SECTION 01100 - SUMMARY

View the file

Other files

File Type Posted
P-153.pdf PDF
014-C-061.pdf PDF
01500.pdf PDF
261200r.pdf PDF
024-C-652.pdf PDF
018-C-204.pdf PDF
L-110.pdf PDF
003-G-021.pdf PDF
031-E-401.pdf PDF
033-E-602.pdf PDF
015-C-201.pdf PDF
P-406.pdf PDF
01420.pdf PDF
P-610.pdf PDF
013-C-055.pdf PDF
027-E-001.pdf PDF
011-C-053.pdf PDF
01310.pdf PDF
01350.pdf PDF
006-G-083.pdf PDF
004-G-081.pdf PDF
007-C-021.pdf PDF
010-C-052.pdf PDF
01320.pdf PDF
005-G-082.pdf PDF
L-109.pdf PDF
32 12 15.pdf PDF
022-C-301.pdf PDF
002-G-002.pdf PDF
01340.pdf PDF
021-C-211.pdf PDF
32 92 19.pdf PDF
009-C-051.pdf PDF
01700.pdf PDF
019-C-205.pdf PDF
01782.pdf PDF
01781.pdf PDF
017-C-203.pdf PDF
020-C-206.pdf PDF
025-C-653.pdf PDF
32 05 33.pdf PDF
026-C-671.pdf PDF
001-G-001.pdf PDF
01330.pdf PDF
32 17 24.00 10.pdf PDF
32 12 10.pdf PDF
030-E-203.pdf PDF
01162.pdf PDF
L-108.pdf PDF
SpecCover_TOC.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01100 - 1 MEAD & HUNT, Inc.

SECTION 01100 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Use of premises.

3. Government’s occupancy requirements.

4. Work restrictions.

5. Specification formats and conventions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Repair Military Taxiway, Project No. TQKD022200

1. Project Location: Portland Air National Guard Base, 6801 NE Cornfoot Road, Portland, Oregon.

B. The Work consists of the following:

1. The Work includes Asphalt milling and paving; airfield safety and security; airfield marking; taxiway centerline lights; a power regulator; and airfield lighting controls.

C. The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complimentary, and what is required by one shall be as binding as if required by all. Performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the intended results. The Contractor will understand that the work herein described shall be complete in every detail, not withstanding every item necessarily involved is not particularly mentioned and the Contractor shall be held to provide all labor and material for the entire work intended to be described.

D. The Contractor is responsible for construction means, methods, techniques, sequences, and procedures. The drawings are graphical in nature and intended to convey the scope of the work to be performed. The Contractor is responsible for determining what is necessary to construct complete and functioning buildings and systems as may reasonably be inferred from the Contract Documents

1.3 USE OF PREMISES

A. The project is on a closed Base and, as such, only those persons granted permission may enter. It is, therefore, required that control be exercised over Contractor personnel while working on the Base. To maintain this control, a listing of all Contractor personnel who will be working under the contract, must be submitted to the Contracting Officer five working days prior to the start of work under the contract. The preferred method of providing this list is via email, to the contract administrator. The listing shall include, but not limited to: contract number, project number, employee name, and the estimated starting and ending date of each employee.

01100 - 2 MEAD & HUNT, Inc.

Subsequent listings of all additions or deletions will be submitted as employees are hired or released.

B. During construction, the Contractor shall permit base personnel access to the facilities within the work area. The Contractor shall provide protection to persons and property throughout the progress of the work.

C. In the event of a declared National Emergency the Contracting Officer may be required to stop work on this contract for security reasons. Contractor shall ensure the Contracting Officer has a current “Off Duty” contact name and telephone number at all times to facilitate notification.

D. The Contractor shall inform all personnel working under his jurisdiction (including sub-contractor and visiting supplier personnel) that access to areas outside of the immediate work area excluding, direct haul and access routes, contracting and Civil Engineering offices and point of supply and storage is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

1.4 GOVERNMENT’S OCCUPANCY REQUIREMENTS

A. Government will occupy the site adjacent construction during the entire construction period and will occupy phases of construction already complete or not yet complete. Occupancy includes operating aircraft in areas adjacent the construction where no debris of any kind can exist, either intentionally or unintentionally. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s day-to-day operations.

1. Provide not less than two week’s notice to Government of activities that will affect

Government’s operations.

B. Government Occupancy:

1. The Government shall have the right to take possession of or use any completed or partially completed part of the work. Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use. However, failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government’s possession or use shall not be deemed an acceptance of any work under the contract.

2. While the Government has such possession or use, the Contractor shall be relieved of the responsibility for the loss of or damage to the work resulting from the Government’s possession or use, notwithstanding the terms of the clause in this contract entitled “Permits and Responsibilities.”

1.5 WORK RESTRICTIONS

A. Normal base work hours for the Contractor will be between the hours of 7:15 AM thru 4:00 PM, excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer three (3) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces and for notification of fire, security and safety. When the Contracting Officer determines that they are reasonably available, he may authorize the Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to

01100 - 3 MEAD & HUNT, Inc.

perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount.

B. The following Federal legal Holidays are observed by this Base:

New Year's Day 1 January Martin Luther's King's Birthday Third Monday of January President's Day Third Monday of February Memorial Day Last Monday of May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veteran's Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December

C. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday, holidays falling on a Sunday will be observed on the following Monday.

D. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more) commencement of any warranty work, and upon completion of warranty work, the Contractor must notify the Contracting Officer (or his/her Contracting Officer Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting Officer’s Representative is sufficient.

Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The above precautions are to ensure construction inspection and recording of work proceedings.

E. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by the Government and others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify COR not less than two weeks in advance of proposed utility interruptions.

2. Do not proceed with utility interruption without COR written permission.

1.6 SPECIFICATION FORMATS AND CONVENTIONS

A. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among Subcontractor or in establishing the extent of the work to be performed by any trade.

B. Specification Format: The Specifications are organized into Divisions and Sections.

1. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete because all available Section numbers are not used. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of Sections in the Contract Documents.

2. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.

01100 - 4 MEAD & HUNT, Inc.

C. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate.

Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications.

Requirements expressed in the imperative mood are to be performed by Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

D. CO: Contracting Officer

E. COR: Contracting Officer’s Representative

1.7 Safety Requirements (within Airport fencing)

See "Construction Operations and Phasing Plan" sheet in plan set for addition requirements

A. Taxiways and Apron: Construction activity adjacent to the taxiways and aprons which will be in use (active) shall be coordinated with COR and Airport Operations. Construction activity will be authorized after NOTAMS (notices to airmen) have been issued by the Airport; after marking, barricade and lighting provisions have been implemented by Contractor; and after it has been determined that the height of equipment and materials is beyond the reach of the aircraft or safely below any part of the aircraft using the operations areas which might overhang these areas.

B. Excavation and Trenches

1. Taxiway and Aprons: Excavation and open trenches may be permitted up to the edge of structural taxiway and apron pavements, provided the drop-off is adequately signed, lighted and marked, with the approval of the COR and Airport Operations.

C. Stockpiled Material: Extensive stockpiled materials will not be permitted within 750 feet from an active runway centerline and 250 feet from an active taxiway centerline, as directed by the COR or as shown in the “Construction Operations and Phasing Plans.”

1.8 Construction Vehicle Traffic (within Airport fencing)

See "Construction Operations and Phasing Plan" sheets in plan set for additional requirements.

A. All motorized vehicles operated by the Contractor on the airport shall be equipped with a 3-foot square flag, consisting of a checkered pattern of International Orange and White squares of not less than 1-foot on each side, displayed in full view above the vehicle. Alternatively or for periods of limited visibility or darkness, these vehicles shall also be equipped with flashing yellow light units.

01100 - 5 MEAD & HUNT, Inc.

B. Where Contractor's operations occur near active runways or taxiways involving air traffic, he shall provide sufficient flag person to properly route all construction equipment.

1.9 Limitations of Construction (within Airport fencing)

See "Construction Operations and Phasing Plan" sheet in plan set for addition requirements.

A. All vehicles are to be parked and serviced behind the construction restriction line 750 feet or more from an active runway centerline or 250 feet from an active taxiway centerline.

B. Open trenches, excavations and stockpiled material at the construction site should be prominently marked with orange flags and lighted with steady burning red light units (acceptable to the COR) during hours of restricted visibility and/or darkness. Under no circumstances are flare pots to be used near aircraft turning areas. Standard for flags is 20 inches square.

C. Stockpiled material shall be constrained in such a manner as to prevent movement as a result of aircraft blast or wind. Material should not be stored near aircraft turning areas or movement areas.

1.10 Marking and Lighting of Closed or Hazardous Areas on Airport (within Airport fencing)

See "Construction Operations and Phasing Plan" sheets in plan set for addition requirements.

A. The Contractor shall have a person on call 24 hours per day for emergency maintenance of airport hazard lighting and barricades.

B. The Contractor shall furnish and place portable barricades across apron or taxiways to keep vehicles from entering active areas and to keep aircraft from taxiing into areas under construction. Care shall be exercised by Contractor during construction adjacent to aprons and taxiways not to place barricades closer than the clear distances stated above. Contractor will be responsible for provision of evenly graded transition, using base course material at same grade as remaining pavement. Transition shall be no steeper than 10:1 slope. At night, barricades shall be equipped with red steady burning lights. Barricades shall have alternating colors of International Orange and White. Red lights shall be at least 5 candelas.

C. The Contractor may not close any active pavement area without giving the COR two weeks prior notice.

D. Spacing of barricades shall be a maximum of 10 feet center to center and for barrels 20 feet center to center. Barricades or barrels used shall be adequately weighted so as to withstand wind, propeller or jet blasts.

1.11 Airport Security (within Airport fencing)

See "Construction Operations and Phasing Plan" sheets in plan set for addition requirements.

A. In the interest of airport security, Contractor's forces shall be readily identifiable. Contractor will be required to certify at the Pre-construction Conference that he will observe and respond to Government’s and Airport's requirements for complying with airport operations requirements.

01100 - 6 MEAD & HUNT, Inc.

B. In the event that security is breached through the Contractor's neglect, Contractor shall pay Port of Portland all costs associated with the security breach, including, but not limited to, fines, legal costs, equipment replacement, and repair of damage.

C. Gates not used during times of hauling (when gate guard is not present) shall be closed and locked.

D. Contractor shall be responsible for any fines for TSA security violations resulting from their construction activities.

1.12 Maintenance of Traffic (within Airport fencing)

See "Construction Operations and Phasing Plan" sheet in plan set for addition requirements.

A. Vehicular traffic crossing any active runways and taxiways must allow aircraft traffic the right-of-way and a flag person equipped with a radio shall be provided to control crossings.

1.13 Construction Superintendent

A. The Contractor shall furnish a construction superintendent for the duration of the project to provide construction management.

B. The responsibilities of the construction superintendent include, but are not limited to:

coordination with the COR, the airport, FAA, and all subcontractors; scheduling of subcontractors; supervision of all construction; supervision of all signing, barricades and lighting; quality control, change order approval; scheduling and monitoring gate guards and haul routes; coordination with all utilities involved and attendance at all construction meetings.

C. The construction superintendent shall be employed by the prime contractor and shall be named at the preconstruction conference, subject to the approval of the COR. The superintendent cannot switch responsibility to a subcontractor or other individual unless approved by the COR.

The superintendent will be available 24 hours a day and will be on the construction site when there is any construction activity on the airport, unless otherwise approved by the COR. During times of day and night work schedules, the superintendent may appoint an additional superintendent, as approved by the COR. At all times during construction, one of these approved superintendents must be on the airport, unless otherwise approved by the COR.

D. Weekly construction meetings will be required unless otherwise authorized by the COR. Daily meetings may be scheduled if desired by the COR, during critical periods.

E. This item also includes separate construction trailers and phone services to be used for the construction superintendent if he deems one necessary.

1.14 Requirements for Airport Identification Badges

A. Purpose

To establish the procedures and guidelines for use in the identification of the contractor personnel during the construction of this project.

B. Scope

01100 - 7 MEAD & HUNT, Inc.

All contractor personnel working inside the airport perimeter fence are required to be badged when on the project site Requirements for ID badges may change if required to provide for the continued safety of the traveling public.

Failure to follow the requirements of the badging guide may result in fines from the Transportation Safety Administration (TSA), the airport or both.

C. Payment

No direct payment will be made for ID badges, the costs of all badge requirements outlined in the guide shall be included in the contract sum.

1.15 Airport Security

A. In the interest of airport security, Contractor's forces shall be readily identifiable. Contractor will be required to certify at the Pre-construction Conference that he will observe and respond to Airport Director's requirements for complying with the Airport Operations Manual. Security Badges issued by the Airport will be required for the Contractor's forces, which will be discussed at the Pre-construction Conference.

B. The Contractor shall have a designated person on call 24 hours per day for emergency maintenance of barricades, temporary fencing, or other security issues that arise as a result of the project construction.

C. No motor vehicles of any type shall be allowed to park overnight or unattended without prior authorization from Airport Operations and the COR.

D. In the event that security is breached through the Contractor's neglect, Contractor shall pay Airport all costs associated with the security breach, including, but not limited to, fines, legal costs, equipment replacement, and repair of damage.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION