This Pre-Proposal Inquiries (PPI) Log is for a U.S. Army Corps of Engineers solicitation (W912PF25QA092) for Battery Energy Storage System (BESS) installation at Longare Base in Italy. The procurement is a design-build project for installing four BESS units across multiple electrical substations, with a total project duration of 512 calendar days (242 days for design and 270 days for construction). The solicitation is a best-value tradeoff procurement where non-price factors are significantly more important than price, with an estimated installation/construction budget between $500,000 and $1,000,000.

Key technical requirements include installing 250 kW BESS units with a minimum 90% round-trip efficiency, capable of black-start functionality, grid-forming operation, and providing ancillary services like frequency regulation and voltage control. The BESS must interface with an existing Microgrid Controller (MGC) using IEC 61850 protocol and support both individual and coordinated parallel operation. Offerors must provide SOA certification (Italian construction qualification) through either direct certification or a qualified subcontractor, and submissions are due by 22 September 2025. The project involves upgrading electrical infrastructure at multiple substations, with specific cybersecurity requirements and a focus on resilience and smart energy management.

View the file

Other files

File Type Posted
Solicitation Amendment W912PF25QA0920005 SF 30.pdf PDF
Solicitation Amendment - W912PF25QA0920005.pdf PDF
B08-RFP_Atch1.8_SOW_REC - BESS at Longare Proponent Signed_20250725.pdf PDF
B08-RFP_Atch4_BidSchedule_CLIN0004_20250904.xlsx XLSX spreadsheet
B08-RFP_Atch4_BidSchedule_CLIN0003_20250904.xlsx XLSX spreadsheet
B08-RFP_Atch4_BidSchedule_CLIN0002_20250904.xlsx XLSX spreadsheet
SS_44_PLC.pdf PDF
Solicitation Amendment - W912PF25QA0920004.pdf PDF
A02-SOW_R1_20250911.pdf PDF
Solicitation Amendment W912PF25QA0920004 SF 30.pdf PDF
B08-RFP_Atch4_BidSchedule_CLIN0001_20250904.xlsx XLSX spreadsheet
SS_44_RTU_MULTIFILARE.pdf PDF
T601-Smart Grid_As Built.pdf PDF
Solicitation Amendment 3 - W912PF25QA0920003.pdf PDF
Solicitation Amendment 3 -W912PF25QA0920003 SF 30.pdf PDF
Amendment 2 - W912PF25QA0920002.pdf PDF
Amendment 2 - W912PF25QA0920002 SF 30.pdf PDF
MIOTTO BASE GENERATORS_PV.pdf PDF
MC N019-24 LO PAESAGGISTICA.pdf PDF
MC N019-24 LO LANDSCAPE.pdf PDF
Design BESS at ESS_43.pdf PDF
Amendment1 W912PF25QA0920001 SF 30.pdf PDF
Design BESS at ESS_34.pdf PDF
Design BESS at ESS_42.pdf PDF
Design BESS at ESS_38.pdf PDF
Amendment1 W912PF25QA0920001_Summary.pdf PDF
B08-RFP_Atch5_Anti-Mafia Certification_20250804.pdf PDF
B08-RFP_Atch2_SOW_GENERAL_20230127.pdf PDF
B08-RFP_Atch3_QA LOG_20250804.xlsx XLSX spreadsheet
B08-RFP_Atch1_SOW_20250725.pdf PDF
Solicitation - W912PF25QA092.pdf PDF
B08-RFP_Atch4_BidSchedule_20250804.xlsx XLSX spreadsheet
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-PROPOSAL INQUIRIES (PPI)

LOG

Doc. Page Sec.

1 28-Aug-25

Comment:

Volume 1 (Mandatory Documentation Required With the Proposal) of Solicitation W912PF25QA092 provides as follows:

“e. The Offeror shall provide proof that the contractor/company holds a valid Società Organismo di Attestazione (SOA) Attestation demonstrating qualification in a category and classification appropriate for the scope of this project. The relevant category SOA Certification is Classifica IV-BIS in category OG10.”

It is our understanding that:

1. SOA certification is a requirement under Italian public procurement law (previously Legislative Decree No. 50/2016, the Codice degli Appalti, and more recently Legislative Decree No. 36/2023, the Codice dei Contratti Pubblici), for contractors participating in Italian public works procurements exceeding €150,000;

2.SOA certification is administered through accredited Italian attestation bodies; and
3.to our knowledge, it would not ordinarily apply to foreign government projects such as

those procured by the United States Government under the U.S. Federal Acquisition Regulation (FAR).

We note that Solicitation W912PF25QA092 relates to a U.S. Army Corps of Engineers (USACE) procurement conducted pursuant to the FAR in connection with a U.S. Government facility located in Italy.

Questions:

We respectfully request confirmation on the following points:

1. Whether SOA certification is in fact required from all Offerors (including U.S.-based entities); and

2. If so, whether the SOA certification must be held directly by the Offeror itself, or whether it may alternatively be satisfied through a related third party, such as: (i) an Italian affiliate within the Offeror’s corporate group; or (ii) an Italian subcontractor or joint venture partner of the Offeror.

We appreciate your prompt clarification to ensure compliance with the solicitation requirements.

1. Yes, the requirement for a valid SOA Attestation in the specified category and classification applies to the entity performing the construction work. For a U.S.-based prime contractor, this requirement must be met by the entity that will be performing the on-site construction and installation work (e.g., a qualified Italian subcontractor).

2. The SOA certification must be held by the legal entity performing the work that requires such certification under Italian law. The solicitation is hereby clarified: A prime contractor may meet this requirement through a key subcontractor who holds the required SOA. If this approach is used, a letter of commitment from the subcontractor must be included in Volume I.

2 27-Aug-25 Solicitation 30/48 VOL 1

SOA Requirement (Cat OG-10 Cl IV-BIS). Performed similar/equal project but we do not have the appropriate Category/Classification required in the Solicitation. Will our proposal be taken into consideration if we submit/provide a Partnering/Teaming Pre-Agreement with a suitable subktr?

Yes. See response to Q1. If an Offeror as a prime contractor does not hold the required SOA certification, its proposal will be considered compliant if it includes a firm letter of commitment from a key subcontractor that holds the required SOA certification (Classifica IV-BIS in categories OG9 or OG10). The letter of commitment must be included in Volume I and will not count against any page limits.

3 26 Aug 2025 Solicitation

W912PF25

QA092

31 of 48 vol,4 past performance

We respectfully request clarification on whether past performance involving the installation of Uninterruptible Power Supply (UPS) systems (with same size and complexity of project requirement) may be deemed acceptable as relevant experience in lieu of Battery Energy Storage Systems (BESS) installations.

As stated in Volume IV, Relevancy Definition, the Government will consider projects "more relevant if they demonstrate experience with...

Installing and integrating Battery Energy Storage Systems (BESS)..."

While UPS and BESS systems share some technological principles, BESS integration into a microgrid is considered a distinct and more complex capability. Offerors may submit UPS projects for consideration, but the burden is on the Offeror to demonstrate the relevance to the SOW.

Projects involving BESS will be considered more relevant.

4 26 Aug 2025 Solicitation

W912PF25

QA092

32 of 48 vol,5 price Will the task order award evaluation be based on the lowest price?

No. As stated in Addendum to FAR 52.212-2, paragraph (b), this is a best-value tradeoff procurement where the non-price factors are significantly more important than price.

REFERENCEDATE

RECEIVED# QUESTION GOVERNMENT RESPONSE

5 26 Aug 2025

B08- RFP_Atch2_

SOW_GEN

ERAL_2023

01272

16 of 180 01 33 10.05 20

Could the Government kindly confirm whether the submission of a completed design package is required from the Contractor (KTR)? If so, we respectfully request clarification on the number and type of design submittal phases expected (e.g., 65%, 95%, Final).

Offerors are not required to submit a completed design package with their proposal . This is a design-build project. The required design submission phases (Initial Design Conference, 65%, 95%, and 100% Final) are detailed in SOW Section 2.3, DESIGN SUBMITTALS. The proposal should describe the Offeror's technical approach to meeting

6 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems

Scope of work specifies the use of lithium-ion batteries. We would like to inquire whether the Government would consider the use of sodium-nickel battery systems as an acceptable alternative, provided they meet or exceed the required performance, safety, and certification standards outlined in the solicitation.

Sodium-nickel batteries offer several advantages over lithium-ion technology, including:

Higher safety (no risk of thermal runaway or fire) Longer cycle life (up to 6,000 cycles) Wider operating temperature range (0°C to +300°C) Reduced environmental impact (no rare earth elements) Compliance with key standards, including UL 9540A, UL 1973, IEC 62984, and EN IEC 61000-6-2/6-4 We have attached a technical report comparing sodium-nickel and lithium-ion systems, including performance data, certifications, and operational considerations

Sodium-nickel battery systems is feasible if it meets the requirements of the SOW. See SOW Rev 1 Section D509090. Section has been revised to remove the lithium ion battery requirement.

7 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Will future replacement with alternative technologies be permitted?

The scope of this contract is for the design and installation of the BESS as proposed and awarded. Future technology replacements are outside the scope of this procurement.

8 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems What is the minimum guaranteed lifespan (in years or cycles)

The SOW is a performance-based specification. It does not state a minimum guaranteed lifespan. Offerors shall propose a system whose lifespan meets the objectives described in the SOW. The proposed warranty and lifespan will be evaluated as part of the Technical

9 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems What is the minimum required round-trip efficiency (e.g., ≥ 90%) Per SOW Revision 1, Section 509090, the minimum round-trip effiociency is 90%.

10 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Does the specified 500 kWh capacity refer to the system’s ability to deliver full load for 2 consecutive hours?

The baterry shall comply with SOW Revision 1 Section 1.0 Project Description. See SOW Revision 1 Section 1.0 Project Description.

Section has been revised to read 250 kW.

11 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Is redundancy required among the PCS units shown in the system diagram? The SOW does not require redundancy among the PCS units shown in the system diagram.

12 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Will the four BESS units operate independently or in coordinated parallel mode?

Per SOW Section D509090, the PCS will be designed to operate in parallel. They will be coordinated by the upgraded Micro Grid Controller (MGC). The BESS units must be able to operate both individually and in coordination with other BESSs and with the other resources of the grid

13 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Is a black-start capability required to initiate the microgrid in the absence of utility power?

Yes. Per SOW Section D509090, a required function of the BESS is to "perform the LV grid restart by black start function, independent of the presence or absence of the MV grid."

14 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Are the BESS units expected to provide ancillary services (e.g., frequency regulation, voltage control, power quality)?

Yes. SOW Section D509090 states the PCS "will be able to regulate or form (grid forming) both the voltage and frequency of the Longare microgrid." Other functions include energy shifting and peak shaving.

15 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems

What is the nature of the so-called “critical loads”? Are there any disturbing loads (e.g., harmonics, inrush currents)? If so, are there defined limits for THD and acceptable inrush levels?

Per SOW Revision 1, Section 1 Project Description, The critical load is the total load supplied by all main low voltage panels in all electrical substations. There are no disturbing loads. The THD < 5%.

16 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Is the PCS required to support overcurrent capability (e.g., 200% for 10 seconds) to handle motor starts?

The SOW does not specify a minimum overcurrent capability. The contractor is responsible for designing a system that can reliably power the connected loads. The proposed PCS capabilities will be evaluated as part of the Technical Approach. The only loads that could create inrush problems should be MV transformers, The base does not have large loads that could create further inrush current problems (e.g. industrial motors etc.) therefore overcurrent problems are not forseen.

17 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Should the bypasses indicated in the diagram be manual, automatic, or both?

Per Attachements: Design BESS single line diagrams provided with the SOW, the bypass depicted as manual and shall comply with SOW Revision 1 Section D503006.

18 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Is the 400/400 V transformer mandatory for all BESS units? Should it provide galvanic isolation only, or also impedance matching and/or short-circuit current reduction?

Per Attachements: Design BESS at ESS#34-38-42-43 Table E-102 Keynotes 3, Yes, 400/400V transformer is mandatory for all BESS units.

The tranformers act as galvanic isolation.

19 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Is redundancy required for auxiliary systems (e.g., HVAC, ventilation, lighting, UPS)? See Response to Question 11 above

20 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems What communication protocol is required for interfacing with the Microgrid Controller (MGC)

(e.g., Modbus TCP, IEC 61850, OPC UA, DNP3)?

Per SOW Rev. #1 Section D503006 BESS will be connected to the MGC network through the IEC 61850 protocol as regards management.

21 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems What level of integration is expected: monitoring only, or also active control (e.g., dispatch, droop control)?

Active control is required. Per SOW Section D503006, the MGC is intended to "monitor and control generation and load assets" and "optimizing the use of BESS."

22 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems What minimum cybersecurity standards must be met (e.g., NIST, IEC 62443, DoD STIG)?

Per SOW Rev. #1 Section D503006 Communication between new equipment and the existing communication network shall be in accordance with the minimum cybersecurity standards that will depend on the devices installed. The minimum requirement is NIST 800-53 version

4. If the devices connect to the existing DPW network infrastructure or are networked, NETC-CSD-RMD-10008, NETCOM SIS-CRN TTP will apply. If a workstation or server is connected to BESS, logically or physically, the DoD_STIG implementation requirements will need to be

23 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Should the fire suppression system send signals to the Base Ederle supervisory system? If so, which communication protocols are acceptable?

The fully compatible fire protection systems at our installations consist of NOTIFIRE control panels that communicate through the fiber optic network with the SAET supervision system through an ISI communicator.

Communication protocol is SAET com. Caserma Ederle supervisory system" is the SAET system for the Fire Prevention system, which is different from the MGC and the DDC. Yes the fire supression system shall send signals to the Caserma Ederle supivisory system.

24 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems

In the event of a total blackout, should each BESS operate in “grid-following” mode (synchronizing to existing voltage/frequency), or in “grid-forming” mode (creating its own voltage/frequency to manage disturbing loads)?

Per SOW Rev. #1 Section D503006 Each BESS to operate in grid-forming mode.

25 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Is a master/slave logic defined among the parallel BESS units, or will a shared droop control be managed by the MGC?

No. There is no Master /slave logic among BESSs. Per SOW Rev. #1 Section D509090 The MGC will have to be able to manage all energy scenarios.

26 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems Will a State of Charge (SOC) balancing algorithm be implemented among the four BESS units to prevent uneven discharge? No, the vendors do not have to provide this.

27 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems How will power supply priority be managed between critical loads in each building and energy injection into the medium-voltage ring?

Per SOW Rev. #1 Section D503006 The primary function of the BESS is to provide resilience to the LV loads connected to each substation. The control logic for this prioritization is part of the detailed design to be proposed by the contractor. In island mode, not connected to the grid, it will be the task of the existing ABB PLC to manage the priorities of the loads, for this purpose all buildings main switches located in the substation needs to be motorized and needs to be managed by the existing ABB PLC during the emergency mode. The contractor shall evaluate the existing ABB PLC to determine if an additional ABB PLC will be required. Contractor is required to provide a fully functional system.

28 01 Sept 2025

B08- RFP_Atch1_

SOW_2025

26 of 30 Provide Battery Energy Storage Systems

Is the MGC expected to perform economic optimization functions (e.g., coordinated peak shaving, energy arbitrage), or only resilience/backup functions? In other words, is the Client requesting a military-grade emergency system, or also a “smart energy manager” aimed at reducing costs and CO₂ emissions?

Both. SOW Section D509090 lists resilience functions (continuity of service, black start) and economic functions (energy shifting, peak shaving). MGC must provide for several macro scenarios, both smart energy management (Cost saving). The ABB PLC will be used for resilience/backup function.

29 2-Sep-25

SOLICITAT

ION

AMEND 03

Factor III\ Past Performance Will the government issue and provide a specific form for Factor III Past Performance? No. Offerors shall provide the required information ensuring all elements requested in Volume IV are included.

30 2-Sep-25

SOLICITAT

ION

AMEND 03

Factor III Past Performance If the submitted projects for Factor III Past Performance have CPARS evaluations, should offerors include those evaluations? If yes, are the CPARS evaluations excluded from the page count?

Offerors are not required to submit CPARS reports. As stated in Volume IV, the Government may independently access CPARS as part of its evaluation.

31 2-Sep-25

SOLICITAT

ION

AMEND 03

General

The Offeror kindly requests an extension of time to submit the proposal of at least one week beyond the current deadline of 18 SEPT 2025 at 15:00 hrs to ensure thorough evaluation.

The reasons for this request are the following:

- size and complexity of the project;

- delay in obtaining feedbacks from suppliers in August of specific materials due to the August closure period for suppliers and subcontractors in Italy delaying price comparisons / evaluations.

RFP has been extended. Proposals are now due on 22 SEPT 2025 @1100Hrs CET

32 2-Sep-25

SOLICITAT

ION

AMEND 03

Factor III Past Performance We kindly request to extend the recency factors (VOLUME III Factor II and Volume IV Factor III) for submitted projects from 03 to 05 years.

The request is considered. The Government has determined that the three

(3) year recency requirement is appropriate for this acquisition and will remain unchanged.

33 2-Sep-25

SOLICITAT

ION

AMEND 03

General Could the government indicate a Magnitude of Price Range for this solicitation ?

This acquisition is primarily for a commercial supply (Battery Energy Storage System units) with an ancillary requirement for installation and construction services. In accordance with Federal Acquisition Regulation (FAR) 36.204, which requires the disclosure of the magnitude of construction projects, the Government is providing the magnitude for the installation/construction portion of this requirement only. The estimated magnitude for the installation/construction portion is between $500,000 and $1,000,000. The solicitation will be amended to officially incorporate this information.

34 2-Sep-25

SOLICITAT

ION

AMEND 03

General This Inquiry is to request confirmation that the Solicitation Number is W912PF25QA092 and not W912PF25RA010 as indicated at page 28 .

The correct solicitation number is W912PF25QA092 The reference to "W912PF25RA010" is a typographical error. The solicitation will be corrected via this amendment.

35 2-Sep-25

SOLICITAT

ION

AMEND 03

Admin Within the Solicitation we have noticed that Performance Guarantees/Bonds nor Insurance have not been requested, is it correct?

A performance guarantee will be required for the construction portion of the work only to ensure successful completion. The guarantee shall be in the amount of 20% of the total price awarded for the construction/installation efforts. Acceptable forms of security are listed in FAR 52.228-15, which is hereby incorporated by reference. An Irrevocable Letter of Credit or Bank Guarantee from a recognized financial institution is an acceptable alternative to a traditional surety

36 2-Sep-25

SOLICITAT

ION

AMEND 03

Volume I

Reference is made to: Page 30 of Solicitation (AMEND02) indicating: '' Volume I point b. i.

New Unique Entity Identifier (UEI). For more information about UEI, please visit https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update. Please clarify which type of document is needed? A simple snap of the UEI number from the SAM.GOV Workspace, showing the Offeror's UEI is sufficient or other documents. Thank you

Yes, a snap will suffice. This is explaining how to get a UEI if you don’t have one. If you are SAM regisitered, your new UEI will show up on your SAM registration as well. The new link for GSA UEI is https://shorturl.at/q4uSh

37 2-Sep-25

SOLICITAT

ION

AMEND 03

Volume IV – Factor III – Past Performance Volume IV – Factor III – Past Performance - Is there a Maximum number of projects to be submitted?

We will be clarifying the requirement via an amendment. Offerors shall submit a minimum of two (2) and a maximum of three (3) of their most relevant past performance projects. If an offeror submits more than three

(3) projects, the Government will only evaluate the first three (3) projects listed in the proposal. Projects submitted beyond the first three (3) will not be evaluated.

38 2-Sep-25

SOLICITAT

ION

AMEND 03

Volume IV – Factor III – Past Performance Are Letters of Commitment for Subcontractor Teaming Agreements required? If yes, in which volume should we enclose such documents? Volume III Corporate Experience / Volume IV Past Performance? Will the mentioned Letters be excluded from the page count?

Letters of Commitment are required if an Offeror is relying on a subcontractor to meet a mandatory requirement (e.g., SOA certification) or if submitting a subcontractor's experience/past performance for evaluation. Letters of Commitment shall be included in Volume I - Mandatory Documentation and will be excluded from the page count.

39 2-Sep-25

SOLICITAT

ION

AMEND 03

General We kindly request to review the solicitation indicating the page numbers, if possibile. Thank you

Unfortunately, our contract writing system (ACWS) does not currently allow us to insert page numbers into solicitation/award documents.

40 2-Sep-25

SOLICITAT

ION

AMEND 03

Volume III – Factor II – Corporate Experience Please confirm that submission of the Key Subcontractor's experience is accepted in Volume III Factor 2 Corporate Experience and in Volume IV- Past Performance. Thank you.

Yes. The Government will consider the experience and past performance of subcontractors. When submitting a subcontractor's project, the Offeror must clearly identify the subcontractor, and their specific role and responsibilities on the project. The Government's evaluation will primarily focus on the prime contractor's record.

41 2-Sep-25

SOLICITAT

ION

AMEND 03

Volume V - Factor IV PRICE

The Bid Schedule provided with the RFP (B08-RFP_Atch4_BidSchedule_20250804) shows only two CLINs divided by project name: CLIN 0001 Basic Contract MI-00001-3J through MI- 00004-3J Install BESS’s Longare, and CLIN 0002 UXO Remediation for MI-00001-3J through MI-00004-3J Install BESS’s Longare. In subsequent amendments (n.1, n.2, and n.3), Volume V: Price specifies that pricing must be submitted in accordance with the instructions provided and that Offerors shall complete and submit pricing in the Standard Form 1449 with amounts for each CLIN 1–5. However, no new or updated Bid Schedule has been issued reflecting five CLINs. Could the Government please clarify each of the CLINs that shall be quoted and provide details on how the different projects MI-00001-3J, MI-00002-3J, MI- 00003-3J, and MI-00004-3J are to be linked to the design drawings provided with Amendment 1 (Design+BESS+at+ESS_34, Design+BESS+at+ESS_38, Design+BESS+at+ESS_42, The Bid Schedule (B08-RFP_Atch4_BidSchedule_20250804) will be replaced w/ B08-RFP_Atch4_BidSchedule_CLIN0001_20250904 through B08-RFP_Atch4_BidSchedule_CLIN0004_20250904 to accurately reflect the RFP CLIN structure and 4 separate projects.

Instructions are provided in the schedule.

42 2-Sep-25

SOLICITAT

ION

AMEND 03

Volume V - Factor IV PRICE Please clarify if Attachment 4 - Bid Schedule should be submitted in excel format also. Thank you

Offerors shall submit the completed Attachment 4, Bid Schedules, in two formats: A signed copy in PDF format. This will be considered the official offer for the record & a native copy in its original Microsoft Excel format. This copy is requested to facilitate the Government's evaluation.

In the event of a discrepancy between the two versions, the signed PDF version shall take precedence https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update https://www.gsa.gov/aboutus/organization/federalacquisition-service/office-of-systems-management/integratedaward-environmentiae/iae-systems-informationkit/unique-entity-identifier-update

43 2-Sep-25

SOLICITAT

ION

AMEND 03

Volume I - Mandatory Documentation To be Compliant to the FAR Clauses incorporated in the solicitation, should offerors Complete & Submit Solicitation FAR Clauses from pages 35 to 48 or should Offerors submit the FAR & DFARS report from SAM?

Offerors must have a complete and active registration in the System for Award Management (SAM.gov), including the annual representations and certifications, as required by FAR 52.212-3. You do not need to submit the standard report from SAM with your proposal; the Government will verify your status online.

By submitting your proposal, you are certifying that the information in your SAM.gov profile is current, accurate, and complete for this solicitation.

If your SAM.gov registration is not complete, or if you need to change a representation for this specific offer, you must complete the relevant provisions in the solicitation and submit this completed document as a separate attachment with your proposal.

All clauses listed in the solicitation will be incorporated by reference or in

44 4-Sep-25 Sol 31 Vol II Request the Government confirm the BESS System and Design documentation requirements ( detailed specifications, diagrams, component lists, warranty, and maintenance contract information for proposed BESS as required by the SOW) are not included in the 6-page limit

The 6-page limit applies exclusively to the Technical Approach Narrative.

This narrative must contain the text, tables, and charts that explain the offeror's methodology, understanding of the requirements, and overall technical solution.

The following Supporting Technical Documentation is excluded from this 6-page limit and shall be provided in a separate, clearly labeled appendix:

Detailed specifications and product data sheets System and design diagrams/drawings Component lists Warranty information Maintenance contract information

This appendix of supporting documentation shall not exceed 10 pages in total. The purpose of this appendix is to substantiate the claims made in the Technical Approach Narrative

45 4-Sep-25 Sol 33 Evaluation Factors Para C, Evaluation Factors makes references to Factors 1-Factor 4. For clarity purposes, request the Government include the factor verbiage in the Volume Content identified on solicitation pages 30-32

Addendum 52.212-1 provides proposal submission Instructions and Addendum 52.212-2 provides proposal Evaluation information and therefore must have different verbiage.The table on page 28 and the detailed instructions for each volume link the volumes to the evaluation factors.

46 4-Sep-25 General Request the Government identify the location Offerors should include signed letters of commitment from subcontractors.

Signed Letters of Commitment from all proposed key subcontractors shall be included in Volume 1, Mandatory Documentation. Offerors should create a clearly labeled subsection for these letters if more than one. See new language in VOL 1 Mandantory Documentation in revised

ADDENDUM TO FAR 52.212-1.

47 4-Sep-25 General Please confirm that letters of commitment are excluded from page constraints identified in the solicitation.

This is confirmed. Letters of Commitment are excluded from the page limitations applied to the Technical Approach Narrative.

48 4-Sep-25 Att 1_SOW, Part 3 4 1.0 Request the Government provide Offerors with the typical approval duration from Third Party

Agencies for the contraints identified.

SOW 2.3 Design Submittals - The typical duration in the worst case scenario is 90 days. The contract grants 100 days. The Government cannot provide definitive or estimated approval timelines for third-party entities, including independent Italian government agencies. Accordingly, offerors are solely responsible for conducting their own due diligence and factoring realistic timelines for all necessary permits and approvals into their proposed project execution plan and schedule. The realism of the proposed schedule, including these third-party dependencies, will be a factor in the technical evaluation

49 4-Sep-25 Amendment

Solicitation

30 Vol III Please confirm that Offerors providing relevant project experience from a committed key subcontractors with a letter of commitment will enable the Government to assess as Offerors experience (i.e. team experience) and will receive a favorable evaluation for this Volume.

Yes, the Government evaluates the experience of the proposed team as a whole. Relevant experience from a committed key subcontractor will be considered as part of the Corporate Experience evaluation, provided the following conditions are met:

The subcontractor is proposed to perform a significant or critical aspect of the work.

A letter of commitment from the subcontractor is included in the proposal.

The experience cited is directly relevant to the scope of work the subcontractor is proposed to perform.

The final evaluation rating will be based on the overall relevance and quality of the combined experience of the prime contractor and its key

50 4-Sep-25 Att 1 SoW, Part 3 2

In the SoW on Part 3 Para 1.0 Project Description is mentioned that Longare Base is already equipped with an MGC, which will require a fully compatible upgrade to the existing system to implement and optimize the new BESSs. Offeror request to know the brand of the System present on the site, receiving the topological and wiring diagrams and the narrative/sequence of operations as well

Longare MGC is not yet operational. The MGC has the preliminary configuration in non-redundant platform and it is based on an ABB Optimax temporary license, containing optimization capabilities, but it shall be specialized and configured in redundant platform for Longare Microgrid. Wiring and topological diagrams will be sent in a new Zip folder named Attachement 01.The narrative of the description/sequence of operations is already described in SOW D503006 (page 24); it needs to be developed to adapt it to the configuration of the new Micro Grid with the requied permanent license.

51 4-Sep-25 General, Time extension

Contractor request for a 2- week time extension to allow adequate time to review solicitation package and obtain offers from subcontractors due to delayed receipt of drawings and other missing information in the documents. We require all technical question to be answered by the Government in order to engage with our engineering team and develop the technical narrative.

RFQ has been extended to 22 SEPT 2025

52 4-Sep-25 Design 24, 38, 42, and

Looking the conceptual design drawings received with the Amendment1 we note that in the event of a power failure of the commercial line, the BESS will have to directly power the critical loads without load interruption and will have to counter-power the microgrid. In this regard, we need to know what is the acceptable power failure time frame of the no-critical loads in counter-powering the microgrid.

In the event of a power interuption from the utility's network, the BESS will have to instantaneuosly support all loads connected to the substations. Moreover, after approximately 30 seconds, both (400kVA each) generators located in Bldg 40 will start automatcally and the BESS/generators will share the installtions load. Upon the generators picking up the entire installation load, the BESS will transiotion to idle mode.

53 4-Sep-25 Solicitation 23 of 48 52.211-10

The solicitation provides a 332 calendar date while Attachment 1, SOW para. 2.3 identifies a total design time of 242 calendar days. While we understand the design schedule may be accelerated if approved by the COR, this would leave an Offeror 90 days to perform construction, install, and connect the BESS systems. Based on our exerience, procurement/delivery of the BESS system alone takes upwards of 8 months. A realistic period of performance for a project of this size and scope should reflect 664 calendar days to ensure design, procurement, delivery, installation, connection, and testing are performed efficiently.

Request the Government change the 332 calendar date to 664 calendar days

The Government finds acceptable a a 6-month extension for the construction period (not design). Therefore the total of days for this project will be 242 calendar days for design (no change) and 270 (vs 90 days) days for construction (construction time is not referenced in the SOW), for a total of 512 calendar days.

54 04 Sep 2025 Environmental Consideration: REC - Battery Energy Storage System (BESS) at Longare Attachment 7: REC - Battery Energy Storage System (BESS) at Longare

CAN YOU PROVIDE THIS MISSING ATTACHMENT?

Will load B08-RFP_Atch1.8_SOW_REC - BESS at Longare Proponent Signed_20250725 into SAM.gov

55 04 Sep 2025

Two out of four intervention areas fall within the Vincolo Paesaggistico D.Lgs 42/2004, Vincolo Idrogeologico forestale R.D. 3267/1923 and the Vincolo di Destinazione Forestale (art.15 L.R.52/78).

The project also includes the installation of four lithium-ion battery energy storage systems (BESS).

Is ISO 14001:2015 environmental certification required for the company to participate in the tender given the presence of these constraints and hazardous elements?

If not, will the presence of an ISO 14001:2015-certified company have a greater

No, ISO 14001:2015 is not required for the company. Constraints will be properly managed by the DOR. Hazardous element surveys will be performed/managed by specialized laboratory firms as subcontractor of the main contractor.

No, the presence of an ISO 14001:2015 certified company will not have a greater impact on the assessment.

56 04 Sep 2025 Can you provide instructions on how to correctly fill out the Excel file "B08- RFP_Atch4_BidSchedule_20250804"?

B08-RFP_Atch4_BidSchedule_20250804 was replaced with a bid schedule for each location B08- RFP_Atch4_BidSchedule_CLIN0001_20250904 through B08- RFP_Atch4_BidSchedule_CLIN0004_20250904. Instructions are

57 04 Sep 2025 How many milliseconds of network failure are accepted for the BESS to take charge of privileged loads?

Per SOW Section D509090 ensure continuity of service without gaps or interruptions.

58 04 Sep 2025 What are the minimum warranty requirements for BESS?

The minimum warranty must be atleast 3-years for the defects in the appliances. The manufacturer may also extend the warranty. This factor will be considered in the technical evaluation.

59 04 Sep 2025 Should the 4 BESS units supply only the LV loads of their MV/LV substation, or should they also supply, in emergency situations, all the loads of the rest of the MV network in islanded operation (i.e., the part of MV grid downstream PI)?

Per SOW Rev. #1 Section D503006 In the event of a power failure from the utility's network, the BESS must be able to power the network in Island mode MV operation.

Q&A Log