This document is a Binding Rates Table for a federal contract opportunity. It provides the direct rates and total burdened rates for key personnel across different labor categories and work locations (home office, home office overtime, field office, field office overtime) for a 5-year period. The labor categories include Program Manager, Project Manager, Site Superintendent, Site Safety & Health Officer, Contractor Quality Control (CQC) System Manager, Project Chemist, and Project Engineer. The direct rates for all labor categories are $1.00 per hour, with 0% combined markup for fringe, overhead, and G&A, resulting in total burdened rates of $1.00 per hour across all years and labor categories.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Markups
| Binding Rates for Prime Contractor | |
| Prime Contractor Name: | |
| Document: | Appendix I-1/Mark-up Development |
| HOME OFFICE LABOR | |
| Markup Type (Provide Description) | % |
| Fringe | 0.00% |
| Overhead | 0.00% |
| G&A | 0.00% |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| Combined Markup for home office | 0.00% |
| FIELD OFFICE LABOR | |
| Markup Type (Provide Description) | % |
| Fringe | 0.00% |
| Overhead | 0.00% |
| G&A | 0.00% |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| Combined Markup for field office/site work | 0.00% |
&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Solicitation Number: W912WJ-17-R-0005 &D
Year 1
| Binding Rates for Key Personnel | Base Year 1 |
| Prime Contractor Name: | |
| Document: |
| Home Office | Home Office OT | Field Office | Field Office OT | |||||||||
| Government Job Title | Contractor Job Title | Unit | DIRECT RATE $ | DIRECT RATE (OT) $ | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE |
| Program Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Superintendent | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Safety & Health Officer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Contractor Quality Control (CQC) System Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Chemist | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Engineer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 |
&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 2
| Binding Rates for Key Personnel | Year 2 |
| Prime Contractor Name: | |
| Document: |
| Home Office | Home Office OT | Field Office | Field Office OT | |||||||||
| Government Job Title | Contractor Job Title | Unit | DIRECT RATE $ | DIRECT RATE (OT) $ | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE |
| Program Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Superintendent | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Safety & Health Officer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Contractor Quality Control (CQC) System Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Chemist | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Engineer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 |
&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 3
| Binding Rates for Key Personnel | Year 3 |
| Prime Contractor Name: | |
| Document: |
| Home Office | Home Office OT | Field Office | Field Office OT | |||||||||
| Government Job Title | Contractor Job Title | Unit | DIRECT RATE $ | DIRECT RATE (OT) $ | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE |
| Program Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Superintendent | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Safety & Health Officer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Contractor Quality Control (CQC) System Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Chemist | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Engineer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 |
&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 4
| Binding Rates for Key Personnel | Year 4 |
| Prime Contractor Name: | |
| Document: |
| Home Office | Home Office OT | Field Office | Field Office OT | |||||||||
| Government Job Title | Contractor Job Title | Unit | DIRECT RATE $ | DIRECT RATE (OT) $ | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE |
| Program Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Superintendent | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Safety & Health Officer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Contractor Quality Control (CQC) System Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Chemist | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Engineer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 |
&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Year 5
| Binding Rates for Key Personnel | Year 5 |
| Prime Contractor Name: | |
| Document: |
| Home Office | Home Office OT | Field Office | Field Office OT | |||||||||
| Government Job Title | Contractor Job Title | Unit | DIRECT RATE $ | DIRECT RATE (OT) $ | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE |
| Program Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Superintendent | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Site Safety & Health Officer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Contractor Quality Control (CQC) System Manager | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Chemist | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | |
| Project Engineer | Hour | $ 1.00 | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 | 0.00% | $ 1.00 |
&G &"Arial,Italic"Callahan Mine Superfund Site IDIQ/RAC, Pick List
| Task 1 |
| Task 2 |
| Task 3a |
| Task 4 |
| Task 3b Initial |
| Task 3b Final |
image1.jpeg