Solicitation Amendment W912P926RA0010004 SF 30.pdf

PDF 5 MB Posted

Attached to
LOCK FOUNDATION AND SITE PREPARATION FOR LOCK and DAM 25 NAVIGATION ECOSYSTEM SUSTAINABILITY PROGRAM (NESP)
Solicitation number
W912P926RA001
Issued by

About this file

This is Amendment 0004 to Solicitation W912P926RA001, issued by the U.S. Army Corps of Engineers (W07P Endist St Louis, KO Contracting Division) on 10 April 2026. The amendment is effective 10 April 2026 and modifies the solicitation for Lock 25, Lock Foundation and Site Prep work. The hour and date for receipt of offers is not extended. Offerors must acknowledge receipt of this amendment prior to the deadline specified in the original solicitation or as amended, through one of three methods: completing items 8 and 15 and returning copies; acknowledging receipt on each offer copy; or via separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt at the designated location by the specified deadline may result in rejection of the offer.

The amendment adds Contract Line Item Number (CLIN) 0020 for Separator Wall Backfill to the pricing schedule and modifies technical specifications and drawings. Specific changes include revisions to Section 00 08 00 (Order and Coordination of Work, Environmental, Sturgeon Spawning); Section 01 22 00 (Furnish Combi-Wall/Separator Wall measurement and addition of measurement and payment paragraphs for Separator Wall Backfill); Section 31 62 17 (Penetration Criteria); and Section 35 20 23 (Dredged Sand Fill for Lock Foundation). Drawing sheets GI002, GC100, CG203, and CG204 have been updated. The attachment list was revised to replace Amendment 0003 00 00 10 Pricing Schedule with Amendment 0004 00 00 10 Pricing Schedule and add new amendment specifications and plans documents dated 9 April 2026. All other terms and conditions of the original solicitation remain unchanged and in full force and effect.

View the file

Other files

File Type Posted
Solicitation Amendment W912P926RA0010006 SF 30.pdf PDF
B3MRLD25202402-PLAN_SET_AMND-2026-04-14-Amendment 0005 Plans.pdf PDF
Solicitation Amendment W912P926RA0010005 SF 30.pdf PDF
B3MRLD25202402-PLAN_SET_AMND-2026-04-08-Amendment 0004 Plans.pdf PDF
Amendment 0004 Specifications.pdf PDF
ProjNet Bidder Inquiries and Replies as of 8 April.pdf PDF
Amendment 0004 00 00 10 Pricing Schedule.pdf PDF
PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS Amd 0003.pdf PDF
EVALUATION FACTORS FOR AWARD Amd 0003.pdf PDF
Amendment 0003 00 00 10 Pricing Schedule.docx DOCX document
B3MRLD25202402-PLAN_SET_AMND-2026-03-27-Amendment 0003 Plans.pdf PDF
Amendment 0003 Specifications.pdf PDF
Solicitation Amendment W912P926RA0010003 SF 30.pdf PDF
Pre Bid Site Visit Sign In Sheet.pdf PDF
ProjNet Bidder Inquiries and Government Replies as of 27 Mar 2026.pdf PDF
PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS Amd 0002.pdf PDF
Solicitation Amendment W912P926RA0010002 SF 30.pdf PDF
W912P926RA001 Attachment 0003 PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS.pdf PDF
Solicitation Amendment W912P926RA0010001 SF 30.pdf PDF
W912P926RA001 Attachment 0004 - EVALUATION FACTORS FOR AWARD.pdf PDF
W912P926RA001 Attachment 0003 - PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS.pdf PDF
W912P926RA001 Attachment 0008 - Appendix C Small Business Participation Commitment Document.pdf PDF
W912P926RA001 Attachment 0005 - 00 00 10 Scour Repair Advance Bid Schedule.pdf PDF
W912P926RA001 Attachment 0001 - Lock Foundation and Site Prep As-Advertised Specs.pdf PDF
W912P926RA001 Attachment 0012 - Wage Determination.pdf PDF
W912P926RA001 Attachment 0007 - Appendix B Subcontractor Consent.pdf PDF
W912P926RA001 Attachment 0009 - Appendix D Subcontractor Letter of Commitment.pdf PDF
W912P926RA001 Solicitation.pdf PDF
W912P926RA001 Attachment 0004 - EVALUATION FACTORS FOR AWARD.pdf PDF
W912P926RA001 Attachment 0010 - Appendix E DoD Checklist for Reviewing Subcontracting Plans.pdf PDF
W912P926RA001 Attachment 0006 - Appendix A Past Performance Questionnaire.pdf PDF
W912P926RA001 Attachment 0011 - Appendix F Small Business Participation Commitment Progress Quarterly Report.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section A - Solicitation/Contract Form

The following additions have been made:

AMENDMENT 0004 NARRATIVE

W912P926RA0010004

pricing schedule which reflects:

- The addition of CLIN 0020 Separator Wall Backfill

SECTION 00 08 00 - Delete this section and replace with the attached like-numbered section which reflects changes to paragraph 1.16.2.d. ORDER AND COORDINATION OF WORK, ENVIRONMENTAL, STURGEON SPAWNING.

SECTION 01 22 00 - Delete this section and replace with the attached like-numbered section which reflects changes to paragraph 1.5.1. FURNISH COMBI-WALL (SEPARATOR WALL), MEASUREMENT.

the addition of measurement and payment paragraphs for 1.22. SEPARATOR WALL BACKFILL

TECHNICAL PROVISIONS

SECTION 31 62 17 - Delete this section and replace with the attached like-numbered section which reflects the changes to paragraph 3.1.5.2. PENETRATION CRITERIA.

SECTION 35 20 23 - Delete this section and replace with the attached like-numbered section which reflects the changes to paragraph 3.3.7.2. DREDGED SAND FILL FOR LOCK FOUNDATION.

DRAWINGS

The following drawing sheets have been updated per this amendment:

GI002, GC100, CG203, CG204

(End of AMENDMENT 0004 NARRATIVE)

Section J - List of Attachments

The attachments table has changed from:

W912P926RA0010004

AMENDMENT 0004 NARRATIVE

Specifications and drawings for: LOCK 25, LOCK FOUNDATION AND SITE PREP are amended as follows:

GENERAL PROVISIONS

PRICING SCHEDULE, SECTION 00 00 10 - Delete the original pricing schedule and replace with the attached revised

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0001 Lock Foundation and Site Prep As-Advertised Specs

Specification 23 Feb 2026 Attach ment

No

0002 Plans Specification 23 Feb 2026 Attach ment

No

0003 PROPOSAL

SUBMISSION I

NSTRUCTION

S

CONDITIONS

AND

NOTICES TO

OFFERORS

Amd 0003

Proposal 27 Mar 2026 Attach ment

No

0004 EVALUATION

FACTORS

FOR AWARD

Amd 0003

Award Evaluation 27 Mar 2026 Attach ment

No

0005 Amendment 0003 00 00 10 Pricing Schedule

Pricing Schedule 27 Mar 2026 Attach ment

No

0006 Appendix A – Past Performance Questionnaire

Drawings 23 Feb 2026 Attach ment

No

0007 Appendix B – Subcontractor Consent

Drawings 23 Feb 2026 Attach ment

No

0008 Appendix C – Small Business Participation Commitment Document

Drawings 23 Feb 2026 Attach ment

No

0009 Appendix D – Subcontractor Letter of Commitment

Drawings 23 Feb 2026 Attach ment

No

0010 Appendix E – Drawings 23 Feb 2026 Attach No

DoD Checklist for Reviewing Subcontracting Plans ment

0011 Appendix F – Small Business Participation Commitment Progress Quarterly Report

Drawings 18 Nov

Attach ment

No

0012 Wage Determination

Drawings 09 Feb 2026 Attach ment

No

0013 Pre Bid Site Visit Sign In Sheet

Pre-Bid Site Visit Sign-In Sheet 27 Mar 2026 Attach ment

No

0014 B3MRLD25202

402-PLAN_SE

T_AMND-2026-

03-27- Amendment 0003 Plans

Drawings 27 Mar 2026 Attach ment

No

0015 Amendment Specifications

Specification 27 Mar 2026 Attach ment

No

0016 ProjNet Bidder Inquiries and Government Replies as of 27 Mar 2026

Bidder Inquiries and Government Replies Amendment 0003

27 Mar 2026 Attach ment

No

To:

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0001 Lock Foundation and Site Prep As-Advertised Specs

Specification 23 Feb 2026 Attach ment

No

0002 Plans Specification 23 Feb 2026 Attach ment

No

0003 PROPOSAL Proposal 27 Mar 2026 Attach No

SUBMISSION I

NSTRUCTION

S

CONDITIONS

AND

NOTICES TO

OFFERORS

Amd 0003 ment

0004 EVALUATION

FACTORS

FOR AWARD

Amd 0003

Award Evaluation 27 Mar 2026 Attach ment

No

0005 Amendment 0004 00 00 10 Pricing Schedule

Pricing Schedule 10 Apr 2026 Attach ment

No

0006 Appendix A – Past Performance Questionnaire

Drawings 23 Feb 2026 Attach ment

No

0007 Appendix B – Subcontractor Consent

Drawings 23 Feb 2026 Attach ment

No

0008 Appendix C – Small Business Participation Commitment Document

Drawings 23 Feb 2026 Attach ment

No

0009 Appendix D – Subcontractor Letter of Commitment

Drawings 23 Feb 2026 Attach ment

No

0010 Appendix E – DoD Checklist for Reviewing Subcontracting Plans

Drawings 23 Feb 2026 Attach ment

No

0011 Appendix F – Small Business Participation Commitment Progress Quarterly Report

Drawings 18 Nov

Attach ment

No

0012 Wage Determination

Drawings 09 Feb 2026 Attach ment

No

0013 Pre Bid Site Visit Sign In Sheet

Pre-Bid Site Visit Sign-In Sheet 27 Mar 2026 Attach ment

No

0014 B3MRLD25202

402-PLAN_SE

T_AMND-2026-

03-27- Amendment 0003 Plans

Drawings 27 Mar 2026 Attach ment

No

0015 Amendment Specifications

Specification 27 Mar 2026 Attach ment

No

0016 ProjNet Bidder Inquiries and Government Replies as of 27 Mar 2026

Bidder Inquiries and Government Replies Amendment 0003

27 Mar 2026 Attach ment

No

0017 Amendment Specifications

Drawings 09 Apr 2026 Attach ment

No

0018 B3MRLD25202

402-PLAN_SE

T_AMND-2026-

04-08- Amendment 0004 Plans

Drawings 09 Apr 2026 Attach ment

No

0019 ProjNet Bidder Inquiries & Replies as of 8 April

Drawings 09 Apr 2026 Attach ment

No

The following contract documents were added:

Amendment 0004 00 00 10 Pricing Schedule Amendment 0004 Specifications B3MRLD25202402-PLAN_SET_AMND-2026-04-08-Amendment 0004 Plans ProjNet Bidder Inquiries & Replies as of 8 April

The following contract documents were deleted:

Amendment 0003 00 00 10 Pricing Schedule

The following contract documents Page Counts were changed:

DOCUMENT PAGE COUNTS

DOCUMENT NAME FROM TO

Amendment 0004 00 00 10 Pricing Schedule none

IDCode: J
Page: 1
Pages: 13
AmendNo: 0004
EffDate: 10 APR 2026
ReqNo:
ProjNo: PANMVD-24-P-0000 004319
IssCode: W912P9
AdmCode:
IssuedBy: W07V ENDIST ST LOUIS

KO CONTRACTING DIVISION, 1222 SPRUCE STREET

SAINT LOUIS, MO 63103-2833

UNITED STATES

ANGIE GRIMES, EMAIL: ANGIE.L.GRIMES@USACE.ARMY.MIL TELEPHONE: 314 331-8965

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912P926RA001
SolDate: 23 FEB 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is to make the changes described in the Amendment 0004 Narrative. All other terms and conditions remain unchanged.
ContNameTitle:
CoNameTitle: WHITNEY R DEE
ContDate:
CODate: 10 APR 2026

File details come from the government source that posted it. Updated .