Remediation Services at Operable Units (OUs) 5 (Shore Road) and 6 (Morgan Francis) at the Raymark Superfund Site in Stratford, CT
Solicitation number
W912WJ25R0001
Issued by

About this file

This file is a binding rates template spreadsheet for the Callahan Mine Superfund Site IDIQ/RAC contract (Solicitation W912WJ-17-R-0005). The template contains markup tables for home office and field office labor rates, as well as binding rate tables for key personnel positions across five years of performance. The key personnel positions include Program Manager, Project Manager, Site Superintendent, Site Safety & Health Officer, Contractor Quality Control System Manager, Project Chemist, and Project Engineer.

The template is structured to capture direct rates, overtime rates, combined markup percentages, and total burdened rates for both home office and field office work. The markup section includes fields for Fringe, Overhead, and G&A percentages. The template shows $1.00 placeholder direct rates and 0% markup values, indicating this is a blank form to be completed by contractors. Years 3-5 specifically note 0% annual escalation rates.

View the file

Other files

File Type Posted
Amendment 0010.pdf PDF
Amendment 0009.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006 - Spec Section 01 35 29 Revision 2.pdf PDF
Amendment 0006 - Drawing C-106 Revision 2.pdf PDF
Amendment 0006 - Revised Spec Section 31 23 20.pdf PDF
Amendment 0006 - Revised Spec Section 31 23 00.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004 - OU3 Remedial Investigation Report (Vol 1 of 3).pdf PDF
Amendment 0004 - Revised Spec Section 01 35 29.pdf PDF
Amendment 0004 - Revised Seed Task Order PWS.pdf PDF
Amendment 0004 - Final Raymark PDI Report.pdf PDF
Amendment 0004 - Past Performance Questionnaire.pdf PDF
Amendment 0004.pdf PDF
Amendment 0004 - Revised Drawing C-106.pdf PDF
Amendment 0004 - Updated Bid Schedule.pdf PDF
Amendment 0004 - OU6 Final Remedial Investigation Report (Vol 1 and 2).pdf PDF
Amendment 0004 - WSP Raymark MF SIR.pdf PDF
Amendment 0004 - OU3 Remedial Investigation Report (Vol 2 of 3).pdf PDF
Amendment 0003.pdf PDF
Amendment 0003 - Site Visit Map.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Drawings.pdf PDF
Bid Schedule.docx DOCX document
W912WJ25R0001.pdf PDF
Specifications.pdf PDF
PWS - IDIQ.pdf PDF
Binding Rates Table.xlsx XLSX spreadsheet
PWS - Seed Task Order.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Markups

Binding Rates for Prime Contractor
Prime Contractor Name:
Document:Appendix I-1/Mark-up Development
HOME OFFICE LABOR
Markup Type (Provide Description)%
Fringe0.00%
Overhead0.00%
G&A0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
Combined Markup for home office0.00%
FIELD OFFICE LABOR
Markup Type (Provide Description)%
Fringe0.00%
Overhead0.00%
G&A0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
Combined Markup for field office/site work0.00%

&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Solicitation Number: W912WJ-17-R-0005 &D

Year 1

Binding Rates for Key PersonnelBase Year 1
Prime Contractor Name:
Document:
Home OfficeHome Office OTField OfficeField Office OT
Government Job TitleContractor Job TitleUnitDIRECT RATE $DIRECT RATE (OT) $Combined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATE
Program ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site SuperintendentHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site Safety & Health OfficerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Contractor Quality Control (CQC) System ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ChemistHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project EngineerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -

&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 2

Binding Rates for Key PersonnelYear 2Annual Escalation
Prime Contractor Name:
Document:
Home OfficeHome Office OTField OfficeField Office OT
Government Job TitleContractor Job TitleUnitDIRECT RATE $DIRECT RATE (OT) $Combined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATE
Program ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site SuperintendentHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site Safety & Health OfficerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Contractor Quality Control (CQC) System ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ChemistHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project EngineerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -

&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 3

Binding Rates for Key PersonnelYear 3Annual Escalation0%
Prime Contractor Name:
Document:
Home OfficeHome Office OTField OfficeField Office OT
Government Job TitleContractor Job TitleUnitDIRECT RATE $DIRECT RATE (OT) $Combined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATE
Program ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site SuperintendentHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site Safety & Health OfficerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Contractor Quality Control (CQC) System ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ChemistHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project EngineerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -

&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 4

Binding Rates for Key PersonnelYear 4Annual Escalation0%
Prime Contractor Name:
Document:
Home OfficeHome Office OTField OfficeField Office OT
Government Job TitleContractor Job TitleUnitDIRECT RATE $DIRECT RATE (OT) $Combined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATE
Program ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site SuperintendentHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site Safety & Health OfficerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Contractor Quality Control (CQC) System ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ChemistHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project EngineerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -

&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 5

Binding Rates for Key PersonnelYear 5Annual Escalation0%
Prime Contractor Name:
Document:
Home OfficeHome Office OTField OfficeField Office OT
Government Job TitleContractor Job TitleUnitDIRECT RATE $DIRECT RATE (OT) $Combined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATECombined Markup %TOTAL BURDENED RATE
Program ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site SuperintendentHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Site Safety & Health OfficerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Contractor Quality Control (CQC) System ManagerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project ChemistHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -
Project EngineerHour$ 1.000.00%$ 1.000.00%$ -0.00%$ 1.000.00%$ -

&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Pick List

Task 1
Task 2
Task 3a
Task 4
Task 3b Initial
Task 3b Final