Amendment 05 - W912PL-16-R-0011 - 3MAR2016 Extend RFI submittal due date to March 09 2016.

View the file

Other files

File Type Posted
Correct_Amendment_06_-_NHCP_PWS_-_18MAR2016-2.docx DOCX document
Am7_W912PL-16-R-0011.pdf PDF
Amendment_06_-_Updated_-_Service_Contract_Wage_Rates_-_17MAR2016.pdf PDF
Amendment_06_-_NHCP_Fuel_Storage_Tanks_-_FIO.pdf PDF
Amendment_06_-_Revised_Section_M_-_17MAR2016.pdf PDF
Amendment_06_-_Updated_-_Davis-Bacon_Wage_Rates_-_17MAR2016.pdf PDF
Amendment_06_-_NHCP_PWS_-_17MAR2016.pdf PDF
Amendment_06_-_Exhaust_hoods-PM_only-_FIO.pdf PDF
Amendment_06_-_FuelFilteringSystem_-_FIO.pdf PDF
Amendment_06_-_W912PL-16-R-0011_-17MAR2016_.pdf PDF
Amendment_05_-_Revised_Section_L_-_3MAR2016.pdf PDF
Amendment_04_-_NURSE_CALL_SYSTEMS_-_2MAR2016.pdf PDF
Amendment_04_-_Section_M_-_2MAR2016.pdf PDF
Amendment_04_-_H-200_EXTERIOR_ELEVATIONS_-_2MAR2016.pdf PDF
Amendment_04_-_FY14_Backflow_Inventory_List_H-200_and_Clinics_-_2MAR2016.xls XLS spreadsheet
Amendment_04_-_Landscaping_areas_-_2MAR2016.pdf PDF
Amendment_04_-_Amalgam_Separator_-_2MAR2016.pdf PDF
Amendment_04_-_11_24_00_00_95_BUILDING_MAINTENANCE_EQUIPMENT-_2MAR2016.pdf PDF
Amendment_04_-_W912PL-16-R-0011_-_2MAR2016_.pdf PDF
Amendment_04_-_Property_Record_Information_-_2MAR2016.xlsx XLSX spreadsheet
Amendment_03_-_PART_XIII_ConstructionSpecifications_Complete_-_23FEB2016.pdf PDF
Contractor_Sign_in_Sheet_20FEB2016.pdf PDF
Amendment_03_-_Government_Furnished_Equipment_-_23FEB2016.pdf PDF
Amendment_03_-_Floor_Plan_14_Area_Trailer_-_23FEB2016.pdf PDF
Amendment_03_-_Med_Gas_Test_Report_-_23FEB2016.pdf PDF
Amendment_03_-_Appendix_A_-_Mechanical_Equipment_Inventory_-_25FEB2016_.xlsx XLSX spreadsheet
Amendment_03_-_Revised_Section_L.pdf PDF
Amendment_03_-_Revised_Section_B.pdf PDF
Amendment_03_-_Work_Request_Summary_Report_Jan_2014_-_Dec_2015.xls XLS spreadsheet
Amendment_03_-_NHCP_PWS_-_25FEB2016.pdf PDF
Amendment_03_-_PM_Frequency_-_23FEB2016.xlsx XLSX spreadsheet
Amendment_03_-_Galley_Refrigerators_and_Freezers_-_23FEB2016.pdf PDF
Amendment_03_-_TJC_Inspections_-_23FEB2016.pdf PDF
Amendment_03_-_Hospital_Clinic_List_-_23FEB2016.xlsx XLSX spreadsheet
Amendment_03_-_H200_Tree_Inv_-_23FEB2016.pdf PDF
Amendment_03_-_FMD_Construction_Package_-__23FEB2016.pdf PDF
Amendment_03_-_Revised_Section_C.pdf PDF
Amendment_03_-_NHCP_Active_RPIE_-_23FEB2016.xlsx XLSX spreadsheet
Amendment_03_-_W912PL-16-R-0011_-_25FEB2016_.pdf PDF
Amendment_03_-_Revised_Section_M.pdf PDF
Amendment_02_-_W912PL-16-R-0011-_23FEB2016.pdf PDF
W912PL-16-R-0011-_Am01_.pdf PDF
Attachment_7_-_DB_Wage_Determinations_20JAN2016.pdf PDF
Attachment_8_-_SCA_Wage_Determinations_19JAN2016.pdf PDF
A.01.30_-_Attachment_2_-_Facility_Overview_-_21JAN2016.pdf PDF
A.01.30_-_Appendix_C_-_Personnel_Resume_Form_-_26JAN2016.docx DOCX document
A.01.30_-_Attachment_4_-_13th_Edition_Glossary_-_21JAN2016.pdf PDF
A.01.30_-_Attachment_6_-_RSMEANS_San_Diego_Cost_Index_-_21JAN2016_.pdf PDF
Solicitation_-_W912PL-16-R-0011_-_27JAN2016.pdf PDF
A.01.30_-_Attachment_1_-_Map_NHCP_and_CLINICS_-_21JAN2016.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 1

0005 Mar 3, 2016

W912PL

U.S. Army Corps of Engineers Los Angeles District 915 Wilshire Boulevard, Suite 930 Los Angeles, California 90017-3401 Attn:Contracting Division CESPL-CT-W

SEE ITEM 6

W912PL-16-R-0011

Jan 27, 2016

Operation and Maintenance on NHCP and Clinics at Camp Pendleton San Diego, Ca. The following changes are incorporated by this amendment:

Revise "Section L" extending the RFI submittal due date to March 9, 2016.