This document is an Appendix A listing conflict items for the Pajaro Reach 6 project, detailing specific site relocation and demolition activities. The table includes seven key issues with precise geographic coordinates, including building demolitions, well relocations, electrical service line changes, and tenant relocation. Resolution dates are scheduled between August 15 and September 30, 2025, with most activities concentrated around demolishing existing structures and relocating infrastructure to prepare for the levee and floodwall construction project.
Specific conflict items include demolishing the La Chilanguita Building and a barn, relocating PG&E electrical service lines, constructing new wells to replace existing ones (Wells 2-5), and relocating a tenant. The locations are situated along the Pajaro River in Santa Cruz County, with activities occurring at specific station markers ranging from STA 0+50 to STA 65+00. Each item has a planned resolution date and brief description of the planned action, such as constructing new wells and then cutting and filling the old well locations.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pajaro Reach 6 -Conflict ItemsPajaro Reach 6 -Conflict ItemsReach 6 Finish Line
Issue Location Resolution Date Discussions on Status and Resolution
La Chilanguita Building needs to be demolished
3656'07"N | 12144'37"W LB Approximate STA 0+50
08/31/25 Building to be demolished in August
Well 2 Electrical Service Line Relocation
3656'08"N | 12145'46"W LB Approximate STA 65+00
08/31/25 The PG&E service line pole relocation is currently scheduled for late August 2025.
Well 3 Relocation 3656'07"N | 12145'35"W RB Approximate STA 54+00
09/30/25 New well is being constructed. Once the new well is operational, the old well will be cut and filled.
Well 4 Relocation 3656'08"N | 12145'16"W LB Approximate STA 37+00
09/30/25 New well is being constructed. Once the new well is operational, the old well will be cut and filled.
Well 5 Relocation 3656'12"N | 12145'03"W LB Approximate STA 25+00
09/30/25 New well is being constructed. Once the new well is operational, the old well will be cut and filled.
Tenant Relocation 3656'06"N | 12144'47"W LB Approximate STA 10+00
08/15/25 Tenant to be relocated by August 15.
Barn Demolition 3656'06"N | 12144'47"W LB Approximate STA 10+00
08/31/25 Building to be demolished in August
APPENDIX A