Pajaro FRM Reach 6_Specifications.pdf

PDF 3 MB Posted

Attached to
Pajaro River Reach 6
Solicitation number
W912P725BA012
Issued by

About this file

The file is a comprehensive set of technical specifications for the Pajaro River Flood Risk Management Project Reach 6 contract, located in Santa Cruz County, California. The project involves constructing approximately 2.6 miles of flood risk management levees, which includes 111,600 cubic yards of compacted fill and 1,500 linear feet of floodwalls along the Corralitos Creek. The engineered levees will have crest elevations ranging from 2 to 8 feet, a minimum crest width of 20 feet, and 3H:1V side slopes, with an access road surfaced with 8 inches of CalTrans Class 2 Aggregate Base.

The contract (W912P725BA012) is managed by the U.S. Army Corps of Engineers San Francisco District, with an estimated cost range between $25-$100 million. The solicitation will be available around July 1, 2025, with bids due on August 8 at 12:00 PM PDT. Prospective bidders must be registered in the System for Award Management (SAM) and the Procurement Integrated Enterprise Environment (PIEE) website to view solicitation documents and submit offers electronically. The project encompasses an area of approximately 10,000 acres within the lower Pajaro River watershed, spanning Santa Cruz and Monterey Counties, with the Highway 152 Bridge raising project being a separate concurrent effort.

View the file

Other files

File Type Posted
Bid Abstract SF 1419 Pajaro Reach 6.pdf PDF
Solicitation Amendment W912P725BA012 0006.pdf PDF
Solicitation Amendment 5 W912P725BA0120005 SF 30.pdf PDF
RFI Set 3 8.15.2025.pdf PDF
Amendment 5 -C-13.pdf PDF
Amendment 5- Revised Specification Section 31 63 29.pdf PDF
RFIs Set 2 W912P725BA012.pdf PDF
31 41 16.pdf PDF
Amendment4 C Sheets 2 of 2.pdf PDF
Amendment 4 C Sheets 1 of 2.pdf PDF
01 50 00 (Revision 2 Entire Spec Section).pdf PDF
TREE SURVEY DATA.pdf PDF
Solicitation Amendment 0004 W912P725BA012 SF 30 FINAL.pdf PDF
01 50 00 (Revision 1 Page Removal of Field Office).pdf PDF
Solicitation Amendment W912P725BA0120003 SF 30.pdf PDF
RFIs Posted 7.31.2025.pdf PDF
01 20 00.pdf PDF
32 31 13.54.pdf PDF
Pajaro Reach6-Amendment3.pdf PDF
Amendment 2_No Work Zone.pdf PDF
2022_A3Geo_Phase 1 Geotechnical Investigation.pdf PDF
Pajaro Existing Geotech Data DRAFT 033122.pdf PDF
Solicitation Amendment W912P725BA0120002 SF 30 7.22.2025.pdf PDF
2023_A3Geo_Phase 2 Geotechnical Investigation.pdf PDF
Pajaro Reach 6 - CONTRACTOR SITE WALK ATTENDANCE.pdf PDF
Pajaro Reach 6 Conflict Items 7.16.2025.pdf PDF
Amendment 1_ W912P725BA0120001 SF 30.pdf PDF
Pajaro FRM-Reach 6-100percent-AppendixH-Improvement Plans (Signed).pdf PDF
W912P7BA012 Pajaro IFB FINAL 7.3.2025.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pajaro River Flood Risk Management Project

Contract No: W912P725BA012

Reach 6

PROJECT TABLE OF CONTENTS Page 1

June 2025

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/22 WORK RESTRICTIONS

01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

00.15

10 11/16, 11/20, CHG

CHG

2:

2:

08/19

08/22

RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

TEMPORARY CONSTRUCTION FACILITIES AND

01 57 19

08/22

CONTROLS

TEMPORARY ENVIRONMENTAL CONTROLS

01 57 23.00 41 04/15 TEMPORARY STORMWATER POLLUTION CONTROL

01 71 10 MOBILIZATION AND DEMOBILIZATION

02/19, 05/19, CHG

CHG

3:

1:

11/21

08/21

CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 08/22 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00

02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE

DIVISION 05 - METALS

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

DIVISION 09 - FINISHES

09 90 00 02/21 PAINTS AND COATINGS

09 97 02.03 10/08 PAINTING: EPOXY SYSTEMS

DIVISION 10 - SPECIALTIES

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE

DIVISION 31 - EARTHWORK

31 41 16 11/20 METAL SHEET PILING

31 63 29 11/19 DRILLED CONCRETE PIERS AND SHAFTS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 23

32 12 16.16

05/22

11/20

AGGREGATE BASE COURSE FOR FLEXIBLE

PAVING

HOT-MIX ASPHALT PAVING

32 31 13.54 05/25 BURIED CHAIN-LINK FENCE FOR RODENT

CONTROL

Reach 6

32 31 26 11/21 WIRE FENCES AND GATES

32 92 19 08/17, CHG 1: 08/21 SEEDING

DIVISION 33 - UTILITIES

33 40 00 11/21 STORMWATER UTILITIES

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 16.54 05/21 SLIDE GATES AND FLAP GATES

35 31 19 01/08, CHG 1: 11/14 ROCK SLOPE PROTECTION

35 41 00 11/18, CHG 1: 02/20 LEVEE CONSTRUCTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2

Reach 6

Final Submittal

SECTION 01 11 00 Page 1 Issued for Construction

SECTION TABLE OF CONTENTS

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

PART 1 GENERAL

1.1 SUBMITTALS

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.3 CONTRACT DRAWINGS

1.4 EXISTING WORK

1.5 ON-SITE PERMITS

1.5.1 Utility Outage Requests and Utility Connection Requests

1.5.2 Borrow, Excavation, Welding, and Burning Permits

1.6 LOCATION OF UNDERGROUND UTILITIES

1.6.1 Notification Prior to Excavation

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

Reach 6

Final Submittal

SECTION 01 11 00 Page 2 Issued for Construction

PART 1 GENERAL

1.1 SUBMITTALS

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

Government approval is required for submittals with a "G" designation.

Submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. "SPN" - San Francisco

District. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests

Utility Connection Requests

Borrow Permits

Excavation Permits

Welding Permits

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes mobilization and demobilization, traffic control and coordination, clearing and grubbing, installation of truck wash-down racks and construction entrance, temporary chain link fencing and gates, temporary erosion control, removal and relocation of utilities, removal, demolition, and disposal of existing fence, appurtenant structures, pipes and gates, and pavement, excavation of levee inspection trench, levee degrade and rebuild excavation, compacted levee fill, compacted general fill, compacted embankment grading, pipe and pipe penetrations, wire fence and gates, rock slope protection fabric, rock slope protection, placement of compacted class 2 aggregate base rock, asphalt concrete Type A, floodwalls, and incidental related work.

1.2.2 Location

The work is located in Santa Cruz County along the right and left banks of

Corralitos Creek between the Highway 152 bridge crossing and Green Valley

Road,, approximately as indicated. The exact location will be shown in the Contract Documents.

1.3 CONTRACT DRAWINGS

The following drawings accompany this specification and are a part thereof.

Drawing Sheets 1 through 89

Reach 6

Final Submittal

SECTION 01 11 00 Page 3 Issued for Construction

USACE will provide Contractor with electronic PDF format documents of contract drawings, maps, and specifications. Contractor to provide two printed hard copy sets of full-size contract drawings, maps, and specifications to USACE without charge. Contractor shall acquire reference publications referenced in the specifications and plans.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 ON-SITE PERMITS

1.5.1 Utility Outage Requests and Utility Connection Requests

Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

Submit requests for utility outages and connections in writing to the

Contracting Officer for approval at least 15 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.5.2 Borrow, Excavation, Welding, and Burning Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Borrow Permits 30 calendar days prior to work

County

Excavation Permits 30 calendar days prior to work

County

Welding Permits/Hot Work Permit 30 calendar days prior to work

Cal OSHA

Post permits at a conspicuous location in the construction area.

Burning of trash or rubbish is not permitted on project site.

1.6 LOCATION OF UNDERGROUND UTILITIES

Comply with local requirements for locating and marking underground

Reach 6

Final Submittal

SECTION 01 11 00 Page 4 Issued for Construction utilities. Contact local utility locating service a minimum of 72 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.6.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

Reach 6

Final Submittal

SECTION 01 14 00 Page 1 Issued for Construction

SECTION 01 14 00

WORK RESTRICTIONS

11/22

PART 1 GENERAL

1.1 SUBMITTALS

1.2 SPECIAL SCHEDULING REQUIREMENTS

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Subcontractors and Personnel Contacts

1.3.2 Working Hours

1.3.3 Work Outside Regular Hours

1.3.4 Utility Cutovers and Interruptions

Reach 6

Final Submittal

SECTION 01 14 00 Page 2 Issued for Construction

1.1 SUBMITTALS

SECTION 01 14 00

WORK RESTRICTIONS

11/22

Government approval is required for submittals with a "G" designation.

Submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. "SPN" - San Francisco

District. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

1.2 SPECIAL SCHEDULING REQUIREMENTS

a. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

b. The contractor must notify the Government at least 14 days prior to any ground disturbing activities, including any clearing and grubbing. A Pre-Construction Biological Resources Survey must be conducted by a Contractor-supplied qualified biologist no more than

1-week prior to ground disturbing activities in each year of construction to identify special- status amphibians, reptiles, and nesting birds present within 50 feet (or nesting raptors within 300 feet) of the proposed construction areas, staging areas, and private access roads to be utilized for the project.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.2 Working Hours

Regular working hours will consist of an 10 hour period established by the

Contracting Officer, between 7 a.m. and 5:00 p.m., Monday to Friday, excluding Government holidays.

1.3.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, Reach 6

Final Submittal

SECTION 01 14 00 Page 3 Issued for Construction contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.

1.3.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The

Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting

Officer giving reasonable advance notice when such operation is required.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Reach 6

Final Submittal

SECTION 01 20 00 Page 1 Issued for Construction

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20, CHG 2: 08/21

1.1 REFERENCES

1.2 SUBMITTALS

1.3 CONTRACT COST BREAKDOWN

1.4 CONTRACT MODIFICATIONS

1.5 PAYMENTS TO THE CONTRACTOR

1.5.1 Obligation of Government Payments

1.5.2 Payment for Onsite and Offsite Materials

1.6 SINGLE JOB PAYMENT ITEMS

1.6.1 Mobilization and Demobilization

1.6.1.1 Payment

1.6.1.2 Unit of Measure

1.6.2 Construction of Reach 6 Levees

1.6.2.1 Payment

1.6.2.2 Unit of Measure

1.6.3 Construction of Reach 6 Floodwalls

1.6.3.1 Payment

1.6.3.2 Unit of Measure

Reach 6

Final Submittal

SECTION 01 20 00 Page 2 Issued for Construction

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20, CHG 2: 08/21

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2021) Engineering and Design --

Construction Equipment Ownership and

Operating Expense Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. "SPN" - San Francisco

District. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

1.3 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to

Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the

Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause DFARS 252.236-7000 Modification

Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the

EP 1110-1-8.

1.5 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

Reach 6

Final Submittal

SECTION 01 20 00 Page 3 Issued for Construction

1.5.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting

Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR

32.103 Progress Payments Under Construction Contracts:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this Contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.

1.5.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with requirement of this Contract. Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental

United States. Other locations are subject to written approval by the

Contracting Officer.

Reach 6

Final Submittal

SECTION 01 20 00 Page 4 Issued for Construction

g. Materials in transit to the job site or storage site are not acceptable for payment.

1.6 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in the PROPOSAL SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.6.1 Mobilization and Demobilization

1.6.1.1 Payment

Payment will be made for costs associated with mobilization and demobilization, as defined in Special Contract PAYMENT FOR MOBILIZATION

AND DEMOBILIZATION.

1.6.1.2 Unit of Measure

Unit of measure: job.

1.6.2 Construction of Reach 6 Levees

This item shall include all labor, equipment, and materials to construct the new levees from Station RB2+39.49 to RB61+02 and between Stations

LB0+95.73 to LB82+74 to top of new levee elevations. Work includes but is not limited all required demolition, placement of site safety equipment and fencing successful demonstration of construction means and methods, quality control, excavation, import of levee fill and placement, excavation of inspection trench, excavation of borrow material, construction and operation of contractor site project offices, traffic control, safety, environmental monitoring and requirements compliance, and all other incidental work.

This item shall include all labor, equipment and materials all levee maintenance including erosion protection and storm water pollution prevention and control, placement of rock slope protection, construction of inlet and outlet structures, pipe penetrations and appurtenant structures, levee crest roadway construction, construction of fencing and gates, rodent and erosion matting construction, top soil placement, and seeding.

1.6.2.1 Payment

Payment will be made for costs associated with operations necessary for construction of these features and providing required services.

1.6.2.2 Unit of Measure

Unit of measure: job.

Reach 6

Final Submittal

SECTION 01 20 00 Page 5 Issued for Construction

1.6.3 Construction of Reach 6 Floodwalls

This item shall include all labor, equipment, and materials to construct the new floodwalls from Station RB0+89.37 to RB4+46.5 and between Stations

LB0+88 to LB2+76 and between Stations LB81+93 to LB91+45 to top of new floodwall elevations. Work includes but is not limited all required demolition, placement of site safety equipment and fencing successful demonstration of construction means and methods, quality control, structure excavation, construction of floodwall piles, floodwall footing, floodwall stem, sheet piles, construction and operation of contractor site project offices, traffic control, safety, environmental monitoring and requirements compliance, and all other incidental work.

1.6.3.1 Payment

Payment will be made for costs associated with operations necessary for construction of the floodwalls.

1.6.3.2 Unit of Measure

Unit of measure: job.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Reach 6

Final Submittal

SECTION 01 30 00 Page 1 Issued for Construction

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 2: 05/22

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 VIEW LOCATION MAP

1.4 PROGRESS AND COMPLETION PICTURES

1.5 SUPERVISION

1.5.1 Superintendent Qualifications

1.5.2 Minimum Communication Requirements

1.5.3 Duties

1.5.4 Non-Compliance Actions

1.6 PRECONSTRUCTION MEETING CONFERENCE

1.6.1 Attendees

1.7 PARTNERING

1.7.1 Facilitated (Formal) Partnering

1.8 MOBILIZATION

Reach 6

Final Submittal

SECTION 01 30 00 Page 2 Issued for Construction

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 2: 05/22

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health

Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. "SPN" - San Francisco

District. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Include aerial photographs. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting

Officer. Submit with the monthly invoice a set of digital photographs, in PDF format,cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch in the electronic PDF format. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

Reach 6

Final Submittal

SECTION 01 30 00 Page 3 Issued for Construction

1.5 SUPERVISION

1.5.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.5.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.5.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.5.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting

Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the

Contractor.

1.6 PRECONSTRUCTION MEETING CONFERENCE

Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the

Preconstruction Meeting Conference. The meeting conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:

daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required

Reach 6

Final Submittal

SECTION 01 30 00 Page 4 Issued for Construction phasing.

1.6.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.7 PARTNERING

To most effectively accomplish this Contract, the Contractor and

Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of

Record are required to participate in the Partnering process.

1.7.1 Facilitated (Formal) Partnering

a. Within 35 calendar days after award, and notice to proceed, and prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and

Government personnel. All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the

Contractor.

b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with

Partnering.

c. The Initial Partnering Session must be a duration of one day and be held at a location agreed to by the Contracting Officer. Partnering session may take place concurrently with the Pre-Construction

Post-Award Kickoff Meeting.

d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant

- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.

e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.

f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.

Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the

Reach 6

Final Submittal

SECTION 01 30 00 Page 5 Issued for Construction follow-on sessions unless an alternative is permitted by the

Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.

1.8 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days after notice to proceed and contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 1 Issued for Construction

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

2.1.2.2 Other Than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Procurement Activities

3.3.4 Mandatory Tasks

3.3.5 Government Activities

3.3.6 Standard Activity Coding Dictionary

3.3.6.1 Workers Per Day (WRKP)

3.3.6.2 Responsible Party Coding (RESP)

3.3.6.3 Area of Work Coding (AREA)

3.3.6.4 Modification Number (MODF)

3.3.6.5 Bid Item Coding (BIDI)

3.3.6.6 Phase of Work Coding (PHAS)

3.3.6.7 Category of Work Coding (CATW)

3.3.6.8 Feature of Work Coding (FOW)

3.3.7 Contract Milestones and Constraints

3.3.7.1 Project Start Date Milestone and Constraint

3.3.7.2 End Project Finish Milestone and Constraint

3.3.7.3 Interim Completion Dates and Constraints

3.3.7.3.1 Start Phase

3.3.7.3.2 End Phase

3.3.8 Calendars

3.3.9 Open Ended Logic

3.3.10 Default Progress Data Disallowed

3.3.11 Out-of-Sequence Progress

3.3.12 Added and Deleted Activities

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 2 Issued for Construction

3.3.13 Original Durations

3.3.14 Leads, Lags, and Start to Finish Relationships

3.3.15 Retained Logic

3.3.16 Percent Complete

3.3.17 Remaining Duration

3.3.18 Cost Loading of Closeout Activities

3.3.18.1 As-Built Drawings

3.3.18.2 O & M Manuals

3.3.19 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.3 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Data CD/DVDs

3.5.2 Narrative Report

3.5.3 Schedule Reports

3.5.3.1 Activity Report

3.5.3.2 Logic Report

3.5.3.3 Total Float Report

3.5.3.4 Earnings Report by CLIN

3.5.3.5 Schedule Log

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

3.5.4.2 Project Milestone Dates

3.5.4.3 Critical Path

3.5.4.4 Banding

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUESTS FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Time Impact Analysis (Prospective Analysis)

3.8.3 Forensic Schedule Analysis (Retrospective Analysis)

3.8.4 Fragmentary Network (Fragnet)

3.8.5 Time Extension

3.8.6 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 3 Issued for Construction

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (2017) Administration -- Project Schedules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. "SPN" - San Francisco

District. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G, (SPN)

Preliminary Project Schedule; G, (SPN)

Initial Project Schedule; G, (SPN)

Periodic Schedule Update; G, (SPN)

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 4 Issued for Construction

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to

FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical

Path Method (CPM) of network calculation to generate all Project

Schedules. Prepare each Project Schedule using the Precedence Diagram

Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 5 Issued for Construction

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original

Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals

(individual activity for each).

b. Submission, review and acceptance of features require design completion

Submission, review and acceptance of design packages.

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 6 Issued for Construction

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Other systems testing, if required.

h. Contractor's pre-final inspection.

i. Correction of punch list from Contractor's pre-final inspection.

j. Government's pre-final inspection.

k. Correction of punch list from Government's pre-final inspection.

l. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and

Notice to Proceed (NTP) for phasing requirements.

3.3.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange

Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil.

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work* http://rms.usace.army.mil/

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 7 Issued for Construction

Field Activity Code Length Description

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.6.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government

Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.6.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work

Area coding indicates the activity is not resource or space constrained.

3.3.6.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the

Government's modification numbering system. An activity can have only one

Modification Number Code.

3.3.6.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 8 Issued for Construction

Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.6.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.6.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to review conferences, permits, construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities.

Each activity can have no more than one Category of Work Code.

3.3.6.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the

Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY

CONTROL. An activity can have only one Feature of Work Code.

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting

Officer for approval on a case by case basis.

3.3.7.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End

Project."

Constrain the project schedule to the Contract Completion Date in such a

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 9 Issued for Construction way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the

"End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate

Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Clauses. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.

3.3.9 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP

Acknowledged" may have no predecessor logic, and the last activity -"End

Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

3.3.10 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish

(AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document

Reach 6

Final Submittal

SECTION 01 32 01.00 10 Page 10 Issued for Construction the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.

3.3.11 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.

Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

3.3.12 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity

ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.

3.3.13 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

3.3.14 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.3.15 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished…

This is the start of the file's text. The full file is on GovTribe.