W912P926RA001 Attachment 0005 - 00 00 10 Scour Repair Advance Bid Schedule.pdf

PDF 77 KB Posted

Attached to
LOCK FOUNDATION AND SITE PREPARATION FOR LOCK and DAM 25 NAVIGATION ECOSYSTEM SUSTAINABILITY PROGRAM (NESP)
Solicitation number
W912P926RA001
Issued by

About this file

This is a Pricing Schedule for a federal construction contract involving lock and dam foundation work. The contract is organized into a Base Schedule with 21 line items (0001-0021) and one Option 1 item (1001). Base Schedule work includes mobilization/demobilization, site preparation activities (erosion control, staging area fill, rip rap slope protection, sanitary outfall pipe, and land-based site work), and lock foundation work (deflector wall installation, steel pipe piles, separator wall furnishing and installation, dredge material placement, alluvium excavation, rip rap excavation, scour protection materials, timber cribbing demolition, and site monitoring). Estimated quantities vary by line item, with unit measurements including Jobs, Cubic Yards (CY), Tons (TN), and Linear Feet (LF). Option 1 consists of Assist Vessel services priced at 90 days.

Offerors must submit both unit prices and extended amounts for all line items; failure to price all items constitutes grounds for disqualification. Line items 0014 (Dredge Material Placement) and 0016 (Rip Rap Excavation) are subdivided with separate pricing for initial and overflow quantities, evaluated on total price basis. FAR Clause 52.211-18 applies to variations in estimated quantities for these subdivided items, with equitable adjustment provisions if actual work falls below 85 percent or exceeds 115 percent of estimated quantities. Option 1 line item 1001 is discretionary and will be directed by the Contracting Officer only as needed; payment is made solely for work actually performed and accepted. All extensions are subject to government verification, with unit price taking precedence over extension amounts in case of discrepancies.

View the file

Other files

File Type Posted
Solicitation Amendment W912P926RA0010006 SF 30.pdf PDF
B3MRLD25202402-PLAN_SET_AMND-2026-04-14-Amendment 0005 Plans.pdf PDF
Solicitation Amendment W912P926RA0010005 SF 30.pdf PDF
B3MRLD25202402-PLAN_SET_AMND-2026-04-08-Amendment 0004 Plans.pdf PDF
Amendment 0004 Specifications.pdf PDF
Solicitation Amendment W912P926RA0010004 SF 30.pdf PDF
ProjNet Bidder Inquiries and Replies as of 8 April.pdf PDF
Amendment 0004 00 00 10 Pricing Schedule.pdf PDF
PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS Amd 0003.pdf PDF
EVALUATION FACTORS FOR AWARD Amd 0003.pdf PDF
Amendment 0003 00 00 10 Pricing Schedule.docx DOCX document
B3MRLD25202402-PLAN_SET_AMND-2026-03-27-Amendment 0003 Plans.pdf PDF
Amendment 0003 Specifications.pdf PDF
Solicitation Amendment W912P926RA0010003 SF 30.pdf PDF
Pre Bid Site Visit Sign In Sheet.pdf PDF
ProjNet Bidder Inquiries and Government Replies as of 27 Mar 2026.pdf PDF
PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS Amd 0002.pdf PDF
Solicitation Amendment W912P926RA0010002 SF 30.pdf PDF
W912P926RA001 Attachment 0003 PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS.pdf PDF
Solicitation Amendment W912P926RA0010001 SF 30.pdf PDF
W912P926RA001 Attachment 0004 - EVALUATION FACTORS FOR AWARD.pdf PDF
W912P926RA001 Attachment 0003 - PROPOSAL SUBMISSION INSTRUCTIONS CONDITIONS AND NOTICES TO OFFERORS.pdf PDF
W912P926RA001 Attachment 0008 - Appendix C Small Business Participation Commitment Document.pdf PDF
W912P926RA001 Attachment 0001 - Lock Foundation and Site Prep As-Advertised Specs.pdf PDF
W912P926RA001 Attachment 0012 - Wage Determination.pdf PDF
W912P926RA001 Attachment 0007 - Appendix B Subcontractor Consent.pdf PDF
W912P926RA001 Attachment 0009 - Appendix D Subcontractor Letter of Commitment.pdf PDF
W912P926RA001 Solicitation.pdf PDF
W912P926RA001 Attachment 0004 - EVALUATION FACTORS FOR AWARD.pdf PDF
W912P926RA001 Attachment 0010 - Appendix E DoD Checklist for Reviewing Subcontracting Plans.pdf PDF
W912P926RA001 Attachment 0006 - Appendix A Past Performance Questionnaire.pdf PDF
W912P926RA001 Attachment 0011 - Appendix F Small Business Participation Commitment Progress Quarterly Report.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICING SCHEDULE

Item Estimated Unit Extended

NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT _

00 00 10-1

Base Schedule

0001. Mobilization and Demobilization 1 JOB _ ___ ________

Site Preparation:

0002. Erosion and Sediment Control 1 JOB _ ___ ________

0003. Staging Area Fill 65,000 CY _ ___ ________

0004. New Rip Rap Slope Protection (Land) 1 JOB _ ___ ________

0005. Sanitary Outfall Pipe 1 JOB _ ___ ________

0006. Land Based Site Work 1 JOB _ ___ ________

Lock Foundation:

0007. Deflector Wall Installation – Dam Apron 1 JOB _ ___ ________

0008. Steel Pipe Piles – 48 Inch 330 LF _ ___ ________ Diameter

0009. Furnish Separator Wall W30x132 20,320 LF _ ___ ________

0010. Furnish Separator Wall PZ-27 40,630 LF _ ___ ________

0011. Install Separator Wall W30x132 4,800 LF _ ___ ________

0012. Install Separator Wall PZ-27 9,600 LF _ ___ ________

0013. Articulating Fabric Formed Concrete Mattress 1 JOB _ ___ ________

0014. Dredge Material Placement – Lock Floor

A. First 105,000 CY 105,000 CY _ ___ ________

B. All Over 105,000 CY 40,000 CY _ ___ ________

0015. Alluvium Excavation 25,000 CY _ ___ ________

0016. Rip Rap Excavation

A. First 39,500 CY 39,500 CY _ ___ ________

B. All Over 39,500 CY 8,000 CY _ ___ ________

PRICING SCHEDULE

Item Estimated Unit Extended

NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT _

00 00 10-2

0017. R5000 Scour Protection 27,500 TN _ ___ ________

0018. Graded B-Stone Scour Protection 5,000 TN _ ___ ________

0019. Graded C-Stone Scour Protection 8,750 TN _ ___ ________

0020. Timber Cribbing & Mattress Demo 1 JOB _ ___ ________

0021. Site Monitoring 1 JOB _ ___ ________

TOTAL Base SCHEDULE PRICE $ _________

Option 1 Schedule

1001. Assist Vessel 90 DAY _ ___ ________

TOTAL Option 1 SCHEDULE PRICE $ _________

TOTAL BASE and OPTION 1 SCHEDULE PRICES $ _________

ABBREVIATIONS

JOB Job CY Cubic Yards TN Ton LF Linear Feet

(See PRICING SCHEDULE NOTES)

00 00 10-3

PRICING SCHEDULE NOTES

1. All quantities shown on the PRICING SCHEDULE are estimated quantities except when the unit is shown as job "JOB".

2. When proposals are solicited on a unit price basis, offerors shall insert in the spaces provided therefore in the SCHEDULE both the "unit price" and the "estimated amount" resulting from applying the said unit price to the estimated quantity shown. In event the offeror quotes only a total price ("estimated amount") in its bid and fails to quote the unit price, the Government will determine such unit price by dividing the total price quoted by the quantity of the item set out in the SCHEDULE. The offeror agrees that the unit price so determined shall be used for the purpose of price evaluation, award and all payments to the Contractor including final payment.

3. All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer and the extension will be corrected accordingly.

4. If a modification to a proposal based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the price schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the price schedule.

5. Offerors are required to submit a price on all items listed on the Pricing Schedule in addition to inserting a total quoted price in the appropriate space provided. Failure to do so will be considered good cause to disqualify the proposal.

6. EVALUATION OF SUBDIVIDED ITEMS (MAR 1995) UAI 5152.211-9000

Item Nos. 0014 and 0016 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub-items.

7. VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS. UAI 5152.211-

9001. This variation in estimated quantities clause is applicable only to Item Nos. 0014 and 0016.

(a) Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.

(b) Where the actual quantity of work performed for Item Nos. 0014 and 0016 is less than 85 percent of the quantity of the first sub-item listed under such item, the Contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed, and, in addition, an equitable adjustment shall be made in accordance with the Contract Clause FAR 52.211-18, Variation in Estimated Quantities.

00 00 10-4

(c) If the actual quantity of work performed under Item Nos. 0014 and 0016 exceeds 115 percent or is less than 85 percent of the total estimated quantity of the sub-items under that item, and/or if the quantity of work performed under the second sub-item or any subsequent sub-item under Item Nos. 0014 and 0016 exceeds 115 percent or is less than 85 percent of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract, the contract completion time will be adjusted in accordance with the Contract Clause FAR 52.211-18, Variation in Estimated Quantities.

8. OPTIONAL LINE ITEMS. Line Item No. 1001 are OPTIONAL ITEMS. Upon the review of inspection at the site, the Contracting Officer, in accordance with the specifications and drawings, will direct the optional line item work as needed. The Contractor shall perform the appropriate work ONLY when directed by the Contracting Officer. The Government is not obligated to request any work under any optional item(s). The prices for each optional item shall represent your firm price to perform that service. Payment will be made ONLY for work actually requested and performed to the Government’s satisfaction.

Optional work is detailed in Specification Section 00 08 00.

File details come from the government source that posted it. Updated .