Amendment 0004 Specifications.pdf

PDF 198 KB Posted

Attached to
LOCK FOUNDATION AND SITE PREPARATION FOR LOCK and DAM 25 NAVIGATION ECOSYSTEM SUSTAINABILITY PROGRAM (NESP)
Solicitation number
W912P926RA001
Issued by

About this file

This document is Amendment 0004 to a federal construction contract for Lock and Dam No. 25 modernization work, issued by the U.S. Army Corps of Engineers (USACE), St. Louis District. The amendment modifies sections covering special contract requirements, measurement and payment, and technical specifications for steel pipe piles and dredging operations.

The contract requires comprehensive construction services including mobilization/demobilization, erosion and sediment control, deflector wall installation, steel pipe pile furnishing and installation (48-inch diameter), combi-wall (separator wall) installation with backfill, articulating fabric concrete mattress placement, staging area fill, dredge material placement for lock foundation, alluvium and riprap excavation, scour protection stone placement, sanitary outfall piping, land-based site work, timber cribbing demolition, site monitoring instrumentation, and navigation assist vessel services. Steel pipe piles must conform to ASTM A 139/A 139M Grade D or E specifications with extensive nondestructive testing, charpy v-notch testing, macroetch testing, tension testing, flattening tests, and guided-bend testing requirements. Dredging specifications require preliminary and final hydrographic surveys, quality control monitoring with electronic positioning, environmental compliance measures (particularly for mussel and sturgeon habitat protection), and placement tolerances for fill material at specified elevations. The contract includes detailed environmental protection requirements addressing bat habitat clearing windows, bald eagle nests, mussels, sturgeon spawning, and invasive species prevention. Payment is structured on a job basis for most items with unit pricing for dredging (cubic yard) and some structural elements. The work must accommodate ongoing lock and dam operations, maintain navigation safety, and comply with all federal, state, and local environmental regulations throughout contract execution.

View the file

Other files

File Type Posted
Solicitation Amendment W912P926RA0010006 SF 30.pdf PDF
B3MRLD25202402-PLAN_SET_AMND-2026-04-14-Amendment 0005 Plans.pdf PDF
Solicitation Amendment W912P926RA0010005 SF 30.pdf PDF
Amendment 0004 00 00 10 Pricing Schedule.pdf PDF
Solicitation Amendment W912P926RA0010004 SF 30.pdf PDF
ProjNet Bidder Inquiries and Replies as of 8 April.pdf PDF
B3MRLD25202402-PLAN_SET_AMND-2026-04-08-Amendment 0004 Plans.pdf PDF
Solicitation Amendment W912P926RA0010003 SF 30.pdf PDF
Pre Bid Site Visit Sign In Sheet.pdf PDF
EVALUATION FACTORS FOR AWARD Amd 0003.pdf PDF
Amendment 0003 00 00 10 Pricing Schedule.docx DOCX document
B3MRLD25202402-PLAN_SET_AMND-2026-03-27-Amendment 0003 Plans.pdf PDF
Amendment 0003 Specifications.pdf PDF
ProjNet Bidder Inquiries and Government Replies as of 27 Mar 2026.pdf PDF
PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS Amd 0003.pdf PDF
PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS Amd 0002.pdf PDF
Solicitation Amendment W912P926RA0010002 SF 30.pdf PDF
Solicitation Amendment W912P926RA0010001 SF 30.pdf PDF
W912P926RA001 Attachment 0003 PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS.pdf PDF
W912P926RA001 Attachment 0004 - EVALUATION FACTORS FOR AWARD.pdf PDF
W912P926RA001 Solicitation.pdf PDF
W912P926RA001 Attachment 0001 - Lock Foundation and Site Prep As-Advertised Specs.pdf PDF
W912P926RA001 Attachment 0003 - PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS.pdf PDF
W912P926RA001 Attachment 0007 - Appendix B Subcontractor Consent.pdf PDF
W912P926RA001 Attachment 0009 - Appendix D Subcontractor Letter of Commitment.pdf PDF
W912P926RA001 Attachment 0012 - Wage Determination.pdf PDF
W912P926RA001 Attachment 0004 - EVALUATION FACTORS FOR AWARD.pdf PDF
W912P926RA001 Attachment 0006 - Appendix A Past Performance Questionnaire.pdf PDF
W912P926RA001 Attachment 0008 - Appendix C Small Business Participation Commitment Document.pdf PDF
W912P926RA001 Attachment 0010 - Appendix E DoD Checklist for Reviewing Subcontracting Plans.pdf PDF
W912P926RA001 Attachment 0011 - Appendix F Small Business Participation Commitment Progress Quarterly Report.pdf PDF
W912P926RA001 Attachment 0005 - 00 00 10 Scour Repair Advance Bid Schedule.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0004

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 08 00

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 WORK AREAS

1.2 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS

1.3 DAMAGE TO WORK.

1.4 QUANTITY SURVEYS

1.5 ELECTRONIC SUBMISSION OF DAVIS-BACON CERTIFIED PAYROLL

1.6 PARTIAL PAYMENT

1.7 CERTIFICATES OF COMPLIANCE

1.8 PURCHASE ORDERS

1.9 ENVIRONMENTAL LITIGATION

1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.11 SUBCONTRACTS

1.12 REQUIRED INSURANCE

1.13 PROTECTION OF MATERIAL AND WORK

1.14 CONTAMINATION OF WATER

1.15 COMMERCIAL WARRANTY

1.16 ORDER AND COORDINATION OF WORK

1.16.1 General

1.16.2 Environmental

1.16.3 Work Areas

1.16.4 River Work

1.16.5 Sequencing

1.16.6 Coordination

1.17 SUBMITTALS

1.18 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING

PLANT

1.19 EMERGENCY ALARMS AND SIGNALS

1.20 USE OF MECHANIZED EQUIPMENT ON FLOATING PLANT

1.21 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002

1.22 SIGNAL LIGHTS

1.23 INSPECTION FACILITIES

1.24 CONTRACTOR PERFORMANCE EVALUATIONS

1.25 SECURITY REQUIREMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

DOCUMENT 00 08 00 Page 1

SECTION 00 08 00

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 WORK AREAS

In accordance with the Contract Clause entitled, "Operations and Storage Areas", and subject to the approval of the Contracting Officer and the restrictions imposed by SECTION 01 11 30 - ENVIRONMENTAL PROTECTION, of the Technical Provisions, the Contractor will be allowed use of Government-controlled land within the construction limits shown on the drawings or as specified herein.

1.2 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS

a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not move or disturb any public utilities or private improvements. Such removals, alterations, and/or relocations, where necessary, will be made by others. The locations shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.

b. The attention of the Contractor is directed to the possibility that public utilities or private improvements may be encountered within the construction limits, some of which may be buried, and the existence of which is presently not known. Should any such utilities or improvements be encountered, the Contractor shall immediately notify the Contracting Officer so that a determination may be made as to whether they shall be removed, relocated, or altered. After such determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required and an equitable adjustment will be made. In the event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latters' removal, alteration, or relocation operations.

1.3 DAMAGE TO WORK.

The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause entitled "Permits and Responsibilities." However, if in the judgment of the Contracting Officer any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or job prices as fixed and established in the contract. If in the opinion of the Contracting Officer there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to the Contract Clause entitled, "Changes," of the contract will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), DOCUMENT 00 08 00 Page 2 utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

1.4 QUANTITY SURVEYS

The Contractor shall have a Professional Land Surveyor registered in the state the work is being accomplished conduct pre- and post-construction bathymetric surveys to verify work is completed to lines and grades shown on the drawings. Surveys shall be performed in the presence of the Contracting Officer and all field survey notes be initialed by the Government Representative and furnished to the Government within 24 hours unless directed otherwise by the Contracting Officer.

1.5 ELECTRONIC SUBMISSION OF DAVIS-BACON CERTIFIED PAYROLL

a. Provide a commercially available electronic system to process and submit certified payrolls electronically to the Government. The Davis-Bacon Act establishes the requirements for preparing, processing, and providing certified labor payrolls.

b. Provide access for all services required to provide receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with the Davis-Bacon Act and related statutes. When using an electronic Davis-Bacon payroll service, it must be used to prepare, process, and maintain the relevant payrolls and basic records for all work under the construction contract. The electronic payroll service must be capable of preserving the payroll and related basic records for the required three years after contract completion. Obtain and provide electronic system access, including electronic review to the Government, as required to comply with the Davis-Bacon Act and related statutes through the duration of the construction contract.

c. The electronic payroll processing system must meet the following basic functional criteria:

1. Commercially available

2. Compliant with appropriate Davis-Bacon Act payroll provisions in the FAR

3. Able to accommodate the required number of employees and subcontractors that will be employed under the contract

4. Capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export into an Excel spreadsheet to be imported into the Contractor's mode of the Resident Management System 3.0 (see section 01 45 00.15 10 )

5. Demonstrate security of data and data entry rights

6. Able to produce contractor-certified electronic versions of weekly payroll data

7. Able to identify erroneous entries and track the date/time of all versions of the certified Davis-Bacon Act payrolls submitted to the Government over the life of the contract; and

DOCUMENT 00 08 00 Page 3

8. Capable of generating a durable record copy in Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during the contract closeout.

d. All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service shall be included in the Contractor's price for the overall work of the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.

1.6 PARTIAL PAYMENT

At the discretion of the Contracting Officer, partial payment will be made for equipment delivered and stored on site or off site providing such storage is in accordance with the provisions of these specifications and the Contractor furnishes satisfactory evidence that title to such equipment has been acquired and that it will be utilized on the work covered by these specifications. Partial payment is defined as the invoice amount plus shipping costs. If the equipment is stored off site, the Government shall have the right to inspect the equipment.

1.7 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall include the signature and title of an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from responsibility for furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.8 PURCHASE ORDERS

Purchase orders for other than stock materials showing the firm names and addresses and list of material shall be furnished to the Contracting Officer or an authorized representative as soon as issued.

1.9 ENVIRONMENTAL LITIGATION

a. If the performance of all or any part of the work is ordered by a court of competent jurisdiction to be suspended, delayed, or interrupted as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a Subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the Contract Clause

DOCUMENT 00 08 00 Page 4 entitled "Suspension of Work".

b. The term "environmental litigation", as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled, "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the baseline for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORKDAYS BASED ON A 5 DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

2 2 3 4 5 4 4 3 3 2 2 2

c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor must record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled workday.

The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".

DOCUMENT 00 08 00 Page 5

d. During high water events as described in the paragraph titled "HIGH WATER", the Contractor shall record on the daily QC report, the occurrence of the event and resultant impact to normally scheduled work. A time extension modification will not be issued for unusually severe weather if the occurrence is concurrent with a high water impact event.

1.11 SUBCONTRACTS

In accordance with the Contract Clause entitled "Subcontracts", the Contractor shall, within seven days after the award of any subcontract by the Contractor or a Subcontractor, deliver to the Contracting Officer an electronic copy of a completed Standard Form 1413 with the original signatures of both parties.

1.12 REQUIRED INSURANCE

a. As required by the Contract Clause entitled "Insurance-Work on a Government Installation", the Contractor shall within 15 days after receipt of Notice of Award and prior to the commencement of work, furnish to the Contracting Officer, a written statement of required insurance as evidence of the following minimum insurance:

(1) Workmen's Compensation . Amounts required by applicable jurisdictional statutes.

(2) Employer's Liability Insurance . $100,000

(3) Comprehensive General Liability Insurance .

Bodily Injury - $500,000 per occurrence

(4) Comprehensive Automobile Insurance .

Bodily Injury - $200,000 each person $500,000 each accident Property Damage - $ 20,000 each accident

b. Statements of required insurance shall be submitted electronically or to the following address:

Department of the Army St. Louis District, Corps of Engineers Central Area Office; CEMVS-EC-CA 1222 Spruce Street St. Louis, Missouri 63103

1.13 PROTECTION OF MATERIAL AND WORK

The Contractor shall at all times protect and preserve all materials, supplies, and equipment of every description (including property which may be Government-furnished or owned) and all work performed. All reasonable requests of the Contracting Officer to enclose or specially protect such property shall be complied with. If, as determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payments due to the Contractor.

DOCUMENT 00 08 00 Page 6

1.14 CONTAMINATION OF WATER

In addition to the requirements set forth in SECTION 01 11 30 , paragraph Protection of Water Resources, the Contractor shall take positive protective measures to prevent spillage of potential pollutant materials such as fuel, emulsion materials, chemicals etc., from storage containers or equipment, into lakes or tributary waters. Such positive protective measures may include, but are not limited to, the following:

(1) A berm enclosure of sufficient capacity to contain such materials.

(2) Security measures to prevent acts of vandalism which could result in spillage of such materials (fences, guards, etc.).

(3) Storage of such materials in an area where the terrain would preclude leakage into lake or tributary waters.

(4) Utilization of secure Government storage areas if the Contracting Officer indicates such space is available. No storage past immediate needs (2 days) without the consent of the Contracting Officer.

The Contractor shall submit its proposals for implementing the above provisions in accordance with SECTION 01 11 30 , paragraph Environmental Protection Plan.

1.15 COMMERCIAL WARRANTY

The Contractor agrees that the standard commercial equipment furnished under this contract shall be covered by the most favorable commercial warranties the manufacturer gives to any customer for such equipment, and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the Government by any other clause of this contract. The Contractor shall furnish an electronic copy of the warranties to the Contracting Officer.

1.16 ORDER AND COORDINATION OF WORK

The Contractor may start and complete the work in such order and sequence as desired subject to compliance with the following paragraphs. The work tasks, milestones, and lock closure periods shall be entered into the Contractor's network analysis and monitored throughout the contract duration. The Contractor shall strictly adhere to specified Approved Lock Closure Periods. The specified duration of the closure periods will not be lengthened. The Contractor is required to obtain and coordinate the necessary resources to perform the designated work in the allotted closure periods.

1.16.1 General

a. The Contractor is advised that other contracts may be ongoing at the project site during the life of this contract. Coordinate work with the other Contractors and cooperate with the Contracting Officer's Representative and other Contractors to the fullest extent possible so as to not interfere with or hinder the progress of other contracts. The Contracting Officer will have the final decision in the event of a controversy between Contractors.

b. Datum. The existing lock facility was built utilizing the National Geodetic Vertical Datum of 1929 (NGVD29). The project is now using the

DOCUMENT 00 08 00 Page 7 newer vertical datum of North American Vertical Datum of 1988 (NAVD88).

The elevations on historic mapping will differ by the following conversion: NAVD88 elevation = NGVD29 elevation - 0.40 ft. The water surface elevation or pool stage has been historically operated and reported as an elevation according to NGVD29. In historical context, pool stage equated to the NGVD29 elevation. However, once the pool gage datum was converted to NAVD88, it was decided that for operational simplicity, the project would continue to operate the pool according to NGVD29 but would designate this value as "stage" and not elevation. In the present context, pool stage does NOT equate to elevation. For example, at a full pool stage of 434.0 feet, the water surface elevation is 433.6 feet NAVD88.

c. River Bottom Elevation Measurements. The Contractor shall measure the river bottom elevations prior to the start of any dredging or excavation work in accordance with Section 01 32 23.00 08 SURVEY AND ALIGNMENT

CONTROL.

The Contractor shall survey the final river bottom and scour protection elevations in accordance with Section 01 32 23.00 08 SURVEY AND ALIGNMENT CONTROL. The final survey is for verification of the conditions of the separator wall, the riprap section, and lock foundation backfill and to serve as an as-built condition.

The Contractor shall provide a safe working environment for hydrographic data collection where survey may be obtained to the level of accuracy required for the project.

d. All elevations and dimensions shall be verified in the field before work begins. The Contractor is responsible for confirming all dimensions prior to shop drawing preparation and material fabrication.

e. The Contractor shall monitor fluctuations of tailwater elevation and make tie off adjustments such that the floating plant shall not damage the piers. At all times when work is not in progress, the Contractor shall be required to have a 24-hour telephone number where the Government may reach a representative of the Contractor to notify of any problems with the floating plant. The representative must be available to be on site to attend to work barge(s) within 60 minutes of a phone call from the Government 24 hours a day, 7 days a week. The Contractor shall post and keep current a list of telephone numbers for emergency action. The Contractor shall submit the contingency plans for addressing headwater and/or tailwater fluctuations to the Contracting Officer for approval at least 7 days before mobilization.

f. Any disposal sites proposed by the Contractor that are not already identified by the Government as approved for this project are subject to approval by the Contracting Officer. This approval process may require the Government to prepare an environmental assessment at no cost to the Contractor. This may require additional review time and may result in additional requirements to offset environmental effects associated with the use of the site. Proposed sites which involve the excavation or placement of material within a cultural site, wetland, wooded area, floodplain, or other environmentally sensitive area will not be approved.

1.16.2 Environmental

a. Bat Habitat. All tree clearing must be coordinated with the USACE environmental compliance section in advance. In Missouri, all tree clearing must be completed from 01 November thru 31 March. No tree

DOCUMENT 00 08 00 Page 8 clearing is permitted in Missouri from 1 April thru 31 October unless otherwise approved by the contracting officer. Approval by the contracting officer may be granted after appropriate coordination by the St. Louis District with the U.S. Fish and Wildlife Service has been conducted, and it is determined that removal can be performed without impacting trees or habitat suitable for protected bat species.

b. Bald Eagle Nests. Should any bald eagle nest be noted within 660' of the project area, the contractor shall immediately contact the contracting officer to determine if any eagle nest buffer zone restrictions will be required for construction operations. Approval by the contracting officer may be granted after appropriate coordination by the St. Louis District with the U.S. Fish and Wildlife Service has been conducted, and it is determined whether an eagle take permit and/or nest buffer zone restrictions are required.

c. Mussels. All work sites must be coordinated with the USACE environmental compliance section in advance for the presence of protected mussel species. Approval by the contracting officer may be granted after appropriate coordination by the St. Louis District with the U.S. Fish and Wildlife Service and state agencies has been conducted, and it is determined that work can be performed without impacting protected mussel beds or habitat.

There shall be no spudding, anchoring, staging, or otherwise disturbing the riverbed at mussel bed locations (see maps at the end of this section). Activities shall not physically disturb mussel beds, nor result in increased sedimentation near mussel beds.

d. Sturgeon Spawning. All work sites must be coordinated with the USACE environmental compliance section in advance for the presence of suitable sturgeon spawning habitat and/or conditions. Approval by the contracting officer may be granted after appropriate coordination by the St. Louis District with the U.S. Fish and Wildlife Service and state agencies has been conducted, and it is determined that work can be performed without impacting sturgeon spawning and/or spawning sites.

The LD25 Illinois abutment is considered an environmentally sensitive area for the endangered Lake Sturgeon. No vessel or barge traffic, staging, spudding, anchoring, or otherwise disturbing the riverbank or riverbed at potential sturgeon spawning sites shall occur within the designated area (LD25 Illinois abutment to 1,200ft downstream on the Illinois side) between 01 April and 15 May annually. Activities in the vicinity of the Illinois tailwaters shall not physically disturb spawning sites, nor result in increased sedimentation near spawning sites between 01 April and 15 May annually. In addition, between 01 April and 15 May annually, tailwater velocities may be heightened along the IL abutment. Usage of the IL abutment may be requested from the Government outside of the 01 April to 15 May time period for ongoing construction activities.

e. Invasive Species.

(1) Invasive mussels and fishes have infested many bodies of water in the United States and can be unknowingly transported by vessels (barges, boats, tugs, etc.), boat trailers, and other equipment that is used in waterways. Contractor shall follow all State inspections and requirements to assist in the prevention of introduction and spread of aquatic nuisance species in rivers, streams, and lakes.

DOCUMENT 00 08 00 Page 9

(2)Inspect and remove weed seeds, plant parts, and/or zebra mussels on all construction equipment, vehicles, and trailers prior to bringing them onto the job site. Wash, including the undercarriage, if necessary.

(3) Inspect and remove weed seeds, plant material and/or zebra mussels on all construction equipment before being taken off the job site. If necessary, use an air compressor to blow clean this material. This should be done where equipment is unloaded or loaded, or at areas that can be easily monitored such as a road, trail head, or parking lot.

(4) Do not clean equipment, vehicles, or trailers in waterways.

1.16.3 Work Areas

a. The Contractor must work around and not conflict with Government operations to include but not limited to deliveries, Government personnel traveling to and within the operating project, the operating dam, the operating lock, and maintenance activities. Work shall not impact navigation or the operating lock. Contractor shall coordinate with lock personnel when construction activities may impact space on the intermediate wall or other areas used for Government operations. Where lock operations are performed, construction activities shall not pose any safety / operational hazards to lock personnel or navigating craft. All work activities shall be identified in the Contractor's work plan submittal for review and approval by the Contracting Officer to assure no adverse impacts to lock operations.

b. The Contractor shall designate a coordinator to assure that the construction work is coordinated with the operation of the lock and dam.

Lock and dam personnel will not accept deliveries, phone calls, or mail or deliver messages for the Contractor.

c. Construction limits will extend as shown on the drawings. Contractor personnel may cross the navigation lock upper and/or lower miter gate when the gates are closed to gain access to the construction limits. Only hand carried equipment shall be brought across the miter gates by Contractor personnel.

d. Parking areas for Contractor personnel, storage areas for Contractor materials and equipment, staging areas, work areas, areas of egress, and similar Contractor required work areas are available for use and shall be in locations as shown on the drawings and/or as designated by the Contracting Officer.

e. Contractor personnel shall not use Government owned and operated public facilities or similar structures within the project area. The Contractor shall provide its own temporary or portable facilities.

Temporary toilet facilities shall conform to paragraph 02.B of the U.S.

Army Corps of Engineers "Safety and Health Requirements Manual" EM 385-1-1.

f. Public Roadways. The Contractor shall maintain access for vehicular traffic on public roadways except as noted on the plans. Coordinate any temporary road closures or blockages with local police, fire, and EMS authorities as well as the governing agency having jurisdiction over the road.

g. Before beginning any construction activities, the Contractor shall

DOCUMENT 00 08 00 Page 10 record the existing conditions of all roads, staging areas, operating areas, and construction areas to be used under this contract by aerial photography/videography. The Contractor shall photo/video document physical structures within the construction limits. Upon completion of the project, the Contractor shall provide similar photographs/videos documenting restoration of the site. The Contracting Officer or Representative will be present during all recordings. One electronic copy of the existing conditions recording shall be provided to the Contracting Officer. Unless otherwise noted on the drawings, all property within the construction limits shall be restored to its pre-construction condition, following the completion of the project.

h. Security fencing and hand railing may be removed in work areas during construction as long as safety and security is maintained and replacement made to its original location and condition, including an approved method and type of touch up painting as necessary. Contractor proposals for modifying fencing and handrails shall meet requirements in EM 385-1-1 and be submitted for approval.

i. Access to the work site at Lock and Dam No. 25 is restricted.

Reasonable access to the site for the Corps of Engineers lock and dam personnel must be maintained at all times. Maintain Government roads and access with no interruptions to mail or deliveries to the site.

j. The Contractor will not be allowed access to the lock and dam control station house other than for coordination purposes.

k. The Contractor is responsible for providing a source of emergency backup power for the Contractor's operations and equipment that exceeds on-site power ratings to ensure critical operations can continue in the event of an electrical power disruption.

l. Utilities not shown or identified in the plans or specifications may be encountered by the Contractor during construction activities. Prior to construction, the Contractor shall submit a utility plan to locate, protect, relocate and restore utilities as required for approval by the Contracting Officer.

m. A simple span, prestressed concrete multi-girder bridge, identified as the Sandy Slough Bridge (Bridge No. CEPLMSMO-000001), provides vehicular traffic access to Lock & Dam 25. This structure is owned and operated by USACE. Previously performed load rating analysis results indicate this bridge meets criteria for AASHTO inventory and operating design loads as well as routine commercial traffic legal loads and no restrictive load posting is present at this time. If the Contractor intends to cross this bridge with any vehicles exceeding FHWA legal loads, the Contractor shall perform a permit load rating analysis, and results shall be submitted to the Government for approval. The permit load rating analysis shall be in accordance with the AASHTO Manual for Bridge Evaluation, Routine/Unlimited Crossings and performed by a licensed Professional Engineer as well as reviewed by an independent third-party licensed Professional Engineer. The submitted analysis shall include results of the permit load rating, detailed description of analysis procedures, axle loads and configuration of the proposed vehicle, explanation of any assumptions utilized, list of references and a complete set of computations supporting the results detailed in the report. The report shall be signed and sealed by both the Licensed Professional Engineer who performed the analysis and the independent third-party reviewer. Requests for original bridge design drawings, construction specifications, recent inspection reports and any

DOCUMENT 00 08 00 Page 11 other pertinent information needed to complete this analysis shall be submitted to the Contracting Officer.

The Government is required to inspect Sandy Slough Bridge every 2 years.

The next inspection is scheduled for 2026. The Government will be granted access and be given the ability to inspect the bridge for 2 days. The Government will coordinate this inspection with the Contractor and will give 30 days notice prior to inspection. The bridge will remain open during inspections.

n. The Contractor shall be responsible for snow and ice removal in the Contractor's access, work and parking areas as necessary to facilitate Contractor operations. Use of salt or corrosive agents shall not be permitted.

o. The Contractor is responsible for mowing within the construction limits.

p. Potable water will not be made available to the Contractor. The Contractor shall furnish all potable water.

q. Load Restrictions. The Contractor shall be aware of and adhere to the following lock load restrictions:

1. Existing Lock Walls. Weight limitations in the area behind the existing lock land wall shall be a maximum 40 tons within 50 feet of the existing lock chamber face of the land wall and maximum 150 tons beyond 50 feet from the existing lock chamber face of the land wall.

2. Protection of Existing Lock. Lock wall surfaces, grating, work platforms, concrete covers, and miscellaneous covers that are not replaced under this contract shall be protected against damage by the Contractor.

The contractor is responsible for protecting in a manner they see fit such as limiting loads and or cover plates to prevent damage. The contractor is responsible to repair or replace any damage at no additional cost to the Government.

1.16.4 River Work

a. Diving. Diving requirements are in U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, Chapter 30. Water movement due to river current presents hazards to divers and the need for general precautions for all construction activities. All work requiring divers is coordinated and accepted by the Contracting Officer and the MVS District Diving Coordinator (DDC). Pre-Diving meetings and the Diving Plan are in accordance with the Corps of Engineers Safety Manual EM 385-1-1.

Prior to submitting bids on this contract, obtain copies of this manual and plan procedures and staffing requirements accordingly.

Submit the following at the time of contract award:

1. Safe Practices Manual

2. Emergency Management Plan (Diving Specific)

3. Hazardous Energy Control Plan (Diving Specific)

4. Sample Equipment Inspection Checklist

5. Sample Dive Log

6. Sample Pre-Dive/Post-Dive Checklist

7. Sample ENG 1927-R Safe Clearance Form

8. Sample ENG 6226 Form

DOCUMENT 00 08 00 Page 12

Submitted the following 3 months prior to any diving operations:

1. Dive Operations Plan

2. Site Specific Emergency Management Plan

3. Site Specific Hazardous Energy Control Plan (If applicable)

4. Site Specific Internal Safety Procedures, Checklists, and Inspection Forms

5. Personnel Qualifications

6. Dive Equipment Certification (Dive Hats, Bailouts, Compressors, Umbilical, 02, etc.)

7. Dive Platform Information

8. Activity Hazard Analysis (Diving)

9. OSHA 29 CFR 1910,Subpart T

10. Navy Dive Tables

11. ENG 1927-R Safe Clearance Form

12. ENG 6226 Form

b. Dam Operations. The Government will close Gate Bays 1 thru 3 when pool stages are 434 ft or below. When pool stage increases due to increasing flow (approximately an open river upper pool stage of 434 ft), Gates 1 thru 3 will be operated so that the gates are not overtopping. This will result in the gates being partially open and allowing flow underneath. The Government retains the authority to deviate from this plan to ensure the safety of Government owned facilities, navigation, and the general public.

The Government will inform the Contractor of any changes to Gates 1-3, prior to operating the gates.

The Contractor shall frequently monitor river stages and daily river forecasts for the possibility of the Government opening Gate Bays 1 thru 3 in the event of higher flow. The Contractor may anticipate the need for gate openings by observing a rising L&D 25 Tailwater gage approaching approximately a stage of 26.0 feet (432.6 feet NAVD88). It is recommended that the Contractor use the Government's daily forecasts (https://www.mvs-wc.usace.army.mil) to plan for the potential of gate openings. SEE ABOVE SUB-PARAGRAPH ENTITLED DATUM FOR INFORMATION ON DATUM

CONVERSIONS.

c. Requested Gate Operations. All requests by the Contractor, with respect to gate settings, will be coordinated with the Contracting Officer. Gate setting changes will only occur when the Contracting Officer concurs and determines them to be safe.

All Tainter and roller gate movements and machinery equipment operations will be conducted by the Government for the Contractor. The Contractor shall schedule any required gate movement within the following parameters:

1) Gate operations will only be performed during the day shift, 0800 to 1600 hours, Monday thru Friday, excluding Government holidays.

2) The Contractor shall provide a minimum 24-hour advance notice to the Contracting Officer's Representative for all gate operations. Notice shall be provided on a working day, i.e., Monday through Friday, excluding Federal holidays.

3) The Contractor shall allow four hours for the Government to complete requested gate position changes.

4) The Government will operate only one gate at a time.

d. Spudding. The Contractor shall take every precaution necessary during use of floating plant spudding operation to prevent damage to the existing facility. Use of spuds for floating plant over existing structures is

DOCUMENT 00 08 00 Page 13 prohibited. Additionally, the floating plant shall be powered by a vessel with sufficient horsepower to safely maneuver the floating plant. Prior to any floating plant work, the Contractor must perform a multi-beam survey of the area and provide results to the Government. At the conclusion of the project, the Contractor shall perform a multi-beam survey and provide the results to the Government; any damage from use of floating plant shall be repaired at no additional cost to the Government. The Contractor shall be aware of depths and required spud lengths.

e. Withdraw any equipment that would be subject to damage by rising river stages, before they are subject to damage. The Contractor shall monitor the prevailing river conditions at the project site, referring to the upstream project river gauge, river forecasts issued by the National Weather Services, and the USGS Stream/River Gage Data, and shall determine when to withdraw equipment and floating plant. The withdrawal of equipment and floating plant shall ultimately be the Contractor's decision and will not be directed by the Government. It shall be the Contractor's responsibility to determine the time necessary to make a complete and safe withdrawal of equipment and floating plant with due consideration given to the location of mooring area, flooding of accessway, roadways, and staging areas; amount of equipment; size of the floating plant, and capacity of towboats and propelling units to operate safely and efficiently at the expected river velocities.

CLOSURE AND OVERTOPPING DATA (NAVD88)

Lock and Dam Closure (TW elevation) 440.1 ft and rising (TW Stage 33.5 ft)

Lock Wall Top Elevation 443.6 ft (Pool Stage 444.0 ft)

Annual Exceedance Probability (AEP) of Overtopping Lock Wall (RM 241.4, interpolated from 2004 Flow Frequency Study)

0.0217 (~46 yr event)

Approx. Overtopping Flow (RM 241.4, interpolated from 2004 Flow Frequency Study)

399,000 cfs

Water Surface Elevation (WSE) Recreational Areas Begin Closing

431.1 ft (TW Stage 24.5)

WSE Winfield Picnic Area Closes 431.76 ft (TW Stage 25.16)

WSE Lock 25 Public Road Access Overtopped 433.1 ft (TW Stage 26.5)

WSE Cap Au Gris Levee Behind Lock Overtops (DS areas overtop prior to this elevation)

444.6 ft (TW Stage 38.0)

f. The Contractor shall submit the contingency plan for addressing headwater and/or tailwater fluctuations to the Contracting Officer for approval at least 14 days after notice to proceed. Work will not be permitted to start until the plan has been reviewed and accepted by the Contracting Officer. At a minimum the contingency plan will include:

DOCUMENT 00 08 00 Page 14

- Procedure(s) for monitoring river conditions including river levels, discharges, and velocities

- Mooring location(s)

- Document river condition which affect notification actions

- Document river conditions which affect withdraw

- Sequence and duration of withdraw for land and river based equipment and materials

- Procedures for care of moored floating plant and equipment

- Document river conditions affecting remobilization

- Sequence and duration of remobilization

Subcontractors will also be thoroughly familiar with their responsibilities and duties under the plan.

g. Floating plant and personnel shall comply with the applicable U.S.

Coast Guard regulations and licensing requirements while on site.

Floating plant equipment shall meet the applicable requirements of 46 CFR Chapter 1 Subchapter E and 46 CFR 44.05-10. Floating vessels operating on the Mississippi River and its tributaries must be operated in accordance with 33 CFR 207.300, "Ohio River, Mississippi River above Cairo, Ill., and their tributaries; use, administration, and navigation". Meet applicable local, state, and federal requirements for disposal of sanitary sewage, and bilge water accumulated aboard floating plant.

h. No priority lockages will be given over other waterway users. Adhere to normal queuing procedures as required unless otherwise approved by the Contracting Officer.

i. No fleeting is permitted upstream of the dam and/or whereas it interferes with the preferred sailing line for approaching vessels without prior approval from the Contracting Officer. Floating plant and other contractor vessels actively working on upstream project features are permitted only during work hours or if manned 24 hours per day, 7 days per week.

j. The Contracting Officer or appointed representative may direct the Contractor to move any vessel which interferes with navigation or poses a safety threat.

k. The Contractor is advised there is a potential for unexpected movement of pool ice during the months of December through March. The Contractor should further be aware that the pool ice can become so thick that work may not be able to be performed upstream of the lock and dam. Any equipment and especially vessels that are captured by the ice will be subjected to severe damage or destruction. The Contracting Officer will attempt to provide advance notice of ice movement as a courtesy to the Contractor. The failure of the Government to issue such a notice will not entitle the Contractor to seek damages against the Government.

Considerable amounts of ice may be encountered while moving equipment on the river and in the locks.

l. The Contractor shall provide measures to protect all Government facilities and equipment, both new and existing, from Contractor work activities, to include but not limited to, contamination by surface preparation, abrasive blast debris, power spraying, weld splatter, concrete splatter, paint overspray, dust or other related debris. The Contractor shall be responsible for any repairs resulting from damage. If contamination occurs, the Contractor shall adjust the protection to

DOCUMENT 00 08 00 Page 15 eliminate contamination at other areas as work progresses.

m. Delays Due to High Water. Refer to historic and daily river gage readings. Delays to the Contractor's operations from ceasing work due to flood will be subject to the Contract Clause entitled "Default (Fixed-Price Construction)" (FAR 52.249-10).

n. Existing Work Flat and Safety (Jon) Boats. The Contractor is advised that Government vessels may be required to transit the facility and construction areas at any time, except during dewatering of the 600 ft lock chamber and including during closure periods, to respond to critical operations. In addition, during lock closure periods, the Government will make every effort to configure tows with limited length and width to facilitate safe passage around construction activities. The Contractor is advised that vessels under contract to the Government are considered Government vessels.

The Government stores a work flat downstream of the existing upper miter gate of the 1200 ft lock chamber. The Government must have continuous access to launch and maintain the work flats.

Safety Boats are on davits on the lockwalls. The Government must have continuous access to launch and maintain the safety boats at all times.

Any requested deviation to temporarily block access to the work flat or safety boats must be coordinated with the Contracting Officer. With approval of the Contracting Officer, the work flat or safety boats may be temporarily relocated.

o. The Contractor's methods for disposal of sanitary sewage, and bilge water accumulated aboard floating plant, shall meet applicable local, State, and Federal requirements.

p. The terms of the Government's easement for property at the ferry landing prohibits the contractor's use of the subject property during high water conditions above tailwater gauge 30. The Contractor will be allowed to use the temporary work area easement at tailwater gauge readings below tailwater gauge 30. The Contractor's inability to use the ferry landing due to tailwater above 30 is not grounds for additional time or compensation. The Contractor may make agreements with the landowner outside of the Government easement at no additional cost to the Government. If agreements are made, provide the Government with a copy.

q. The Contractor shall provide 1 navigation assisting vessels with a minimum of 1,000 horsepower to assist commercial vessels entering and existing the lock chamber on the downstream approach of the lock. Each boat shall be equipped with power winches and at least one deckhand.

Assist vessel assistance will be coordinated by the tow operator. All electronic, environmental, safety and fire-fighting equipment shall be in good working order and meet established marine industry and US Coast Guard standards. The Government reserves the right to disqualify a vessel if the vessel's condition or seaworthiness is judged unacceptable or it is deemed unable to perform the task safely.

The Contractor shall establish, maintain, and submit, as part of the work plan, accommodations to ensure the safety of commercial and recreational traffic in the construction area. This plan shall be in accordance with EM 385-1-1 and include actions as required to protect the public and prevent damage to incomplete construction. The Contractor shall be responsible for

DOCUMENT 00 08 00 Page 16 coordinating with the Coast Guard and other regulating agencies to implement any necessary restrictions. Coordinate with the Coast Guard for appropriate navigation lighting and signage requirements during the construction contract. The Contractor shall also develop and implement a plan to provide public notice of any construction and any necessary restrictions and closures.

1.16.5 Sequencing

The lock will be continuously open to river traffic except for approved navigation outages. During placement of the staging area fill, the Contractor may request navigation outages where the lock is closed to navigation. The Contractor shall strictly adhere to approved navigation outages. The navigation outages must be entered into the Contractor's schedule. Each outage can be no greater than 12 hours and no more than 96 hours in a month. There must be at least 24 hours between each outage to allow for passing of accumulated navigation through the lock. A minimum 7-day notice must be provided to the Government for approval prior to each outage. An outage can be cancelled within 7 days of the requested outage but an outage cannot be added within 7 days of an outage. To accommodate peak recreational traffic periods, closures may not be scheduled on Memorial Day, Labor Day, Juneteenth, or 4th of July Holidays. It is suggested closures not occur on Fridays, Saturdays, or Sundays.

1.16.6 Coordination

a. Points of Contact for various entities are listed below:

Winfield Fire Chief 3931 E Highway 47 Winfield, MO 63389 636-566-8406

MoDOT - Northeast District 1711 S. Highway 61 Hannibal, MO 63401 573-808-3562

Lincoln County Highway Department 219 Highway H Troy, MO 63379 636-528-7112

Winfield Police Department 51 Harry's Way Winfield, MO 63389 636-566-6936

Lincoln County Sheriff 65 Business Park Dr Troy, MO 63379 636-528-6100 636-528-8546

Winfield Ferry Calhoun Ferry Company 618-535-5759

Lars Okmark

DOCUMENT 00 08 00 Page 17

USCG Sector Upper Mississippi Waterways Management Division Chief Lars.Okmark@uscg.mil Office: (314) 269-2560 Cell: (309) 737-1982

1.17 SUBMITTALS

Additional submittals for this contract that are not listed within individual technical provisions are listed below. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 - SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Statements of Required Insurance ; G Work Plan ; G, STR Safe Practices Manual ; G, DIV Emergency Management Plan (Diving Specific) ; G, DIV Hazardous Energy Control Plan (Diving Specific) ; G, DIV Sample Equipment Inspection Checklist ; G, DIV Sample Dive Log ; G, DIV Sample Pre-Dive/Post-Dive Checklist ; G, DIV Sample Eng 1927-R Safe Clearance Form ; G, DIV Sample Eng 6226 Form ; G, DIV Dive Operations Plan ; G, DIV Site Specific Emergency Management Plan ; G, DIV Site Specific Hazardous Energy Control Plan ; G, DIV Site Specific Internal Safety Procedures, Checklists, And Inspection Forms ; G, DIV Personnel Qualifications ; G, DIV Dive Equipment Certification ; G, DIV Dive Platform Information ; G, DIV Activity Hazard Analysis (Diving) ; G, DIV Osha 29 Cfr 1910, Subpart T ; G, DIV Navy Dive Tables ; G, DIV Eng 1927-R Safe Clearance Form ; G, DIV Eng 6226 Form ; G, DIV existing conditions recording contingency plan Utility Plan ; G Multi-Beam Survey

1.18 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING PLANT

Two means of escape shall be provided for assembly, sleeping, and messing areas on floating plants. For areas involving 10 or more persons, both means of egress shall be through standard size doors opening to different exit routes.