This document is a Performance Work Statement (PWS) for a Remediation Services Contract Task Order at the Raymark Superfund Site in Stratford, Connecticut. The PWS describes the scope of work for remediating two Operable Units (OUs) - OU3 (Upper Upper Ferry Creek) and OU6 (Morgan Francis). The key objectives include excavating contaminated soil and sediment, transporting and consolidating the material at the OU6 site, installing an engineered RCRA cap at OU6, and restoring the sites. Major tasks include site mobilization, preparing plans, implementing erosion and dust controls, performing excavation and soil sampling, and completing a final remedial action report. The performance period is 12 months, and the contract type is Firm Fixed Price. Key requirements address environmental protection, health and safety, quality control, data management, and stakeholder coordination. The PWS references the related federal contract opportunity, which is for the remediation of OU5 (Shore Road) and OU6 (Morgan Francis) at the Raymark Superfund Site.

View the file

Other files

File Type Posted
Amendment 0010.pdf PDF
Amendment 0009.pdf PDF
Amendment 0009 - Revised Binding Rates Table.xlsx XLSX spreadsheet
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006 - Spec Section 01 35 29 Revision 2.pdf PDF
Amendment 0006 - Drawing C-106 Revision 2.pdf PDF
Amendment 0006 - Revised Spec Section 31 23 20.pdf PDF
Amendment 0006 - Revised Spec Section 31 23 00.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004 - OU3 Remedial Investigation Report (Vol 1 of 3).pdf PDF
Amendment 0004 - Revised Spec Section 01 35 29.pdf PDF
Amendment 0004 - Final Raymark PDI Report.pdf PDF
Amendment 0004 - Past Performance Questionnaire.pdf PDF
Amendment 0004.pdf PDF
Amendment 0004 - Revised Drawing C-106.pdf PDF
Amendment 0004 - Updated Bid Schedule.pdf PDF
Amendment 0004 - OU6 Final Remedial Investigation Report (Vol 1 and 2).pdf PDF
Amendment 0004 - WSP Raymark MF SIR.pdf PDF
Amendment 0004 - OU3 Remedial Investigation Report (Vol 2 of 3).pdf PDF
Amendment 0003.pdf PDF
Amendment 0003 - Site Visit Map.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Drawings.pdf PDF
Bid Schedule.docx DOCX document
W912WJ25R0001.pdf PDF
Specifications.pdf PDF
PWS - IDIQ.pdf PDF
Binding Rates Table.xlsx XLSX spreadsheet
PWS - Seed Task Order.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement For Remediation Services Contract

Task Order No. 1 (Seed)

Morgan Francis Raymark Superfund Site Stratford, Connecticut

15 November 2024

For Remediation Services Contract

Task Order No. 1 (Seed)

Morgan Francis Raymark Superfund Site Stratford, Connecticut

TABLE OF CONTENTS

1.0 Background

2.0 Contract Procurement Objectives and Overview

3.0 Contract Type

4.0 Task Order 1 (Seed Task Order) - Performance Objectives and Standards

5.0 Seed Task Order Description & Design Documents

5.1 Task 1 – General Conditions

5.1.1 Task 1.1 – Project Management/Project Controls

5.1.2 Task 1.2 – Prepare Plans

5.1.2.1 Task 1.2.1 – Project Management Plan

5.1.2.2 Task 1.2.2 – Construction Work Plan (CWP)

5.1.2.3 Task 1.2.3 – Health and Safety Documentation

5.1.2.4 Task 1.2.4 – Sampling and Analysis Plan and Quality Assurance Project Plan

5.1.3 Task 1.3 – Site Mobilization and Preparation

5.1.4 Task 1.4 – Temporary Facilities

5.1.5 Task 1.5 – Environmental Protection

5.1.6 Task 1.6 – Survey

5.1.7 Task 1.7 – Site Demobilization

5.2 Task 2 – Remediation & Restoration of OU3 and OU6 Properties

5.3 Task 3 – Completion of OU6 - Morgan Francis Cap

5.4 Task 4 – Prepare Completion Reports

6.0 Additional Requirements

6.1 Environmental Protection Requirements

6.2 Sustainability Requirements

6.3 Protection of Property

6.4 Health and Safety Requirements

6.5 Sampling and Analysis Quality Control

6.5.1 Analytical Testing

6.5.2 Sample Data Review/Validation and Reporting

6.5.3 Data Management

6.5.4 Geotechnical Testing

6.6 Regulatory Involvement

6.7 Project Stakeholders

6.8 Deliverable Requirements

6.8.1 Mailing Requirements

6.8.2 Late Submittals

6.8.3 Submittal Format

6.8.4 Meeting Notes

6.9 Expertise and Related Personnel

6.10 Travel

6.11 Rights of Entry

6.12 Engineering Support

6.13 Contractor Furnished Resources

6.14 Government Rights

6.15 Stop Work Authority

6.16 Project Repository and Administrative Record

6.17 Government Furnished Resources

7.0 Government Support

8.0 Travel and Meetings

9.0 Manifesting, Transportation, and Disposal Requirements

10.0 Public Relations

11.0 Physical Security

12.0 Warranty of Construction

13.0 AT-OPSEC Requirements

For Remediation Action Contract

Morgan Francis Raymark Superfund Site Stratford, Connecticut

1.0 Background

The Raymark Industries, Inc. Superfund Site (the “Site”) includes areas that have been contaminated as a result of manufacturing processes from the former Raymark Industries, Inc. facility. The former Raymark Facility, which was located at 75 East Main Street in Stratford, Connecticut, operated from 1919 to 1989. Known as Raybestos- Manhattan, Inc., Raymark manufactured gaskets, clutches and heavy brake friction components for the automotive industry. Raymark generated wastes containing asbestos, lead, copper, polychlorinated biphenyls (PCBs) and a variety of solvents, adhesives, and resins as byproducts of its manufacturing operations. The resultant byproducts were available as “free fill” to the Town and residents. The Raymark waste that remains in the town of Stratford presents a threat to human health that needs to be addressed.

U.S. Environmental Protection Agency (US EPA) approved two Record of Decisions (ROD) and one Explanation of Significant Differences (ESD) that specified the selected remedies for the subject properties at the Raymark Superfund Project located in the town of Stratford, Connecticut. The relevant ESD and RODs are titled:

• RAYMARK INDUSTRIES, INC. SUPERFUND SITE RECORD OF DECISION FOR FINAL

SOURCE CONTROL ACTIONS AT FOUR PROPERTIES WITHIN OPERABLE UNIT 6

(ADDITIONAL PROPERTIES) AND INTERIM ACTIONS AT OTHER LOCATIONS

CONTAINING RAYMARK WASTE, dated July 2011

• RAYMARK INDUSTRIES, INC. SUPERFUND SITE RECORD OF DECISION FOR FINAL

REMEDY AT OPERABLE UNIT 2 (GROUNDWATER), INCLUDING VAPOR MITIGATION

ACTIONS; AND FINAL SOURCE CONTROL ACTIONS FOR OPERABLE UNIT 3 (UPPER

FERRY CREEK), OPERABLE UNIT 4 (RAYBESTOS MEMORIAL FIELD), OPERABLE

UNIT 6 (ADDITIONAL PROPERTIES) AND MODIFICATION TO THE OU1 REMEDY,

dated September 2016

• EXPLANATION OF SIGNIFICANT DIFFERENCES RAYMARK INDUSTRIES, INC.

SUPERFUND SITE OPERABLE UNITS 4 AND 6, dated September 2023

The general scope of work for this task order involves the remediation of OU3 (Upper Upper Ferry Creek) & OU6 (Morgan Francis). See site figure 1 below for reference.

Contaminated soil and sediment will either be transported to OU6 Morgan Francis for consolidation or sent off-site for disposal. The contractor shall be responsible for all transport and disposal (T&D) activities whether disposal is at the OU6 Morgan Francis site or off-site. The work involves managing, coordinating, and implementing all remedial efforts at the properties during the excavation, restoration, consolidation, and capping activities. The contractor shall be responsible for establishing and implementing all stormwater management activities. The contract also involves the installation of an engineered cap at OU6 Morgan Francis upon completion of all excavation and consolidation activities.

Figure 1 Site Location Map

OU6 – Morgan Francis The portion of the Site consisting of the former Morgan Francis property encompasses approximately 5.7 acres and formerly consisted of two (2) separate parcels, 576 and 600 East Broadway, but the boundary for 576 East Broadway parcel has been vacated and now the entire Morgan Francis property is recorded as 576 East Broadway and owned by the Town of Stratford. The Morgan Francis property is currently primarily heavily vegetated. During operations, waste generated from the Raymark facility (referred to as Raymark Waste) was deposited at the Morgan Francis property as fill material. Through the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process, Raymark Waste was defined as soil containing lead above 400 parts per million (ppm) and asbestos (chrysotile only) greater than 1%, and either copper above 288 ppm or polychlorinated biphenyls (Aroclor 1268 only) above 1 ppm. An estimated 44,000 cy of Raymark Waste is buried at the Morgan Francis property.

The former separate 576 East Broadway parcel was approximately 1.4 acres of Light Industrial District, MA zoned land. Located in Stratford, Connecticut, this property contains two connected buildings. The buildings are vacant and reportedly consist of a former wood shop and a warehouse. A portion of existing building is dilapidated with the 1-story wood framed portion close to collapse. There is an asphalt parking lot adjacent to the buildings. The buildings currently occupy approximately 3,000 square ft while the existing asphalt parking lot occupies approximately 0.3 acres. A chain-link fence runs along the northern, western, and southern edges of the pavement area, separating the buildings and existing pavement from the wooded area of the property. These buildings and related infrastructure will be demolished as part of the remedial activities.

A tributary of Tanner Creek is located just off the northwest end of the property and enters UUFC, located on the northeastern property line adjacent to the 335 Ferry Boulevard parcel. The undeveloped former separate 600 East Broadway parcel is located to the west of the 576 parcel. The former separate 576 parcel is generally flat with a slight downward slope to the northwest, toward Ferry Creek and away from East Broadway. No known stormwater drain inlets are in the parking lot. The fill on this parcel consists of both soil and manmade materials comprised predominantly of sand, silt, gravel, and manmade debris including Raymark Waste, typically loose to medium dense in terms of relative density. The fill thickness ranges from about two (2) to 17 ft across the parcel. The manmade materials include the following: presumed asbestos containing material (PACM) (fibrous asbestos mats and pads), asphalt, brake pads, brick, cinders, coal, concrete, gasket material, glass, metal debris, plastic, steel, and tiles. Raymark Waste found in manmade fill materials on this parcel contains asbestos, lead, copper and/or Aroclor 1268. Raymark Waste is not visible on the surface at this property.

The former 600 East Broadway parcel was approximately 4.3 acres of MA Light Industrial zoned land. From 1948 until sometime in the 1970s, this property was occupied by the Morgan Francis Flagpole Company. Beginning in the late 1980s, this property was an active industrial waste disposal area. Currently, the property is undeveloped and overgrown with heavy vegetative growth. The fill on this property consists of both natural and manmade materials. The manmade materials include the following: PACM (fibrous asbestos mats and pads), asbestos fibers, asphalt, brake pads, brick, cinders, broken rock, concrete, glass, metal debris, nails, roofing shingles, rubber soles, slag, and wood. These materials were discovered with natural fill consisting of sand, silty sand and sand-silt mixtures, gravelly silty sand, and sand and gravel. Raymark Waste found in fill materials on this property contains asbestos, lead, copper and/or Aroclor 1268.

OU3 – Ferry Creek The portion of OU3 for this project consists of the uppermost portion of Ferry Creek known as Upper Upper Ferry Creek (UUFC) and adjacent wetlands where Raymark Waste was deposited through placement of fill, overland runoff, or surface water transport. OU3 extends from the outlet of a culvert at I-95 downstream for approximately 2,500 ft to the Broad Street Bridge. Ferry Creek is tidally influenced, and flow can be restricted and/or controlled by flood gates and a pumping station located at the Broad Street Bridge. The approximate 600-foot (ft) portion of Upper Ferry Creek, located between Ferry Boulevard and I-95 is included in this project and is referred to as UUFC.

The UUFC includes the Tanner Creek Tributary. UUFC is surrounded by historically identified areas of Raymark Waste, including the Morgan Francis property and the vacant lot abutting I-95.

2.0 Contract Procurement Objectives and Overview

No information for this task order.

3.0 Contract Type

This task order is fixed price. All tasks on this task order are considered service tasks.

4.0 Task Order 1 (Seed Task Order) - Performance Objectives and Standards

This Task Order PWS is for a results-based contract with intent to successfully complete all performance objectives shown in Table 1. All tasks will be Firm Fixed Price (FFP). The Period of Performance for this task order will be twelve months from task order award. The Contractor shall furnish all labor, materials and equipment necessary to successfully complete all performance objectives identified in this PWS and Table 1, Performance Requirements Summary. Achievement of the performance objectives is successfully attained upon the finalization of appropriate documentation certifying that the documents have been accepted by the USACE. USACE approval of the Performance Standards will be by the KO or Contracting Officer’s Representative

(COR).

Table 1 – Performance Requirements Summary Performance Objective/Task Performance Standard

Task 1 – General Conditions Task 1.1 - Project Management/Project Controls

Submit Monthly Status Reports and Vouchers by 5th day of each month in accordance with program requirements and USACE acceptance

Task 1.2 – Prepare & Submit Plans Task 1.2.1 – Project Management Plan in accordance with Paragraph 5.1.2.1.

USACE acceptance of Final Project Management Plan

Task 1.2.2 – Construction Work Plan in accordance with Paragraph 5.1.2.2 and the Specifications.

USACE approval of Final Construction Work Plan.

Task 1.2.3 – Health and Safety Documentation in accordance with Paragraph 5.1.2.3 and the Specifications.

USACE approval of Final APP/SSHP

Task 1.2.4 – Sampling and Analysis Plan (SAP) and Quality Assurance Project Plan (QAPP) in accordance with Paragraph 5.1.2.4 and the Specifications.

USACE approval of Final SAP/QAPP

Task 1.3 – Site Mobilization and Site Preparation – Establish Work Surfaces, Staging Areas, Ecological Resources Protection, Security, Dust Control, and Surface Water Management.

Complete Site Mobilization and Site Preparation in accordance with approved CWP to achieve stable, safe, and protective work areas and accurate horizontal and vertical control for future data collection.

Task 1.4 – Temporary Facilities – Provide project trailers, electrical and communication services, and portable toilets.

Provide temporary facilities necessary to execute the work in accordance with all approved plans.

Task 1.5 – Environmental Protection in accordance with the Specifications and NHPA Compliance.

Establish and maintain sedimentation and erosion control measures and other environmental protection measures in accordance with all approved plans to achieve maximum protection of environmental resources and avoid disruption of work. USACE approval of Final Pre & Post-Construction Digital Photo Documentation.

Task 1.6 – Survey – Provide all survey requirements in accordance with the Specifications.

USACE approval of Final Survey As-built drawings and Environmental Land Use Restriction (ELUR) surveys.

Task 1.7 – Site Demobilization Demobilize remaining materials and equipment from the Site in accordance with the Work Plan.

Task 2 – Remediation & Restoration of OU3 and OU6 Properties – Completion of Remediation and Restoration at OU3 and OU6 (Morgan Francis) in accordance with the Drawings, Specifications, and Approved Plans from Task 1.

USACE approval of remediation and restoration at the following OU3 and OU6 Properties:

• OU3 - Ferry Creek from Ferry Boulevard to I-95

• OU6 – Morgan Francis

Task 3 – Completion of OU6 - Morgan Francis Cap – Completion of the Cap at OU6 – Morgan Francis in accordance with the Drawings, Specifications, and Approved Plans from Task 1.

USACE approval of interim and final cap.

Table 1 – Performance Requirements Summary Performance Objective/Task Performance Standard

Task 4 – Prepare Completion Report - Final Completion Report shall include summary of work completed, geotechnical results, analytical results, as-built drawings and an evaluation of the effectiveness of slope stabilization, capping, and waste rock exposure measures.

USACE approval of Final Completion Report.

In the event that there may be multiple milestones and/or deliverables for each of the performance objective tasks, partial payments will be based on the successful completion of milestones. Final decisions regarding the adequacy of milestone and deliverable completion resides with the KO or COR.

The Contractor shall furnish all necessary labor, equipment, materials, and supplies to complete the tasks listed in Table 1 above and defined in the following paragraphs. All work shall be conducted in a safe, secure, cost efficient, and environmentally acceptable manner in accordance with the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), the relevant Record of Decisions, and EPA green and sustainability principles. Work shall be completed correctly in a professional, workmanlike manner, in accordance with approved work plans. Work is to be performed commensurate with the level of effort and quality intended, with appropriately qualified quality control (QC) representation (as part of the contractor’s overall QC Program) controlling the work.

Contractor Quality Control (CQC) is the means by which the Contractor ensures that the work, to include that of subcontractors and suppliers, complies with the requirements of the contract. The control shall be adequate to cover all operations, including both on-site and off-site activities. The Contractor is responsible for quality control and shall establish and maintain an effective quality control system. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product that complies with governing regulations and contract task order requirements.

The Contractor's quality control program shall include inspections and tests as described in the task orders.

5.0 Seed Task Order Description & Design Documents

The general scope of work for the Seed Task Order involves the excavation of Raymark waste contaminated soils and sediments from two operable units (OUs) of the Raymark Superfund Project (OUs 3 & 6). Contaminated soil and sediment will either be transported to the OU6 Morgan Francis consolidation area or sent off-site for disposal.

The contractor shall be responsible for all transport and disposal (T&D) activities whether disposal is at the OU6 Morgan Francis site or off-site. The work involves managing, coordinating, and implementing all remedial efforts at the properties during the excavation, restoration, consolidation, and capping activities. The contractor shall be responsible for establishing and implementing all stormwater management activities.

The contract also involves the installation of an engineered cap at OU6 Morgan Francis upon completion of all excavation and consolidation activities.

The contractor shall be responsible for not only excavating contaminated soil and sediment, but also developing and implementing a robust soil and sediment sampling and characterization program to assure all Raymark waste is removed laterally and to the record of decision (ROD) prescribed depth limits. The contractor will also be responsible for site restoration.

Details of the work on the Seed Project shall include, but are not limited to:

• Preconstruction Soil Sampling

• Clearing and grubbing

• Interim cover system

• Installation of erosion and sedimentation controls

• Construction of laydown areas and decontamination pads

• Excavation and fill

• Confirmatory Soil Sampling

• Transportation and disposal of hazardous materials

• Topsoil and seed

• Site restoration

• Traffic Management and Air Monitoring

• Monitoring well preservation and abandonment

All work under this Task Order shall be completed in accordance with this PWS and the Morgan Francis Remediation Drawings and Specifications. The Drawings and Specifications are attached to this PWS and are titled as follows:

• Morgan Francis Remediation Raymark Superfund Site Stratford, Connecticut Construction Solicitation and Specifications, September 2024, Prepared by WSP (Specifications)

• Remedial Design Drawings Morgan Francis Consolidation Area Cap (OU6) and Upper Upper Ferry Creed Remediation (OU3) Raymark Industries Superfund Site Stratford, Connecticut, September 2024, Prepared by WSP (Drawings)

The Contractor shall perform all the necessary services required to successfully meet all performance objectives of this PWS. The Contractor shall comply with all applicable Federal, State, and local laws and regulations in order to successfully complete all performance objectives of this PWS in a manner that is consistent with any applicable orders and permits and relevant Department of Defense (DOD) and Army policies for the duration of this Task Order. The Contractor shall also use the references listed below (and default to most recent version if different) and references listed in the Specifications when preparing the proposal and executing the work:

• EPA New England Region 1 – Raymark Industries, Inc. Superfund Site – Record of Decision, Stratford, Connecticut dated September 2016;

• Raymark Superfund Site –Final OU3 Feasibility Study Stratford, Connecticut – Remedial Investigation/Feasibility Study dated June 29, 2016 – Nobis Engineering, Inc.

• Raymark Superfund Site –Final OU6 Feasibility Study Addendum, Stratford, Connecticut – Remedial Investigation/Feasibility Study dated June 28, 2016 – Nobis Engineering, Inc.

• Engineer Manual (EM) 1110-1-4007 Safety and Health Aspects of Hazardous, Toxic, and Radioactive Waste Remediation Technologies, USACE, 2024.

• EM 200-1-3, Requirements for the Preparation of Sampling and Analysis Plans, USACE, 01 Feb. 2001

• ER 1110-1-263, Chemical Data Quality Management for Hazardous, Toxic, Radioactive Waste Remedial Activities, USACE, 30 Apr 1998

• EM 200-1-6, Chemical Quality Assurance for HTRW Projects, USACE, 10 Oct.

• DOD Quality Systems Manual (QSM), for Environmental Laboratories, Revision

5.0 dated July 2013

• Uniform Federal Policy for Quality Assurance Project Plans (UFP for QAPP), Evaluating, Assessing and Documenting Environmental Data Collection and Program Use, Part 1 and Part 2, Final version 1, March 2005

• Intergovernmental Data Quality Task Force Uniform Federal Policy for Quality Assurance Project Plans Optimized UFP-QAPP Worksheets.

www.epa.gov/fedfac. DoD/EPA/DOE, March 2012

• EPA New England Environmental Data Review Program Guidance. Version 4- 22-2013

• DoD General Data Validation Guidelines Final Draft, Environmental Data Quality Workgroup, December 2016

• National Functional Guidelines for Superfund Organic Methods Data Review.

EPA-540-R-2016-002

• National Functional Guidelines for Superfund Inorganic Methods Data Review.

EPA-540-R-2016-001

• ER1180-1-6, Construction Quality Management, USACE, 30 Sep 1995

• EM 385-1-1 U.S. Army Corps of Engineers Safety and Health Requirements

Manual (2008)

• EM 1110-1-4000, Monitoring Well Design, Installation, and Documentation at

Hazardous Toxic, and Radioactive Waste Sites, USACE, Dated November 1, 1998.

• 42 U.S. Code Chapter 103 – Comprehensive Environmental Response, Compensation, and Liability.

• EQASOP-GW 0001, Low Stress (low flow) Purging and Sampling Procedure for the Collection of Groundwater Samples from Monitoring Wells, prepared by USEPA Region 1, dated July 30, 1996, revised January 19, 2010.

• ER 1110-1-8157, Engineering and Design Geotechnical Data Quality Management for Hazardous Waste Remedial Activities, 2002.

• EM 1110-1-1804 Geotechnical Investigations, Engineering and Design, 2001.

http://www.epa.gov/fedfac

• EM 1110-1-1802 Geophysical Exploration for Engineering and Environmental Investigations, 1995.

• EM 1110-2-1902, Slope Stability, USACE, 31 October 2003.

• United States Environmental Protection Agency, 2006. Guidance on Systematic

Planning Using the Data Quality Objectives Process (EPA QA/G-4). Published by the Office of Environmental Information.

• U.S. Department of the Interior, Bureau of Reclamation, Engineering Geology Field Manual, Second Edition, Volumes I and II, 1998, Reprinted 2001.

• U.S. Department of the Interior, Bureau of Reclamation, Earth Manual, Third Edition, Volumes I and II, 1998.

• Applicable ASTM Standards

5.1 Task 1 – General Conditions

5.1.1 Task 1.1 – Project Management/Project Controls

This task provides for oversight of the below activities to include the Program Manager, Project Manager, Subcontracts Manager, Project Controls, Cost Scheduler, and Administrative staff when engaged in representative non-site specific activities.

• Cost and schedule reporting and tracking.

• Subcontractor cost and schedule reporting and tracking.

• Program resource planning selection and resource conflict resolution.

• Participation by the Project Manager and Site Superintendent in monthly conference calls with USACE, EPA, Town of Stratford Health Department, and subcontractors; weekly conference calls during field construction.

• Contract basis review, verification, and tracking of invoices to ensure conformance to applicable contract requirements.

• Preparation of monthly invoices.

• Preparation of daily update on field activities via e-mail.

• Preparation of weekly field update on field activities via e-mail.

5.1.2 Task 1.2 – Prepare Plans

The contractor shall prepare all plans as required by this PWS and the contract specifications.

5.1.2.1 Task 1.2.1 – Project Management Plan

The Contractor shall develop and maintain a detailed Project Management Plan (PMP). The PMP will specify the schedule, execution, and completion of the performance objectives. The first draft PMP shall be submitted within 30 calendar days of contract award. The draft PMP and subsequent revisions will be subject to USACE review and approval through the COR. The final PMP will be due within fifteen (15) calendar days of comments received from the COR. Assume a Draft, Draft Final, and Final PMP. A payment milestone will be established for USACE’s approval of the final PMP through the COR.

As part of the PMP, the Contractor will develop and maintain an activity-based schedule that fully supports the technical approach and outlines the due dates for all milestones and payable deliverables. The schedule shall be in Gantt format created using MS Project or similar scheduling software. The comprehensive Gantt schedule shall begin with one Project Start milestone, end with one Project Finish milestone, and predecessors and successors for each activity (including milestones) shall be clearly identified via relationship arrows. The schedule shall include Government review periods. Critical path activities shall be displayed in red. Displayed activity data shall include Activity ID, Activity Description, Start, Duration, Finish and Total Float. A payment plan will be included with the schedule that allows for payments to the Contractor based on successful completion of interim milestones proposed by the Contractor. It is the Army’s intent to make all payments after verification of progress in accordance with this schedule. As part of the PMP, the Contractor will identify and implement a means for providing project monthly status reports to the COR. The PMP will address the content of status reports.

The Final PMP for USACE approval shall be submitted within 60 days of award.

5.1.2.2 Task 1.2.2 – Construction Work Plan (CWP)

The Contractor shall prepare a draft, draft-final and final construction work plan prior to the commencement of any work on the project site. The Construction Work Plan (CWP) shall contain, but not be limited to, the following:

• Statement of the work to be accomplished including a statement of Data Quality Objective(s);

• Discussion on implementation of the project including the method of operation, type of equipment, personnel required, and other special considerations for the tasks required under the task order.

• A copy of the schedule detailing the work to be performed with key project milestones as described under Section 6.2.1 Task 2.1 Project Management Plan.

• Permits, licenses, access agreements, and certificates required;

• Key personnel to be used on the project along with their roles and responsibilities;

• Site-specific assumptions and clarifications;

• Logs, reports, and record keeping to be utilized.

Assume internal draft, regulatory draft, draft final and final versions will be required with Response to Comments (RTCs) and response to comments letters (RCL) by the Contractor. Contractor shall assume a minimum of 10 business days for each Government review phase. Acceptance of the Contractor's work plan by the Government is required prior to any field mobilization. Acceptance is conditional and will be predicated on satisfactory performance during field activities. Deviations or proposed changes to the approved work plan shall be submitted to the USACE’s PM and COR for review, comment, and approval. The Government reserves the right to require the Contractor to make changes in his work plan and operations as necessary. During execution of the task order, the Contractor shall follow the approved work plan.

The CWP for USACE approval shall be submitted within 60 days of award.

5.1.2.3 Task 1.2.3 – Health and Safety Documentation

The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities to be performed. The documentation shall include an Activity Hazard Analysis (AHA) for each phase of work as described below. All work shall be conducted in accordance with the APP, the U.S. Army Corps of Engineers Safety and Health requirements Manual (EM 385-1-1, most recent edition), and all applicable federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at Headquarters USACE website under publications using the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf

The APP shall detail how safety and health will be managed during the project. The APP shall address the requirements of applicable Federal, State and local safety and health laws, rules, and regulations. The Contractor shall comply with Federal Acquisition Regulation Clause No. 52.236-13 for Accident Prevention, which is added by reference. The APP shall be developed by a qualified person. The contractor shall be responsible for documenting the qualified person’s credentials. Work shall not proceed until the APP has been reviewed by the Government Designated Authority (GDA) and deemed acceptable for use on the project.

The contractor shall prepare a Site Health and Safety Plan (SSHP) that complies with the minimum requirements outlined in identified in EM385-1-1, Section 36-7. Minimum Plan Requirements. The SSHP shall be attached to the APP as an Appendix. SSHP elements adequately covered elsewhere in the APP need not be duplicated in the SSHP.

https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf

The APP shall interface with the Contractor's overall safety and health program. Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

The Contractor shall conduct a safety meeting at the project site on the first day of work, and whenever a new activity or phase of work begins. All safety meetings shall be documented. Records of the safety briefings shall be submitted to the GDA weekly.

Activity Hazard Analysis (AHA)

An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work shall not proceed on a phase of work until the AHA has been accepted by the GDA. A preparatory meeting shall be conducted by the contractor to discuss the AHA contents with all engaged in the activity. The preparatory meeting shall be conducted by the prime contractor and shall include all subcontractors and Government on-site representatives. The AHA shall be continuously reviewed and revised to address changing site conditions or operations as appropriate.

Accident Reporting

All accidents and near misses shall be investigated by the Contractor. All work-related injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the GDA within 4 hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D. shall be immediately reported to the GDA. ENG Form 3394 shall be completed and submitted to the GDA within five working days of the incident.

The Contractor shall complete the “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (for prime and its subcontractors) and forward the completed form to the GDA no later than close of business on the 10th calendar day of the following month. The form shall be transmitted by the prime contractor to the GDA electronically.

The APP for USACE’s approval shall be submitted within 60 days of award.

5.1.2.4 Task 1.2.4 – Sampling and Analysis Plan and Quality Assurance Project Plan

A Sampling and Analysis Plan (SAP) shall be prepared in accordance with this paragraph, the Specifications, and EM 200-1-3, dated February 1, 2001, or subsequent revision. In addition, the SAP will be required to include a Quality Assurance Project Plan (QAPP), prepared in accordance with Uniform Federal Policy for Quality Assurance Project Plans (DTIC ADA 427785), dated March 2005 or subsequent revision. The Contractor shall also develop data quality objectives (DQOs) for all phases of required work from existing project documents, applicable state and federal guidance and directives, and own sources, and include them in the appropriate sections of the work plans.

Copies of the Contractor’s SOPs and appropriate field forms shall be included as part of the SAP.

The SAP and QAPP for USACE approval shall be submitted within 60 days of award.

5.1.3 Task 1.3 – Site Mobilization and Preparation

The contractor shall prepare the site for the remediation work in accordance with all USACE approved plans. Activities include but are not limited to:

• Clearing and grubbing as required for staging and work areas.

• Interim cap system to prevent dust release and/or erosion;

• Establishment of vehicular traffic pathways, staging areas, and lay-down areas;

• Soil and sediment erosion controls;

• Stormwater controls and treatment;

• Stabilization measures, as necessary;

• Installation of security fencing;

• Establishment of exclusion zones, reduction zones and support zones throughout the execution of remediation activities.

5.1.4 Task 1.4 – Temporary Facilities

The contractor shall provide all necessary temporary facilities to perform the work in accordance with all USACE approved plans. The following activities are included under this task:

• Trailer setup with temporary utilities, sewer, water, electrical and telephone.

5.1.5 Task 1.5 – Environmental Protection

The contractor shall provide all necessary environmental protection measures to perform the work in accordance the Specifications, NHPA Compliance, and all USACE approved plans.

5.1.6 Task 1.6 – Survey

The contractor shall provide all survey control and data collection as in accordance with the Specifications and all USACE approved plans.

5.1.7 Task 1.7 – Site Demobilization

The work shall include furnishing all labor, equipment, and materials to demobilize from the site in accordance with the Specifications and all USACE approved plans. The work includes but is not limited to:

• Removal of excess materials

• Removal of all trash and work-related debris.

• Removal of temporary facilities, site/access controls, and erosion and sedimentation controls.

5.2 Task 2 – Remediation & Restoration of OU3 and OU6 Properties

The Contractor shall complete remediation and restoration at the following properties in accordance with the Drawings, Specifications, and Approved Plans from Task 1.

• OU3 - Ferry Creek from Ferry Boulevard to I-95

• OU6 – Morgan Francis

OU3 – Upper Upper Ferry Creek requires but not limited to excavation, transport, consolidation, and short-term stockpiling of Raymark waste at OU6 - Morgan Francis.

Also, establishing and implementing all stormwater management activities, sediment and soil sampling to define limits of Raymark Waste, and site restoration of property.

OU6 - Morgan Francis Property requires but not limited to excavation, transport, consolidation, and short-term stockpiling of Raymark waste at OU6 - Morgan Francis.

Also, demolition of existing site building, establishing and implementing all stormwater management activities, soil sampling to define limits of Raymark Waste, and site restoration of property.

5.3 Task 3 – Completion of OU6 - Morgan Francis Cap

The Contractor shall complete installation of an engineered cap in accordance with the Drawings, Specifications, and Approved Plans from Task 1.

5.4 Task 4 – Prepare Completion Reports

The contractor shall prepare Final Completion Reports/ Remedial Action Reports to summarize the work completed, geotechnical results, air monitoring results, analytical results, as-built drawings and an evaluation of the effectiveness of the as-built slope stabilization measures for the following properties:

• OU3

• OU6 (Morgan Francis)

Reports are to follow the EPA guidance for the preparation of the remedial action closure reports. The guidance titled “Close Out Procedures for National Priorities List Sites” prepared by EPA and dated May 2011. The guidance is available online.

Assume internal draft, regulatory draft, draft final and final versions will be required with response to comments (RTCs) and response to comments letters (RCL) by the Contractor. The Final Completion Reports shall be approved by USACE.

Draft Completion Reports are due 60 days after construction is completed.

6.0 Additional Requirements

6.1 Environmental Protection Requirements

The Contractor shall identify applicable Federal, State and Local laws, regulations, and Project specific orders or agreements and perform all work in accordance with said authorities. The Contractor shall ensure that all activities performed by its personnel, subcontractors and suppliers are executed in accordance with said authorities. Any incident of noncompliance noted by the Contractor shall immediately be brought to the attention of the USACE’s KO, COR, and PM via telephone, followed by written notice. Nothing in this PWS shall relieve the Contractor of its responsibility to comply with applicable laws and regulations. The Contractor shall investigate the requirements for and obtain all permits, licenses, approvals, and/or certificates necessary to accomplish the work specified. When the work to be performed requires clearances, such as digging or drilling permits, the Contractor shall obtain such clearances and/or permits, with the assistance of the facilities/site point of contact, prior to initiation of any drilling or excavating operations. The Contractor shall coordinate all excavating with USACE prior to performing work. Contractors on environmental sites are required to perform their own utility checks. The Contractor shall comply with all USACE or site-specific time and procedural requirements (federal, state, and local) described in the permits obtained. The USACE will continue to independently review Contractor work to ensure compliance with all applicable requirements.

The Contractor shall perform all work in a manner that minimizes the pollution of air, water or land and develop contingency measures for cleanup of any spills that may occur during performance of this contract. The allowability of spill correction costs incurred by the Contractor shall be determined by the contract clauses "Allowable Cost and Payment", "Insurance - Liability to Third Persons" and any other applicable clauses. The Contractor shall control noise and dust within reasonable limits or limits established by applicable federal, state, and local laws and regulations.

6.2 Sustainability Requirements

The Contractor shall review EO 13834 “Efficient Federal Operations” dated 17 May 2018.

The Contractor shall consider and implement green response/remediation strategies and applications to maximize sustainability, reduce energy and water usage, promote carbon neutrality, promote industrial materials reuse and recycling, and protect and preserve land resources, consistent with DOD and EPA Policies on Green and Sustainable Remediation Practices in the EPA Federal Superfund Program (https://www.epa.gov/superfund/superfund-green-remediation). The Contractor shall present green remediation options and approaches in its work plans, maintain records of “green-related” activities, and report this information to the COR in its project status reports.

EPA Superfund and Green Remediation guides, standards, and Policies include but are not limited to:

1. Superfund Green Remediation Strategy, Sep 2010, U.S. Environmental Protection Agency, Office of Superfund Remediation and Technology Innovation.

2. Memorandum, U.S. Environmental Protection Agency, 02 August 2016, Consideration of Greener Cleanup Activities in the Superfund Cleanup Process.

3. Clean and Greener Policy for Contaminated Sites, EPA Region 1, Feb 2012, Office of Site Remediation and Restoration

The Contractor shall meet the recycled content requirements set forth by EPA for the products identified in the Comprehensive Procurement Guideline (CPG) and at the following link: https://www.epa.gov/smm/comprehensive-http://www.epa.gov/smm/comprehensive-procurement-guideline-procurement-guideline- cpg-program.

The Contractor shall meet the Bio-Preferred Program requirements set forth by USDA for the products identified in the following link:

http://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml)

All deliverables shall be printed double sided on post-consumer fiber paper.

6.3 Protection of Property

The Contractor shall be responsible for any damage that may be caused to property by the activities of the Contractor under this PWS. Additionally, the contractor shall exercise due diligence in the protection of all property located on the premises against fire or damage from any and all other causes. Any property damaged or destroyed by the Contractor incident to the exercise of the privileges herein granted shall be promptly repaired or replaced by the Contractor to a condition satisfactory to the COR or reimbursement shall be made therefore by the Contractor in an amount necessary to restore or replace the property to a condition satisfactory to the COR in accordance with Federal Acquisition Regulation (FAR) Clause 52.237-2.

6.4 Health and Safety Requirements

a. The Contractor shall submit the safety and health organizational structure for their company. This shall include the name and qualification of the experienced Safety Manager directly accountable for the effectiveness of safety efforts under the contract as well as for the implementation of the Corporate Safety Program.

b. The Contractor shall submit their written Corporate Safety Program document which details the company’s safety policies, procedures, and programs as detailed below:

• Management Commitment to Safety

• Safety and Health Program Goals and Metrics

• General Safety Rules and Regulations

• Safety Officer Qualifications, Responsibilities, and Duties

• Hazard Identification and Assessment (to include safety audits, hazard identification, and risk assessment, evaluation, and control).

• Hazard Prevention and Control (to include Hazard Communication and the method by which safety-related matters are coordinated with all disciplines and subcontractors)

• Safety Report of Hazards and Concerns

• Mishap Investigation, Loss Control, Trend Analyses, and Lessons Learned

• Safety Inspection Program

• Selection of subcontractors

• Safety Training http://www.epa.gov/smm/comprehensive-procurement-guideline-http://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml)

• Hiring and Indoctrination of Employees (Safety Personnel, Supervisors and Employees)

• Safety Meetings & Committees (to include the method by which safety concerns or issues are resolved)

• Safety Awards Program

• Emergency Preparedness

• Enrollment in Medical Surveillance Program

• Safety Program Evaluation and Improvement

• Coordination and Communication on Multiemployer Worksites

• Process for Establishing Optimal Staffing Levels for Successful

Completion of Contractually-required Tasks

• Recordkeeping (Mishaps, safety meetings, inspections, training, program audits)

c. The Contractor shall provide their Experience Modification Rate (EMR) for the past five years. The Contractor shall demonstrate an annual EMR Rate of 1.0 or less. Subcontractors utilized by the Prime Contractor on any Task Orders under this contract shall provide documentation that they have maintained an EMR of

1.0 or less for the previous three years. Acceptable documentation of EMR may be a letter provided by the insurance company, written on company letterhead, detailing the EMR for the Prime Contractor and Subcontractors.

d. Each Task Order will contain site-specific safety requirements tailored to the work to be performed. The Contractor shall ensure one qualified Safety Officer and one Alternate Safety Officer meeting the qualification requirements detailed in each Task Order is designated to oversee onsite work. All work executed under each Task Order shall comply with all Federal, State, and local regulations as well as the most recent edition of the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. A copy of EM 385-1-1 can be accessed electronically at Headquarters USACE website under publications using the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf

e. Mishap Reporting. All mishaps (accidents and near miss incidents) shall be investigated by a competent person employed by the Contractor. All work-related recordable injuries, illnesses, and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the GDA within 4 hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the GDA. USACE ENG Form 3394 (Attachment 1) shall be completed and submitted to the GDA within seven working days of the incident. Within 10 days of an OSHA recordable incident or USACE reportable property damage incident, the Contractor shall submit to the GDA a Lessons-Learned document.

f. Safety Briefings. The Contractor shall conduct a safety meeting at the project site on the first day of work, whenever a new activity or phase of work begins, or at least weekly during the progress of work. All safety meetings shall be documented (Attachment 2). A copy of the weekly safety meeting form will be submitted to the GDA weekly.

g. Monthly Reporting. For each Task order involving field activities, the Contractor shall complete the “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (Attachment 3) (for the Prime Contractor and Subcontractors). The completed form shall be submitted to the GDA no later than close of business on the 5th calendar day of the following month. The method of transmission shall be electronic.

h. Equipment Inspection. The Contractor shall ensure heavy equipment used to complete field activities on any Task Order under this contract is inspected by a competent person. The inspection shall document that the equipment is suitable and safe for the work tasks being performed. Safety inspection documentation shall be accepted by the GDA prior to the equipment being mobilized to the site.

6.5 Sampling and Analysis Quality Control

Appropriate documentation of Quality Control shall be provided whenever sampling or analysis for chemical, geophysical, geotechnical, particulate, or soils parameters is required in order to meet the PWS objectives. The laboratory(ies) to be used by the Contractor shall be certified by the National Environmental Laboratory Accreditation Program (NELAP) or an equivalent agency. The Contractor may also establish an on- site testing laboratory at the project site if determined necessary by the Contractor. However, this on-site testing shall meet the requirements of EPA and any specific state regulator requirements. The Contractor shall also comply with all requirements of the DoD Quality Systems Manual, Final Version 3, dated January 2006 or more recent version.

6.5.1 Analytical Testing

Environmental laboratory services are to be provided only by laboratories that have successfully passed the new Environmental Laboratory Accreditation Program (ELAP) audit implemented 1 October 2009, including being compliant with the most recently published version of the Department of Defense (DOD) Quality Systems Manual (QSM Version 5.1.1 and holding current NELAP accreditation for all the preparatory and analysis. The latest version of the DOD QSM is available at http://www.denix.osd.mil or http://navylabs.navy.com.

As requested by the COR, the laboratory shall submit in a timely manner, their ELAP accreditation certificate (including supporting documentation). Before testing services can be performed by the laboratory, the COR will notify the candidate laboratory of the acceptability of their ELAP accreditation and supporting documentation. The ELAP accreditation certificate is to be provided http://www.denix.osd.mil/ http://navylabs.navy.com/ http://navylabs.navy.com/ upon each recertification while supporting USACE contracts.

An environmental laboratory, either participating, or engaged in support of USACE contracts, shall notify the prime contractor and COR, immediately of change in status of laboratory operations that may affect on-going compliance with these requirements. The COR may, at any time, conduct audits (including requests for pertinent data or information) that support an environmental laboratory's ELAP accreditation with this policy. If the COR finds the laboratory non-compliant; alternate, compliant laboratory services will be utilized, until such time as compliance is again demonstrated. Before performing environmental testing for the USACE, the laboratory shall have access to the agency approved Sampling and Analysis Plan (SAP) and/or QAPP as the case may be.

The laboratory shall provide sample results in both paper copy and electronic data deliverable (EDD) format within the prescribed turnaround time (TAT) associated with any sampling event. The Contractor shall work closely with the analytical laboratories to schedule all sampling events in advance in order to meet the TAT requirements of the program. The laboratory report shall include:

a) Sample Results.

b) Dates of Extraction and Analysis.

c) Associated Quality Control including laboratory method blank, trip blanks, equipment blanks, Laboratory Control Sample (LCS), matrix spike and matrix spike duplicate (MS/MSD), surrogate recovery, and duplicate sample results.

d) Narrative describing any sample anomalies or quality control exceedance, and their impact on the analytical results.

e) Copies of Chain of Custody and Sample Receipt forms.

f) Electronic data deliverables.

g) All appropriate data required for a CLP data package/EDD…