31 41 16.pdf

PDF 44 KB Posted

Attached to
Pajaro River Reach 6
Solicitation number
W912P725BA012
Issued by

About this file

This document is a detailed Section 31 41 16 specification for Metal Sheet Piling for the Pajaro River Flood Risk Management Project (Reach 6), with contract number W912P725BA012. The specification provides comprehensive technical requirements for metal sheet piling installation, including material specifications, driving procedures, quality control, and environmental considerations. Key technical requirements include using hot-rolled steel sheet piling conforming to ASTM A572/A572M, Grade 50, Type PZ22, with free-sliding interlocks that provide a minimum 5-degree swing angle when interlocked.

The specification mandates rigorous installation procedures, including precise placement tolerances (1/8 inch out-of-plumbness per foot), detailed driving techniques, and extensive monitoring requirements. Critical environmental controls include vibration monitoring (limited to 2 inches per second peak particle velocity) and noise monitoring at sensitive areas. The contractor must also conduct a preconstruction condition survey of structures within 200 feet of the pile driving activity, documenting existing conditions through high-definition video and photographs. The project is scheduled for final submittal in August 2025, with the specification issued for construction at that time.

View the file

Other files

File Type Posted
Bid Abstract SF 1419 Pajaro Reach 6.pdf PDF
Solicitation Amendment W912P725BA012 0006.pdf PDF
Solicitation Amendment 5 W912P725BA0120005 SF 30.pdf PDF
RFI Set 3 8.15.2025.pdf PDF
Amendment 5 -C-13.pdf PDF
Amendment 5- Revised Specification Section 31 63 29.pdf PDF
RFIs Set 2 W912P725BA012.pdf PDF
Amendment4 C Sheets 2 of 2.pdf PDF
Amendment 4 C Sheets 1 of 2.pdf PDF
01 50 00 (Revision 2 Entire Spec Section).pdf PDF
TREE SURVEY DATA.pdf PDF
Solicitation Amendment 0004 W912P725BA012 SF 30 FINAL.pdf PDF
01 50 00 (Revision 1 Page Removal of Field Office).pdf PDF
Solicitation Amendment W912P725BA0120003 SF 30.pdf PDF
RFIs Posted 7.31.2025.pdf PDF
01 20 00.pdf PDF
32 31 13.54.pdf PDF
Pajaro Reach6-Amendment3.pdf PDF
Amendment 2_No Work Zone.pdf PDF
2022_A3Geo_Phase 1 Geotechnical Investigation.pdf PDF
Pajaro Existing Geotech Data DRAFT 033122.pdf PDF
Solicitation Amendment W912P725BA0120002 SF 30 7.22.2025.pdf PDF
2023_A3Geo_Phase 2 Geotechnical Investigation.pdf PDF
Pajaro Reach 6 - CONTRACTOR SITE WALK ATTENDANCE.pdf PDF
Pajaro Reach 6 Conflict Items 7.16.2025.pdf PDF
Amendment 1_ W912P725BA0120001 SF 30.pdf PDF
Pajaro FRM Reach 6_Specifications.pdf PDF
Pajaro FRM-Reach 6-100percent-AppendixH-Improvement Plans (Signed).pdf PDF
W912P7BA012 Pajaro IFB FINAL 7.3.2025.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pajaro River Flood Risk Management Project Reach 6 Contract No: W912P725BA012

SECTION TABLE OF CONTENTS

DIVISION 31 - EARTHWORK

SECTION 31 41 16

METAL SHEET PILING

11/20

PART 1 GENERAL

1.1 DESCRIPTION

1.2 REFERENCES

1.3 ESTIMATED QUANTITIES

1.4 SUBMITTALS

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery and Storage

1.5.2 Handling

1.5.3 Damaged Piles

1.6 MATERIAL CERTIFICATES

PART 2 PRODUCTS

2.1 METAL SHEET PILING

2.1.1 Interlocks

2.1.2 General Requirements

2.2 APPURTENANT METAL MATERIALS

2.3 TESTS, INSPECTIONS, AND VERIFICATIONS

2.3.1 Materials Tests

2.4 PILE DRIVING EQUIPMENT

2.4.1 Driving Hammers

2.4.2 Jetting Equipment

PART 3 EXECUTION

3.1 PRELIMINARY WORK

3.1.1 Pile Length Markings

3.2 EARTHWORK

3.3 INSTALLATION

3.3.1 Placing and Driving

3.3.1.1 Placing

3.3.1.2 Driving

3.3.2 Cutting-Off and Splicing

3.3.3 Inspection of Driven Piling

3.3.4 Pulling and Redriving

3.3.5 Testing Agency Qualifications

3.3.6 Survey Data

3.4 INSTALLATION RECORDS

3.5 VIBRATION CONTROL

3.5.1 Vibration Best Management Practices

3.5.2 Vibration Monitoring

3.6 NOISE CONTROL

3.7 PRECONSTRUCTION CONDITION SURVEY

-- End of Section Table of Contents --

Final Submittal SECTION 31 41 16 Page 1 Issued for Construction August 2025

Final Submittal SECTION 31 41 16 Page 2 Issued for Construction

SECTION 31 41 16

METAL SHEET PILING

11/20

PART 1 GENERAL

1.1 DESCRIPTION

Design, furnish, install and test metal sheet piles at the locations indicated on the drawings and specified herein.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M (2020; Errata 1 2021) Structural Welding Code - Steel

AWS D1.5M/D1.5 (2020; Errata 1 2022) Bridge Welding Code

ASTM INTERNATIONAL (ASTM)

ASTM A6/A6M (2021) Standard Specification for General Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling

ASTM A572/A572M (2021; E 2021) Standard Specification for High-Strength Low-Alloy Columbium-Vanadium Structural Steel

ASTM C1077 (2017) Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation

ASTM E329 (2021) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection

ASTM E548 (1994; E 1995) Standard Guide for General Criteria Used for Evaluating Laboratory Competence

1.3 ESTIMATED QUANTITIES

The estimated quantities of sheet piling listed in the unit price schedule of the contract, as to be furnished by the Contractor, are given for bidding purposes only. Sheet piling quantities for payment will consist of the linear feet of piling acceptably installed. Installed quantities will consist of all piling including fabricated sections driven between the required top and bottom elevations of pilings plus any additions thereto resulting from changes in design or alignment as provided in

Final Submittal SECTION 31 41 16 Page 3 Issued for Construction paragraph DRIVING.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. "SPN" - San Francisco District. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Installation Procedures ; G, (SPN)

SD-02 Shop Drawings

Metal Sheet Piling ; G, (SPN)

Pile Splicing ; G, (SPN)

Pile Placement ; G, (SPN)

As-Driven Survey ; G, (SPN)

Pile Shoe ; G, (SPN)

SD-03 Product Data

Driving

Pile Driving Equipment ; G, (SPN)

Delivery, Storage, and Handling ; G, (SPN)

Pulling and Redriving ; G, (SPN)

SD-05 Design Data

Procedure for Insufficient Pile Length ; G, (SPN)

SD-06 Test Reports

Materials Tests

SD-07 Certificates

Pile Shoe ; G, (SPN)

Welding Certifications ; G, (SPN)

Steel Plant Certificate ; G, (SPN)

SD-11 Closeout Submittals

Pile Driving Record ; G, (SPN)

Final Submittal SECTION 31 41 16 Page 4 Issued for Construction

1.5 DELIVERY, STORAGE, AND HANDLING

Conform all delivery, storage, and handling of materials to the requirements specified herein. Develop and submit plans for the delivery, storage, and handling of piles. Submit delivery, storage, and handling plans for piles at least 30 days prior to delivery of piles to the job site.

1.5.1 Delivery and Storage

Materials delivered to the site must be new and undamaged and must be accompanied by certified test reports. Provide the manufacturer's logo and mill identification mark on the sheet piling as required by the referenced specifications. Store and handle sheet piling in the manner recommended by the manufacturer to prevent permanent deflection, distortion or damage to the interlocks; as a minimum, support on level blocks or racks spaced not more than 10 feet apart and not more than 2 feet from the ends. Storage of sheet piling should also facilitate required inspection activities and prevent damage to coatings and corrosion protection prior to installation.

1.5.2 Handling

Lift piles to ensure that the maximum permissible curvature is not exceeded. Holes may be burned above the cutoff length for lifting piles into the leads. If there is evidence of pile damage during driving due to the holes, Contracting Officer may forbid the burning of holes. Do not damage piles when dragging piles across the ground or barge deck.

Inspect piles for excessive curvature and for damage before transporting them from the storage area to the driving area and immediately prior to placement in the driving leads. Curvature in the pile must be measured with the pile laying on a flat surface and is the distance between the pile at the mid-length of the pile and the flat surface. Straightness of the sections of piles must conform to AWS D1.5M/D1.5 , Section 3.5.1.1.

Piles having excessive curvature will be rejected.

1.5.3 Damaged Piles

Inspect each pile for straightness and structural damage before transporting them to the project site and immediately prior to placement in the driving leads. Bring any damage to the attention of the Contracting Officer. Piles which are damaged during delivery, storage, or handling to the extent they are rendered unsuitable for the work, in the opinion of the Contracting Officer, will be rejected and removed from the project site, or may be repaired, if approved, at no cost to the Government.

Any pile damaged by reason of internal defects or by improper driving must be corrected by one of the following methods approved by the Engineer for the pile in question:

a. The pile is withdrawn, if practicable, and replaced by a new and, if necessary, longer pile.

b. One or more replacement piles are driven adjacent to the defective pile.

A pile driven below the specified butt elevation must be corrected by one

Final Submittal SECTION 31 41 16 Page 5 Issued for Construction of the following methods approved by the Engineer:

a. The pile is spliced (if approved).

b. A sufficient portion of the footing is extended down to properly embed the pile.

A pile driven out of its proper location or out of plumb as approved by the Engineer, must be corrected by one of the following methods approved by the engineer:

a. One or more replacement piles are driven next to the pile in question.

b. As directed by the structural engineer.

1.6 MATERIAL CERTIFICATES

For each shipment, submit certificates identified with specific lots prior to installing piling. Include in the identification data piling type, dimensions, chemical composition, mechanical properties, section properties, heat number, and mill identification mark.

PART 2 PRODUCTS

2.1 METAL SHEET PILING

Submit detail drawings for sheet piling, including fabricated sections, showing complete piling dimensions and details, driving sequence and location of installed piling.

a. Include in the drawings details of top protection, special reinforcing tips, tip protection, lagging, splices, fabricated additions to plain piles, cut-off method, corrosion protection, and dimensions of templates and other temporary guide structures for installing piling.

Provide details of the method for handling piling to prevent permanent deflection, distortion or damage to piling interlocks.

b. Metal sheet piling must be hot-rolled steel sections conforming to ASTM A572/A572M , Grade 50, Type PZ22.

c. For protection of sheet piling, coat it in accordance with Section

09 90 00 PAINTS AND COATINGS.

2.1.1 Interlocks

The interlocks of sheet piling must be free-sliding, provide a swing angle suitable for the intended installation but not less than 5 degrees when interlocked, and maintain continuous interlocking when installed.

2.1.2 General Requirements

Provide sheet piles with minimum section modulus, moment of inertia, shape, and size as specified in the plans. Sheet piling must be full-length sections of the dimensions shown. Provide sheet piling with standard lifting holes. Metalwork fabrication for sheet piling must be as specified and in Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS.

Final Submittal SECTION 31 41 16 Page 6 Issued for Construction

2.2 APPURTENANT METAL MATERIALS

Provide metal plates, shapes, bolts, nuts, rivets and other appurtenant fabrication and installation materials conforming to manufacturer's standards and to the requirements specified in the respective sheet piling standards.

2.3 TESTS, INSPECTIONS, AND VERIFICATIONS

Requirements for material tests, workmanship and other measures for quality assurance must be as specified and in Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS. Provide manufacturer's steel plant certificate for Government review and approval.

2.3.1 Materials Tests

Submit certified materials tests reports showing that sheet piling and appurtenant metal materials meet the specified requirements, for each shipment and identified with specific lots prior to installing materials.

Material test reports must meet the requirements of ASTM A6/A6M. Perform materials tests conforming to the following requirements. Sheet piling and appurtenant materials must be tested and certified by the manufacturer to meet the specified chemical, mechanical and section property requirements prior to delivery to the site. Testing of sheet piling for mechanical properties must be performed after the completion of all rolling and forming operations. Testing of sheet piling must meet the requirements of ASTM A6/A6M.

2.4 PILE DRIVING EQUIPMENT

Submit complete descriptions of sheet piling driving equipment including hammers, extractors, protection caps and other installation appurtenances, prior to commencement of work. Descriptive information includes manufacturer's name, model numbers, capacity, rated energy, hammer details, cushion material, helmet, and templates. Provide pile driving equipment conforming to the following requirements. Submit descriptions of pile driving equipment, including hammers, power packs, driving helmets, hammer cushions, pile cushions, leads, extractors, jetting equipment, and preboring equipment at least 30 days prior to commencement of work.

2.4.1 Driving Hammers

Hammers must be steam, air, or diesel drop, single-acting, double-acting, differential-acting, or vibratory or press-in type. The driving energy of the hammers must be able to develop sufficient energy to drive the pile at a penetration rate of not less than 1/8 inch per blow at the nominal driving resistance as recommended by the manufacturer for the piling weights and subsurface materials to be encountered. Repair damage to piling caused by use of a pile hammer with excess delivered force or energy.

2.4.2 Jetting Equipment

When driving resistance prohibits advancing sheet pile to required minimum tip elevation, jetting may be used as necessary to advance the pile to required minimum tip elevation. Jetting may be used at no additional cost to the Government. Jetting equipment must have not less than two removable or fixed jets of the water or combination air-water type. Water

Final Submittal SECTION 31 41 16 Page 7 Issued for Construction jets must be designed so that the discharge volume and pressure are sufficient to freely erode the material under and adjacent to the piling.

PART 3 EXECUTION

3.1 PRELIMINARY WORK

3.1.1 Pile Length Markings

Mark each pile prior to driving with horizontal lines at one foot intervals. Mark the interval number on pile every 5 feet from pile tip.

3.2 EARTHWORK

Perform in accordance with Section 35 41 00 LEVEE CONSTRUCTION.

Pre-excavation will not be permitted. Backfill as indicated.

3.3 INSTALLATION

3.3.1 Placing and Driving

3.3.1.1 Placing

Submit a written description of the site specific pile installation procedures for Government review and approval. Pile placement installation drawings and details must also be provided. Installation plan must demonstrate how the Contractor will prevent the installation of the sheet piles from affecting the performance of the drilled piles, or vice versa. The plan shall include how to monitor changes on installed sheet piles after installation and the limits of the allowed changes on installed sheet piles.

Any excavation required within the area where sheet pilings are to be installed must be completed prior to placing sheet pilings. Pilings properly placed and driven must be interlocked throughout their length with adjacent pilings to form a continuous diaphragm throughout the length or run of piling wall.

a. Pilings must be carefully located as indicated. Pilings must be placed plumb with out-of-plumbness not exceeding 1/8 inch per foot of length and true to line. Place the pile so the face will not be more than 6 inches from vertical alignment at any point. Top of pile at elevation of cut-off must be within 1/2 inch horizontally and 2 inches vertically of the location indicated. Manipulation of piles to force them into position will not be permitted. Check all piles for heave.

Re-drive all heaved piles to the required tip elevation.

b. Provide temporary wales, templates, or guide structures to ensure that the pilings are placed and driven to the correct alignment. Use a system of structural framing sufficiently rigid to resist lateral and driving forces and to adequately support the sheet piling until design tip elevation is achieved. Use two templates, at least, when placing each piling at third points not less than 20 feet apart. Templates must not move when supporting sheet piling. Fit templates with wood blocking to bear against the web of each alternate sheet pile and hold the sheet pile at the design location alignment. Provide outer template straps or other restraints as necessary to prevent the sheets from warping or wandering from the alignment. Mark template for the location of the leading edge of each alternate sheet pile. If in

Final Submittal SECTION 31 41 16 Page 8 Issued for Construction view, also mark the second level to assure that the piles are vertical and in position. If two guide marks cannot be seen, other means must be used to keep the sheet pile vertical along its leading edge.

3.3.1.2 Driving

Submit records of the completed sheet piling driving operations, including a system of identification which shows the disposition of approved piling in the work, driving equipment performance data, piling penetration rate data, piling dimensions and top and bottom elevations of installed piling. The format for driving records must be as directed. Drive pilings with the proper size hammer and by approved methods so as not to subject the pilings to damage and to ensure proper interlocking throughout their lengths.

a. Maintain driving hammers in proper alignment during driving operations by use of leads or guides attached to the hammer. Caution must be taken in the sustained use of vibratory hammers when a hard driving condition is encountered to avoid interlock-melt or damages.

Discontinue the use of vibratory hammers and impact hammers employed when the penetration rate due to vibratory loading is one foot or less per minute.

b. Employ a protecting cap in driving when using impact hammers to prevent damage to the tops of pilings. Use cast steel shoe to prevent damage to the tip of the sheet piling. Submit pile shoe installation details and material data for Government review and approval prior to use in the field. Remove and replace pilings damaged during driving or driven out of interlock at the Contractor's expense.

c. Drive pilings without the aid of a water jet unless otherwise authorized. Perform authorized jetting on both sides of the pilings simultaneously; discontinue it when the pile tip is approximately 5 feet above the indicated pile tip elevation and make the final 5 feet of penetration by driving. Before commencing the driving of the final 5 feet , firmly seat the pile in place by the application of a number of reduced energy hammer blows.

d. Take adequate precautions to ensure that pilings are driven plumb.

Where possible, drive Z-pile with the ball end leading. If an open socket is leading, a bolt or similar object placed in the bottom of the interlock will minimize packing material into it and ease driving for the next sheet. If at any time the forward or leading edge of the piling wall is found to be out-of-plumb in the plane of the wall the piling being driven must be driven to the required depth and tapered pilings must be provided and driven to interlock with the out-of-plumb leading edge or other approved corrective measures must be taken to insure the plumbness of succeeding pilings. The maximum permissible taper for any tapered piling must be 1/8 inch per foot of length.

e. Pilings in each run or continuous length of piling wall must be driven alternately in increments of depth to the required depth or elevation. No piling will be driven to a lower elevation than those behind it in the same run except when the pilings behind it cannot be driven deeper. Incrementally sequence driving of individual piles such that the tip of any sheet pile must not be more than 4 feet below that of any adjacent sheet pile. When the penetration resistance exceeds five blows per inch , the tip of any sheet pile must not be more than 2 feet below any adjacent sheet pile. If the piling next to

Final Submittal SECTION 31 41 16 Page 9 Issued for Construction the one being driven tends to follow below final elevation it may be pinned to the next adjacent piling.

f. If obstructions restrict driving a piling to the specified penetration, the obstructions must be removed or penetrated with a chisel beam. If the Contractor demonstrates that removal or penetration is impractical, make changes in the design alignment of the piling structure as directed to ensure the adequacy and stability of the structure. Pilings must be driven to depths shown and must extend up to the elevation indicated for the top of pilings. A tolerance of 2 inches above the indicated top elevation will be permitted. Pilings must not be driven within 100 feet of concrete less than 7 days old.

g. Pre-augering or spudding of piles may be used at no additional cost to the Government. Discontinue pre-augering or spudding approximately 5 feet above the indicated pile tip elevation. Drive the pile the final 5 feet of penetration.

3.3.2 Cutting-Off and Splicing

Pilings driven to refusal or to the point where additional penetration cannot be attained and are extending above the required top elevation in excess of the specified tolerance must be cut off to the required elevation. Pilings driven below the required top elevation and pilings damaged by driving and cut off to permit further driving must be extended as required to reach the top elevation by splicing when directed at no additional cost to the Government. Submit procedure for insufficient pile length . Provide pile splicing information and details for Government review and approval prior to installation in the field. If directed, pilings must be spliced as required to drive them to depths greater than shown and extend them up to the required top elevation.

a. Pilings adjoining spliced pilings must be full length unless otherwise approved. Splicing of pilings must be as indicated. Ends of pilings to be spliced must be squared before splicing to eliminate dips or camber. Pilings must be spliced together with concentric alignment of the interlocks so that there are no discontinuities, dips or camber at the abutting interlocks. Spliced pilings must be free sliding and able to obtain the maximum swing with contiguous pilings. Welding of splices must conform to the requirements of Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS. Shop and field welding, qualification of welding procedures, welders, and welding operators must be in accordance with AWS D1.1/D1.1M . Submit welding certifications for all welders and welding operators for Government review and approval.

b. The tops of pilings excessively battered during driving must be trimmed when directed, at no cost to the Government. Piling cut-offs will become the property of the Contractor and must be removed from the site.

c. Cut holes in pilings for bolts, rods, drains or utilities in a neat and workmanlike manner, as shown or as directed. Use a straight edge in cuts made by burning to avoid abrupt nicks. Bolt holes in steel piling must be drilled or may be burned and reamed by approved methods which will not damage the surrounding metal. Holes other than bolt holes must be reasonably smooth and the proper size for rods and other items to be inserted. Do not use explosives for cutting.

Final Submittal SECTION 31 41 16 Page 10 Issued for Construction

3.3.3 Inspection of Driven Piling

Perform continuous inspection during pile driving. Inspect all piles for compliance with tolerance requirements. Bring any unusual problems which may occur to the attention of the Contracting Officer. Inspect the interlocked joints of driven pilings extending above ground. Pilings found to be out of interlock must be removed and replaced at the Contractor's expense.

3.3.4 Pulling and Redriving

Submit the proposed method of pulling sheet piling, prior to pulling any piling. Pull, as directed, selected pilings after driving to determine the condition of the underground portions of pilings. Any piling so pulled and found to be damaged, to the extent that its usefulness in the structure is impaired, must be removed and replaced at the Contractor's expense. Pilings pulled and found to be in satisfactory condition must be redriven when directed.

3.3.5 Testing Agency Qualifications

Engage an independent testing agency qualified according to ASTM C1077 and ASTM E329 for testing indicated, as documented according to ASTM E548, and approved by the Contracting Officer.

3.3.6 Survey Data

After the driving of each pile group is complete and before superimposed concrete is placed, provide the Contracting Officer with an as-driven survey showing actual location and top elevation of each pile. Submit an as-driven survey showing actual location and top elevation of each production pile within 7 calendar days of completing the pile installation. Do not proceed with placing concrete until the Contracting Officer has reviewed the survey and verified the safe load for the pile group driven. Present a survey in such form that it gives deviation from plan location in two perpendicular directions and elevations of each pile to nearest half inch . Survey must be prepared and certified by a land surveyor licensed in California.

3.4 INSTALLATION RECORDS

Maintain a pile driving record for each sheet pile driven. Indicate on the installation record: installation dates and times, type and size of hammer, rate of operation, total driving time, dimensions of driving helmet and cap used, blows required per foot for each foot of penetration, final driving resistance in blows for final 6 inches , pile locations, tip elevations, ground elevations, cut-off elevations, and any reheading or cutting of piles. Record any unusual pile driving problems during driving. Submit complete records to the Contracting Officer.

3.5 VIBRATION CONTROL

3.5.1 Vibration Best Management Practices

Reduce vibration from construction and operational activity. To help reduce any vibration-related impacts to structures and sensitive receptors, the following Best Management Practices (BMPs) would be used:

The construction contractor would be required to prepare a vibration plan

Final Submittal SECTION 31 41 16 Page 11 Issued for Construction prior to construction. The construction contractor would be required to employ vibration-reducing construction practices. Conduct pre-construction surveys for potential buildings and structures that could be affected by vibrations. Reduce vehicle and truck speeds to 10 miles per hour.

3.5.2 Vibration Monitoring

Perform vibration monitoring at the locations decided by the Contracting Officer during the pile driving operations. Perform vibration monitoring using seismographs and geophones within a distance of 200 feet from the pile driving activity. Engage the services of a qualified, independent vibration consultant, acceptable to the Government, to conduct the vibration monitoring. The vibration consultant must have minimum of five years of experience in vibration monitoring. A minimum of 28 days before the installation of vibration monitors, submit to the Government the name of the vibration consultant and a list of at least three previously completed projects of similar scope and purpose.

Prior to the pile driving activities, obtain baseline readings of ambient vibrations. The vibration during the pile driving activities must be limited to a peak particle velocity of not more than 2 inches per second .

Determine appropriate vibration limits as per American Association of State Highway and Transportation Officials (AASHTO) guidelines. During pile driving activities, monitor the vibrations to ensure the limits are not exceeded. If the limits are exceeded, cease the pile driving activity causing the vibration until the Vibration consultant and the Contracting Officer are on site to observe the structures nearest to the vibration monitor which has exceeded the limits.

The Contractor must be responsible for all damages resulting from the pile driving operations and must take whatever measures necessary to maintain peak particle velocity within the specified limit. After completion of the project, remove the vibration monitors off the site and off Government property and restore the monitoring locations back to their original condition.

3.6 NOISE CONTROL

Perform noise monitoring at the locations decided by the Contracting Officer at noise sensitive public areas during the pile driving operations. Perform noise monitoring using noise meters. Engage the services of a qualified, independent noise consultant, accept able to the Government, to conduct the noise monitoring. The noise consultant must have minimum of five years of experience in noise monitoring. A minimum of 28 days before the installation of noise monitors, submit to the Government the name of the noise consultant and a list of at least three previously completed projects of similar scope and purpose.

Prior to the pile driving activities, obtain baseline readings of ambient noise levels. Determine appropriate noise limits as per Occupation Safety and Health Administration guidelines. During pile driving activities, monitor the noise to ensure the limits are not exceeded. If the limits are exceeded, cease the pile driving activity and install noise mitigation measures.

The Contractor must be responsible for all damages resulting from the pile driving operations and must take whatever measures necessary to maintain noise within the specified limit. After completion of the project, remove

Final Submittal SECTION 31 41 16 Page 12 Issued for Construction the noise monitors off the site and off Government property and restore the monitoring locations back to their original condition.

3.7 PRECONSTRUCTION CONDITION SURVEY

Perform preconstruction condition survey of structures and utilities within 200 feet of the pile driving activity. Perform outreach to the owner of the structures 28 days before performing the preconstruction condition survey. The Contractor must obtain written permission from the owner of the structure prior to accessing the structure. The preconstruction condition survey must include video and photographic documentation of the exterior and interior of above ground structures and of the interior of underground structures. Video documentation must be in high definition, and show existing conditions and highlight, where possible, existing cracks, deteriorated concrete, exposed and corroded reinforcement, cracked or broken brick or mortar, and other signs of distress. For utilities, perform the survey when the greatest extent of the interior is exposed.

Provide supplementary artificial lighting as needed. The video must include annotation with location and structure nomenclature which describes any areas of distress over the video and time code superimposed on the video. Photographs must be accompanied by sketches or descriptions that indicate the location and direction of each photograph. For each structure surveyed, provide a Pre-Construction Condition Survey Report following completion of the survey. The report must contain all documentation associated with the survey including DVD copies. In the report, include notes, sketches, photographs, and videos. Provide general information, such as location details and structure type, as well as particular information on materials, condition, existing damage, aperture and persistence of cracks, and disrepair observed during visual survey.

Provide a graphical depiction of locations of damage or other features of concern. Submit the Preconstruction Condition Survey Reports no later than 28 days before the commencement of pile driving activity. Accept responsibility for damages to existing adjacent or adjoining structures created by pile driving work, and repair any damages to these structures without cost to the Government.

-- End of Section --

Final Submittal SECTION 31 41 16 Page 13 Issued for Construction

File details come from the government source that posted it. Updated .