64 Confirm requirements: Customer Interview 5 days 8 days 0% 11/22/2023 11/29/...

65 Furniture Design 40 days 61 days 0% 11/30/2023 1/29/2...

66 GSA/Customer Review 10 days 14 days 0% 1/30/2024 2/12/2...

67 Coordinate Furniture Power/Data Requirements with

Design firm (delete if design done by prime AE) 10 days 15 days 0% 2/13/2024 2/27/2...

68 Furniture Purchase 30 days 42 days 0% 2/28/2024 4/9/2024 69 Select furniture finishes 5 days 7 days 0% 4/10/2024 4/16/2...

70 Furniture lead time 50 days 72 days 0% 4/17/2024 6/27/2...

71 Furniture Delivery and Install 5 days 8 days 0% 6/28/2024 7/5/2024 72 Furniture Inspection and Acceptance 1 day 1 day 0% 7/8/2024 7/8/2024 73 Connect furniture power and data 2 days 2 days 0% 7/9/2024 7/10/2...

74 Furniture Contractor Evaluation, Payment 10 days 14 days 0% 7/9/2024 7/22/2...

75 Move Services 118 days 172 days 0% 2/9/2024 7/29/2...

76 Move SOW and Estimate 1 day 1 day 0% 2/23/2024 2/23/2...

Project Manager,Customer

Project Manager,Customer

Contracting Officer,Customer

AE,Customer

AE,Customer

Customer,Project Manager

AE

Customer,Contracting Officer

Customer,Project Manager

Customer,Project Manager

Project Manager,Customer

Project Manager,Customer

Contracting Officer,Customer

AE,Customer

AE,Customer

Customer,Project Manager

AE

Customer,Contracting Officer

Customer,Project Manager

Customer,Project Manager

Customer,Project Manager

Customer,Project Manager

Customer,Project Manager

Customer,Contracting Officer

AE,Customer

AE,Customer

Customer,Project Manager

AE

Customer,Project Manager

Customer,Project Manager

Construction Contractor,Customer

Construction Contractor,Customer

Customer,Project Manager

Construction Contractor

Customer,Project Manager

Customer,Project Manager

H1 H2 H1 H2 H1 H2 H1 H2

Task Name Kahua Milestone Code

Duration Calendar Days

% Complete Scheduled Start

Scheduled Finish

77 Move Prep - Inventory 10 days 15 days 0% 2/9/2024 2/23/2...

78 Move Services RWA (if being purchased through GSA) 20 days 26 days 0% 2/26/2024 3/22/2...

79 Move Services Procurement / change order to construction contractor 15 days 19 days 0% 3/25/2024 4/12/2...

80 Confirm Requirements: Customer Interview 5 days 5 days 0% 4/15/2024 4/19/2...

81 Pre-Occupancy Meeting with Tenant - create emergency occupancy plan, hand over keys, etc 1 day 1 day 0% 4/22/2024 4/22/2...

82 Tenant Move 3 days 5 days 0% 7/11/2024 7/15/2...

83 List Excess furniture 40 days 61 days 0% 5/16/2024 7/15/2...

84 Excess furniture 2 days 2 days 0% 7/16/2024 7/17/2...

85 Existing Lease Expiration (add date constraint - see notes) 0 days 0 days 0% 7/17/2024 7/17/2...

86 Move Contractor Evaluation, Payment 10 days 14 days 0% 7/16/2024 7/29/2...

87 Execution 411 days 596 days 0% 12/2/2022 7/19/2...

88 CMa/Environmental Consultant/Other Procurement - IDIQ 60 days 88 days 0% 12/2/2022 2/27/2...

89 Compile Technical Documents, RFQ, confirm estimate, gather supplemental information - include estimate triage level

7 days 11 days 0% 12/2/2022 12/12/...

90 Procurement Request and Acquisition Package Development

11 days 15 days 0% 12/13/20... 12/27/...

91 Create and Route Procurement Request (PR) 1 day 1 day 0% 12/13/2022 12/13/...

92 PR Review by Contracting Supervisors 5 days 7 days 0% 12/14/2022 12/20/...

93 CO Accepts the Acquisition Package 5 days 7 days 0% 12/21/2022 12/27/...

94 Solicitation 20 days 29 days 0% 12/28/20... 1/25/2...

95 RFQ out for proposals 5 days 7 days 0% 12/28/2022 1/3/2023 96 Hold walk thru and publish clarifications 5 days 7 days 0% 1/4/2023 1/10/2...

97 Receive Proposals 1 day 1 day 0% 1/11/2023 1/11/2...

98 Negotiate Final Proposal 5 days 8 days 0% 1/12/2023 1/19/2...

99 Receive Final Proposal 4 days 6 days 0% 1/20/2023 1/25/2...

100 Award 22 days 33 days 0% 1/26/2023 2/27/2...

101 Amend funding request and re-route PR (if necessary) 10 days 14 days 0% 1/26/2023 2/8/2023 102 Compile Award Documentation 2 days 2 days 0% 1/26/2023 1/27/2...

103 Award CMa Contract 1 day 1 day 0% 2/27/2023 2/27/2...

104 Kahua Milestone: CMa Award 4.245 0 days 0 days 0% 2/27/2023 2/27/2...

105 Issue CMa NTP 0 days 0 days 0% 2/27/2023 2/27/2...

106 PALT Average (based on AE Single Award task order.

Delete if CO agrees to above timeline) 41 days 59 days 0% 12/28/2022 2/24/2...

107 Design Build Prime Contract Procurement 165 days 238 days 0% 12/2/2022 7/27/2...

108 Design Build - IDIQ 56 days 82 days 0% 12/2/2022 2/21/2...

109 Compile Technical Documents, RFQ, confirm estimate, gather supplemental information -include estimate triage level

7 days 11 days 0% 12/2/2022 12/12/...

110 Procurement Request and Acquisition Package Development

11 days 15 days 0% 12/13/20... 12/27/...

111 Create and route Procurement Request (PR) 1 day 1 day 0% 12/13/2022 12/13/...

112 PR Review by Contracting Supervisors 5 days 7 days 0% 12/14/2022 12/20/...

113 Kahua Milestone: PM Submits Design Build Package4.401 0 days 0 days 0% 12/20/2022 12/20/...

114 CO Accepts the Acquisition Package 5 days 7 days 0% 12/21/2022 12/27/...

115 Kahua Milestone: Design Build PR Package Accepted4.411 0 days 0 days 0% 12/27/2022 12/27/...

Customer,Project Manager

Customer,Project Manager

Customer,Contracting Officer

Customer,Construction Contractor

Customer,Project Manager

Customer,Project Manager

Customer

Customer,Project Manager

7/17

Customer,Project Manager

COR,Project Manager,Property Manager

Project Manager,COR

Contracting Officer

Contracting Officer

Contracting Officer,COR,Project Manager

Contracting Officer,COR,Project Manager

Contracting Officer

Contracting Officer,COR,Project Manager

Contracting Officer

Project Manager,COR,Customer

Contracting Officer

Contracting Officer

2/27

2/27

Contracting Officer

Contracting Officer,COR,Project Manager,Property Manager

Project Manager,COR

Contracting Officer

12/20

Contracting Officer

12/27

H1 H2 H1 H2 H1 H2 H1 H2

Task Name Kahua Milestone Code

Duration Calendar Days

% Complete Scheduled Start

Scheduled Finish

116 Solicitation 26 days 37 days 0% 12/28/20... 2/2/2023 117 RFQ out for proposals 15 days 22 days 0% 12/28/2022 1/18/2...

118 Schedule and hold Pre-proposal Conference and site walkthru, publish clarifications 5 days 7 days 0% 12/28/2022 1/3/2023

119 Receive Proposals 2 days 2 days 0% 1/19/2023 1/20/2...

120 Negotiate Final Proposal 5 days 5 days 0% 1/23/2023 1/27/2...

121 Receive Final Proposal 4 days 4 days 0% 1/30/2023 2/2/2023 122 Award 12 days 19 days 0% 2/3/2023 2/21/2...

123 Amend funding request (if necessary) 7 days 11 days 0% 2/3/2023 2/13/2...

124 Compile and Award Contract 5 days 8 days 0% 2/14/2023 2/21/2...

125 Kahua Milestone: Prime Contract Award 4.491 0 days 0 days 0% 2/21/2023 2/21/2...

126 Design Build - Full and Open Competition 165 days 238 days 0% 12/2/2022 7/27/2...

127 Develop scope of work and RFP, confirm estimate and Liquidated Damages Calculation 10 days 14 days 0% 12/2/2022 12/15/...

128 [Over SAT: Have estimate reviewed by Estimating Team] - only if costs change due to SOW revisions

10 days 14 days 0% 12/16/2022 12/29/...

129 Compile Solicitation Package 33 days 48 days 0% 12/16/20... 2/1/2023 130 SBA Approval 20 days 28 days 0% 12/16/20... 1/12/2...

131 Market Research - sources sought - dynamic small business search 10 days 14 days 0% 12/16/2022 12/29/...

132 OSBU and SBA Review and Approval 10 days 14 days 0% 12/30/2022 1/12/2...

133 Procurement Request and Acquisition Plan 23 days 34 days 0% 12/30/20... 2/1/2023 134 Create Procurement Request (PR) 2 days 4 days 0% 12/30/2022 1/2/2023 135 Route PR for funds certification and approval 3 days 3 days 0% 1/3/2023 1/5/2023 136 Create/Finalize acquisition plan 5 days 7 days 0% 1/6/2023 1/12/2...

137 [Over SAT: Additional Routing of Acquisition plan for approval] 3 days 6 days 0% 1/13/2023 1/18/2...

138 If not Using Lowest Price, Complete the Source Selection Evaluation Plan

10 days 15 days 0% 1/13/2023 1/27/2...

139 Kahua Milestone: PM Submits Design Build Package4.401 0 days 0 days 0% 1/18/2023 1/18/2...

140 CO Accepts the Acquisition Package and

Finalizes RFP 10 days 14 days 0% 1/19/2023 2/1/2023

141 Kahua Milestone: Design Build PR Package Accepted4.411 0 days 0 days 0% 2/1/2023 2/1/2023 142 Solicitation 65 days 92 days 0% 2/2/2023 5/4/2023 143 Issue RFP 1 day 1 day 0% 2/2/2023 2/2/2023 144 RFP out for proposals 22 days 33 days 0% 2/3/2023 3/7/2023 145 Schedule and hold Pre-Proposal Conference and

Site Walkthru 10 days 14 days 0% 2/3/2023 2/16/2...

146 RFI Due Date 5 days 8 days 0% 2/17/2023 2/24/2...

147 Publish Clarifications/Amendments 5 days 5 days 0% 2/27/2023 3/3/2023 148 Initial Proposal Due 2 days 2 days 0% 3/6/2023 3/7/2023 149 Technical and Price Evaluation, peform pricing policy TI/Shell check with asset management, prepare pre-negotiation objectives

10 days 14 days 0% 3/8/2023 3/21/2...

150 Conduct Negotiations 15 days 21 days 0% 3/22/2023 4/11/2...

151 Final Proposal Revision (best and final) 7 days 9 days 0% 4/12/2023 4/20/2...

Project Manager

COR,Property Manager,Project Manager

Contracting Officer

Contracting Officer,COR,Project Manager

Contracting Officer,Project Manager,COR

Project Manager,COR,Customer

Contracting Officer

2/21

Develop scope of work and RFP, confirm estimate and Liquidated Damages Calculation

[Over SAT: Have estimate reviewed by Estimating Team] - only if costs change due to SOW revisions

Contracting Officer

Contracting Officer

Create Procurement Request (PR)

Route PR for funds certification and approval

Create/Finalize acquisition plan

[Over SAT: Additional Routing of Acquisition plan for approval]

COR,Project Manager

1/18

CO Accepts the Acquisition Package and Finalizes RFP

2/1

Contracting Officer

Construction Contractor

Contracting Officer,COR,Project Manager

Construction Contractor

Contracting Officer

Contracting Officer

Project Manager,Contracting Officer,COR,Asset Manager

Project Manager,COR,Contracting Officer

Construction Contractor

H1 H2 H1 H2 H1 H2 H1 H2

Task Name Kahua Milestone Code

Duration Calendar Days

% Complete Scheduled Start

Scheduled Finish

152 Technical Report and Recommendation 5 days 7 days 0% 4/21/2023 4/27/2...

153 Accept Report and Recommendation and Finalize

Selection Decision 5 days 7 days 0% 4/28/2023 5/4/2023

154 Award 57 days 84 days 0% 5/5/2023 7/27/2...

155 Route PR for Policy/Legal Review and Signatures 20 days 29 days 0% 5/5/2023 6/2/2023 156 Compile Award Documentation, Record of

Negotiations, Price Reasonableness Determination

10 days 15 days 0% 5/19/2023 6/2/2023

157 Award Contract 1 day 1 day 0% 7/27/2023 7/27/2...

158 Kahua Milestone: Design Build Contractor Award 4.491 0 days 0 days 0% 7/27/2023 7/27/2...

159 PALT Average (<SAT full and open): delete if CO agrees to above timeline 52 days 75 days 0% 1/26/2023 4/10/2...

160 PALT Average (>SAT full and open): delete if CO agrees to above timeline

126 days 182 days 0% 1/26/2023 7/26/2...

161 Design 143 days 210 days 0% 7/28/2023 2/22/2...

162 Pre-Design 60 days 88 days 0% 7/28/2023 10/23/...

163 Issue NTP 1 day 1 day 0% 7/28/2023 7/28/2...

164 Obtain Security Clearances 60 days 88 days 0% 7/28/2023 10/23/...

165 Site Investigations 5 days 7 days 0% 7/28/2023 8/3/2023 166 Customer interviews 10 days 14 days 0% 7/28/2023 8/10/2...

167 Schedule and hold Kick-off meeting 10 days 12 days 0% 7/31/2023 8/11/2...

168 Prealteration assessment 10 days 12 days 0% 8/14/2023 8/25/2...

169 Design Execution 142 days 207 days 0% 7/31/2023 2/22/2...

170 Conceptual design / Space Planning / DIDs (delete if space planning done before design) 61 days 87 days 0% 7/31/2023 10/25/...

171 Concepts / Block Plans/DIDs Submission 20 days 26 days 0% 7/31/2023 8/25/2...

172 GSA and Customer Review Concepts/Block Plans/DIDs 15 days 22 days 0% 8/28/2023 9/18/2...

173 Customer Union Review Concepts/Block Plans/DIDs 40 days 58 days 0% 8/28/2023 10/24/...

174 Consolidate Concepts/Block Plans/DIDs comments 1 day 1 day 0% 10/25/2023 10/25/...

175 Construction Documents (CDs) 81 days 120 days 0% 10/26/20... 2/22/2...

176 Prepare 1st CDs Submission 20 days 28 days 0% 10/26/2023 11/22/...

177 GSA and Customer Review 1st CDs Submission 15 days 21 days 0% 11/24/2023 12/14/...

178 Prepare 2nd CDs Submission 20 days 33 days 0% 12/15/2023 1/16/2...

179 GSA and Customer Review 2nd CDs Submission 15 days 21 days 0% 1/17/2024 2/6/2024 180 [Over SAT: Have estimate reviewed by Estimating Team] 10 days 14 days 0% 1/17/2024 1/30/2...

181 Prepare Final CDs Submission 10 days 15 days 0% 2/7/2024 2/21/2...

182 GSA Review and Approval of Final CDs Submission 1 day 1 day 0% 2/22/2024 2/22/2...

183 Kahua Milestone: Design Complete 4.361 0 days 0 days 0% 2/22/2024 2/22/2...

184 Construction 246 days 358 days 0% 7/28/2023 7/19/2...

185 Pre-Construction 25 days 40 days 0% 12/15/20... 1/23/2...

186 Division 1 Submittals (Emergency contact list, safety plan, QC plan, Preliminary Schedule, Permits, Bonds, etc)

10 days 15 days 0% 12/15/2023 12/29/...

187 GSA Review of Submittals 15 days 22 days 0% 1/2/2024 1/23/2...

188 General Contractor Construction Execution 246 days 358 days 0% 7/28/2023 7/19/2...

189 Kahua Milestone: Construction Start 4.581 0 days 0 days 0% 2/22/2024 2/22/2...

190 [Insert and Link Contractors Construction Schedule] 90 days 130 days 0% 2/23/2024 7/1/2024 191 Building Management Controls (BMC) 246 days 358 days 0% 7/28/2023 7/19/2...

192 Project Planning, Scope Development & Sourcing 25 days 35 days 0% 7/28/2023 8/31/2...

COR,Project Manager

Contracting Officer

Project Manager,Contracting Officer,COR,OGC,Construction Contractor

Contracting Officer

Award Contract

7/27

Contracting Officer

PALT Average (>SAT full and open): delete if CO agrees to above timeline

Issue NTP

Construction Contractor,COR

AE,Property Manager

AE,Customer

Schedule and hold Kick-off meeting

Prealteration assessment

Concepts / Block Plans/DIDs Submission

Project Manager,COR,Property Manager,Asset Manager,Subject Matter Expert

Customer Union Review Concepts/Block Plans/DIDs

Consolidate Concepts/Block Plans/DIDs comments

Prepare 1st CDs Submission

GSA and Customer Review 1st CDs Submission

Prepare 2nd CDs Submission

GSA and Customer Review 2nd CDs Submission

Subject Matter Expert

Prepare Final CDs Submission

GSA Review and Approval of Final CDs Submission

2/22

Construction Contractor

Project Manager,COR,Contracting Officer,Property Manager

2/22

[Insert and Link Contractors Construction Schedule]

H1 H2 H1 H2 H1 H2 H1 H2

Task Name Kahua Milestone Code

Duration Calendar Days

% Complete Scheduled Start

Scheduled Finish

193 Project Coordination/Communication with Other Program Stakeholders20 days 28 days 0% 7/28/2023 8/24/2...

194 Identify Opportunities for BMC Elements 20 days 28 days 0% 7/28/2023 8/24/2...

195 SOW Development 5 days 7 days 0% 8/25/2023 8/31/2...

196 Reference Chapter 8 of the BTTRG for IT Scope Requirements5 days 7 days 0% 8/25/2023 8/31/2...

197 Consideration for SMAs for Future System Support 5 days 7 days 0% 8/25/2023 8/31/2...

198 Design 90 days 128 days 0% 2/7/2024 6/13/2...

199 BMC System Design 90 days 128 days 0% 2/7/2024 6/13/2...

200 120+ Calendar Days Out 90 days 128 days 0% 2/7/2024 6/13/2...

201 Initiate HSPD-12 Clearance Process for Users Requiring ENT Domain90 days 128 days 0% 2/7/2024 6/13/2...

202 Engage with GSA IT & OFM on BMC

Integration/upgrade project/project kick off

1 day 1 day 0% 2/7/2024 2/7/2024

203 Review Network Topology (discuss cabling, hardware needs, IP needs, device/app)10 days 15 days 0% 2/8/2024 2/22/2...

204 Request Cut Sheets from BAS Contractor 5 days 7 days 0% 2/8/2024 2/14/2...

205 Order New/Upgraded Circuits 40 days 56 days 0% 2/23/2024 4/18/2...

206 Initiate Device/Application Scanning with GSA-IT Sec10 days 14 days 0% 2/23/2024 3/7/2024 207 Final Approval at 50% Design with FM and GSA-IT (Kahua Milestone)

4.305 0 days 0 days 0% 2/22/2024 2/22/2...

208 60 Calendar Days Out 10 days 14 days 0% 2/23/2024 3/7/2024 209 Provide Network Riser (Include Controller Locations) for Review and Approval by GSA-IT5 days 7 days 0% 2/23/2024 2/29/2...

210 Confirm New Cabling Requirements with GSA-IT 10 days 14 days 0% 2/23/2024 3/7/2024 211 40 Calendar Days Out 20 days 28 days 0% 3/8/2024 4/4/2024 212 Government Furnished Equipment Ordered and Delivered to Site20 days 28 days 0% 3/8/2024 4/4/2024 213 Construction 70 days 99 days 0% 3/8/2024 6/14/2...

214 BMC System Delivery 70 days 99 days 0% 3/8/2024 6/14/2...

215 Submittal Review & Approval prior to

Construction RFP (Final) 10 days 14 days 0% 3/8/2024 3/21/2...

216 Provide Updated Schedule to Smart Building POC 5 days 7 days 0% 3/22/2024 3/28/2...

217 Install Network Equipment 1 day 1 day 0% 6/14/2024 6/14/2...

218 Closeout & Commissioning 23 days 33 days 0% 6/17/2024 7/19/2...

219 Punch-list& Commissioning 20 days 30 days 0% 6/17/2024 7/16/2...

220 Confirm Required BMC System Access 3 days 4 days 0% 6/17/2024 6/20/2...

221 Closeout Password Coordination 3 days 4 days 0% 6/17/2024 6/20/2...

222 O&M Coordination for Warranties 5 days 7 days 0% 6/21/2024 6/27/2...

223 Update Any Necessary O&M Contract Clauses 10 days 15 days 0% 6/28/2024 7/12/2...

224 Coordination for Software Maintenance Agreement (SMA) Contracts5 days 5 days 0% 7/15/2024 7/19/2...

225 BMC Training for Operators 3 days 3 days 0% 7/17/2024 7/19/2...

226 Emergency Preparedness Including Building Recovery 3 days 3 days 0% 7/17/2024 7/19/2...

227 Request Substantial Completion 1 day 1 day 0% 7/2/2024 7/2/2024 228 Kahua Milestone: Substantial Completion 4.691 0 days 0 days 0% 7/2/2024 7/2/2024 229 Kahua Milestone: Rent Start 5.041 0 days 0 days 0% 7/2/2024 7/2/2024 230 Kahua Milestone: IRIS ASID Substantial Completion 5.005 0 days 0 days 0% 7/2/2024 7/2/2024 231 Kahua Milestone: RETA RWA Financial Completion 5.008 0 days 0 days 0% 7/2/2024 7/2/2024 232 Close Out 43 days 63 days 0% 7/3/2024 9/3/2024 233 Construction Contract Closeout 42 days 59 days 0% 7/3/2024 8/30/2...

234 Perform Contractor Evaluations 5 days 8 days 0% 7/3/2024 7/10/2...

235 Release of Claims 5 days 8 days 0% 7/3/2024 7/10/2...

Project Manager

Smart Buildings Specialist

SME Team

Smart Buildings Specialist

Project Manager

Project Team

Smart Buildings Specialist,GSA IT

SME Team,Technical COR

GSA IT,FM

GSA IT,FM

2/22

BAS,BMC Vendor

BAS,BMC Vendor

GSA IT,FM

GSA IT,FM

Project Manager

BAS,BMC Vendor

BAS,BMC Vendor

Project Manager

GSA IT,FM

FM

FM

Smart Buildings Specialist

BAS,BMC Vendor

GSA IT,FM

Request Substantial Completion

7/2

7/2

7/2

7/2

Contracting Officer,Project Manager

Contracting Officer,Construction Contractor

H1 H2 H1 H2 H1 H2 H1 H2

Task Name Kahua Milestone Code

Duration Calendar Days

% Complete Scheduled Start

Scheduled Finish

236 Allowed Contractor Construction Completion time per spec

42 days 59 days 0% 7/3/2024 8/30/2...

237 Construction Final Payment 10 days 14 days 0% 7/11/2024 7/24/2...

238 Project Closeout 28 days 41 days 0% 7/25/2024 9/3/2024 239 Reconcile actual TI costs and finalize OA 10 days 14 days 0% 7/25/2024 8/7/2024 240 Close Funding Documents (RETA, IRIS etc) and Return

Remaining Funds 3 days 5 days 0% 8/8/2024 8/12/2...

241 Update Electronic Databases, Mark Project Closed in Kahua 1 day 1 day 0% 9/3/2024 9/3/2024 242 Kahua Milestone: Project Closeout 6.011 0 days 0 days 0% 9/3/2024 9/3/2024

Allowed Contractor Construction Completion time per spec

COR,Project Manager,Contracting Officer

Asset Manager,Customer,Project Manager

Project Manager,Finance

Update Electronic Databases, Mark Project Closed in Kahua

9/3