This document contains a draft request for proposal for a national elevator modernization indefinite delivery/indefinite quantity multiple award contract and two related initial task order attachments.
The General Services Administration intends to award multiple IDIQ contracts for a one year base period and four one-year options with a total maximum value of $650 million. The scope of the IDIQ and task orders includes elevator construction and modernization projects valued over $1 million. Questions and comments are requested on the draft RFP and task order attachments by April 11, 2024. Proposals for the IDIQ contracts are due approximately 30 days after final RFP release. The initial task order attachments are for modernization projects at Lafayette Building #9. This represents an opportunity for elevator construction and modernization contractors to bid on a new multiple award IDIQ vehicle and initial task orders from the General Services Administration.
View the file
Other files for this federal contract opportunity
Show all 50
National Elevator Modernization & Construction IDIQ for Task Orders over $1 Million has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Waste Diversion Report
Project Waste Management Plan : split report into 2? anticipated and actual?
| -Steve Scavo - PMCB | Submittal Type: | Waste Diversion Plan (Anticipated) : | TRUE | Waste Diversion Report (Final) : | TRUE | ||||||
| (to be filled out by GSA) | |||||||||||
| Project Name: | HUD Weaver Elevator Modernization DB | ECC: | Project Manager: | Christopher Cahoon | Kahua Project # : | 26175 | |||||
| Project Short Description: | Design Build Modernization of Passenger Elevators 1-16, Freight Elevators 17-19, Hydraulic Service Elevators 20-21, & Vertical Lift 22 | PM email or phone: | christopher.cahoon@gsa.gov | gBUILD Project # : | N/A | ||||||
| Building Number: | DC0092ZZ | Service Center / Field Office: | Budget Activity: | BA80 | RWA # : | TBD | |||||
| (to be filled out by Contractor) | |||||||||||
| Anticipated Waste Diversion Plan | |||||||||||
| To be filled out and submitted Pre-Construction (with final Construction Documents) | Actual Waste Diversion Report | ||||||||||
| To be submitted during Project Close-Out | Diversion |
Rate
| Material | ||||||||||||||||
| (see weight conversion factors below) | Diversion | Waste not Diverted | Diverted Materials all methods | Waste not Diverted | Total Diverted + Landfilled lbs | |||||||||||
| Reuse | Recycle | Compost | Estimate % of each material diverted | Vendor / Facility | Landfill | Estimate % of landfill material | Diverted lbs | Vendor / Facility | Landfilled lbs | |||||||
| Asphalt | ||||||||||||||||
| Concrete | ||||||||||||||||
| Soil, Rock, Land Clearing Debris | ||||||||||||||||
| Cardboard | ||||||||||||||||
| Carpet, Padding/Foam | ||||||||||||||||
| Brick, Masonry, and Tile | ||||||||||||||||
| Metals | ||||||||||||||||
| Sheetrock (not painted) | ||||||||||||||||
| Clean Wood | ||||||||||||||||
| Ceiling tile | ||||||||||||||||
| Painted wood, painted drywall, plywood | 0 | |||||||||||||||
| Reusable items | (complete Reuse List below) | |||||||||||||||
| Roofing | ||||||||||||||||
| Other Debris: Controllers | ||||||||||||||||
| Other Debris: | ||||||||||||||||
| Other Debris: | ||||||||||||||||
| Total: | 0 | 0 | 0 | 0 |
| Reuse List: Reusable items such as cabinets, built-ins, framing lumber, siding, etc. are encouraged to be reused on-site or off-site. Please list accordingly. | |||
| Item | Use location | Off-Site Benefactor or Deconstruction Company | |
| On-site | Off-site | ||
| On-site | Off-site | ||
| On-site | Off-site | ||
| On-site | Off-site | ||
| On-site | Off-site |
| Weight Conversion Factors |
| Use the following conversion factors to help you with your estimated diversion for the Waste Diversion Plan. The Waste Diversion Report is a record of your actual diversion and disposal. The Waste Diversion Report and receipts from landfills, processing facilities, and recyclers must be available for review at project close-out. |
| Asphalt paving, crushed = 1,380 lbs / cubic yard | Concrete , scrap, loose = 1,855 lbs / cubic yard |
| Asphalt/shingles comp, loose = 418.5lbs / cubic yard | Earth, loose = 2,052 lbs / cubic yard |
| Brick, laid flat = 20 lbs/square foot flat | Fiberglass insulation, loose = 17lbs / cubic yard |
| Brick, loose = 120 lbs / cubic foot, 3,200 lbs / cubic yard | Sheetrock scrap , loose = 393.5 /cubic yard |
| Ceramic tile, scrap , loose = 1,214 lbs / cubic yard | Rock, crushed = 2,570 lbs / cubic yard |
mailto:christopher.cahoon@gsa.gov Instructions
| Instructions |
| If you are completing this Worksheet, fill in the Waste Diversion Plan (pink-shaded) portion of the document prior to starting your project and the Waste Diversion Report (green shaded) portion of the document prior to final inspection. The following descriptions, resources, and examples will help you complete the Worksheet. |
-- Material: Typical construction debris types are listed in the column labeled “Material”. If you have a significant quantity of a material that is not listed, use “Other Debris” and specify material. Hazardous materials are exempt from diversion.
-- Anticipated Diversion: Insert an X under the appropriate column (“Reuse”, “Recycle”, or “Compost”) depending on how you plan on diverting the type of debris listed. For example, sheetrock scrap can be broken down and reused as a soil amendment on-site, in which case you would enter an X for compost. More than one use can apply. If the material listed is not a debris type on your site, enter an NA
-- Estimated % of Each Material Diverted: Estimate the percent of the total of each material type that you plan to divert. For example, under Brick, Masonry and Tile, you may have brick that you plan to reuse on-site, but need to dispose of old tile flooring and mortar bed. If you estimated brick as half of the combined total of the material type Brick, Masonry and Tile, then you would enter “50%” in the estimated per centage in the Waste column.
-- Vendor/Facility: Enter the anticipated vendor or facility that will be receiving your diverted debris. If you are reusing a material on-site, enter “on-site”. To find vendors that recycle specific C&D materials as well as processing facilities that accept mixed C&D materials consult the local state vendor directoy lists.
-- Anticipated Waste: Enter an X under “Landfill” for materials to be landfilled even if only a portion of the material will be landfilled.
-- Estimated % of Landfill Material: Estimate the percent of the total of each material type that you plan to landfill.
-- Diverted Pounds: Enter the total number of pounds for the material category actually diverted. This should include the weight of the specific material type reused, recycled, and composted. Conversion tables below can be used to estimate weight if receipts are in cubic yards.
-- Vendor/Facility: Enter the actual vendor or facility that received your diverted debris. If more than one vendor is used, enter both. If you are reusing a material on-site, enter “on-site”. Save receipts from each vendor.
-- Actual Waste not diverted: .Enter the total number of pounds for the material category not diverted.
-- Vendor/Facility: Enter the actual vendor or facility that received your diverted debris. If more than one vendor is used, enter both. If you are reusing a material on-site, enter “on-site”. Save vendor receipts.
-- Actual Waste: No more than 50% of the combined total of materials of construction waste should be sent to landfill.
-- Total Diverted + Landfilled lbs
-- Diversion Rate: At the bottom of column K, enter the sum of the diverted items. In Column N enter the sum of the waste items. Divide the total amount diverted (K) by the total debris (K+N) and multiply by 100 to get your diversion percentage. (K/(K+N))x100=diversion%