This document appears to be a section of a construction contract (Section 01 50 00) for the Pajaro River Flood Risk Management Project, Contract No: W912P725BA012. The section provides detailed requirements for contractor temporary facilities and administrative field offices. Key specifications include performing backflow preventer tests quarterly using specific certification procedures, and establishing a temporary administrative field office with precise requirements such as minimum dimensions (12 feet wide, 16 feet long, 7 feet headroom), electrical specifications (24kVA service, 110-120 volt power), and furnishings including a work table, desk, chairs, file cabinet, refrigerator, and microwave. The field office must also include security features like deadbolt locks, non-removable door hinge pins, window screens, and air conditioning capabilities.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pajaro River Flood Risk Management Project Reach 6 Contract No: W912P725BA012 supply.
Perform backflow preventer tests using test equipment, procedures, and certification forms conforming to those outlined in the latest edition of the Manual of Cross-Connection Control published by the FCCCHR Manual.
Test and tag each reduced pressure backflow preventer upon initial installation (prior to continued water use) and quarterly thereafter. Tag must contain the following information: make, model, serial number, dates of tests, results, maintenance performed, and signature of tester.
Record test results on certification forms conforming to requirements cited earlier in this paragraph.
3.5 CONTRACTOR'S TEMPORARY FACILITIES
Contractor-owned or -leased trailers must be identified by Government assigned numbers. Apply the number to the trailer within 14 calendar days of notification, or sooner, if directed by the Government. Temporary facilities must meet requirements as identified in EM 385-1-1 Section 04.
Contractor is responsible for security of their property. Provide adequate outside security lighting at the temporary facilities. Trailers must be anchored to resist high winds and meet applicable state or local standards for anchoring mobile trailers. Coordinate anchoring with EM 385-1-1 Section 04. The Contract Clause entitled "FAR 52.236-10, Operations and Storage Areas" and the following apply:
3.5.1 Administrative Field Offices
Provide and maintain administrative field office facilities for the Government within one of the designated staging areas to be determined by the Government. Government office and warehouse facilities will not be available to the Contractor's personnel.
Provide a temporary administrative field office that is a minimum 12 feet in width, 16 feet in length and have a minimum of 7 feet of headroom.
Equip the building with approved electrical wiring, at least one double convenience outlet and the required switches and fuses to provide 110-120 volt power. Electric service with a minimum 24kVA service shall be provided to the building. Provide a work table with stool, desk with chair, two additional chairs, and one legal size file cabinet that can be locked. Provide a minimum of one 9 cubic feet of refrigerator and one microwave oven. The building must be waterproof, supplied with a heater, have a minimum of two doors, electric lights, a telephone, a battery-operated smoke detector alarm, a sufficient number of adjustable windows for adequate light and ventilation, and a supply of approved drinking water. Provide approved sanitary facilities. Screen the windows and doors and provide the doors with deadbolt type locking devices or a padlock and heavy-duty hasp bolted to the door. Door hinge pins must be non-removable. Arrange the windows to open and to be securely fastened from the inside. Protect glass panels in windows by bars or heavy mesh screens to prevent easy access. In warm weather, provide air conditioning capable of maintaining the office at 50 percent relative humidity and a room temperature 20 degrees F below the outside temperature when the outside temperature is 95 degrees F . Unless otherwise directed by the Contracting Officer, remove the building from the site upon completion and acceptance of the work.
Final Submittal SECTION 01 50 00 Page 10 Issued for Construction June 2025 ezane Strikethrough Provide and maintain administrative field office facilities for the Government within one of the designated staging areas to be determined by the Government. Government office and warehouse facilities will not be available to the Contractor's personnel.
ezane Strikethrough Provide a temporary administrative field office that is a minimum 12 feet in width, 16 feet in length and have a minimum of 7 feet of headroom.
Equip the building with approved electrical wiring, at least one double convenience outlet and the required switches and fuses to provide 110-120 volt power. Electric service with a minimum 24kVA service shall be provided to the building. Provide a work table with stool, desk with chair, two additional chairs, and one legal size file cabinet that can be locked. Provide a minimum of one 9 cubic feet of refrigerator and one microwave oven. The building must be waterproof, supplied with a heater, have a minimum of two doors, electric lights, a telephone, a battery-operated smoke detector alarm, a sufficient number of adjustable windows for adequate light and ventilation, and a supply of approved drinking water. Provide approved sanitary facilities. Screen the windows and doors and provide the doors with deadbolt type locking devices or a padlock and heavy-duty hasp bolted to the door. Door hinge pins must be non-removable. Arrange the windows to open and to be securely fastened from the inside. Protect glass panels in windows by bars or heavy mesh screens to prevent easy access. In warm weather, provide air conditioning capable of maintaining the office at 50 percent relative humidity and a room temperature 20 degrees F below the outside temperature when the outside temperature is 95 degrees F. Unless otherwise directed by the Contracting Officer, remove the building from the site upon completion and acceptance of the work.