32 92 19.pdf
PDF 28 KB Posted
- Attached to
- Repair Military Taxiway located at the Portland Air National Guard Base, Portland, Oregon
- Solicitation number
- W912JV-09-R-0008
About this file
SEEDING
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P-153.pdf | ||
| 014-C-061.pdf | ||
| 01500.pdf | ||
| 261200r.pdf | ||
| 024-C-652.pdf | ||
| 018-C-204.pdf | ||
| L-110.pdf | ||
| 003-G-021.pdf | ||
| 031-E-401.pdf | ||
| 033-E-602.pdf | ||
| 015-C-201.pdf | ||
| P-406.pdf | ||
| 01420.pdf | ||
| P-610.pdf | ||
| 013-C-055.pdf | ||
| 027-E-001.pdf | ||
| 011-C-053.pdf | ||
| 01310.pdf | ||
| 01350.pdf | ||
| 006-G-083.pdf | ||
| 004-G-081.pdf | ||
| 007-C-021.pdf | ||
| 010-C-052.pdf | ||
| 01320.pdf | ||
| 005-G-082.pdf | ||
| L-109.pdf | ||
| 32 12 15.pdf | ||
| 022-C-301.pdf | ||
| 002-G-002.pdf | ||
| 01340.pdf | ||
| 021-C-211.pdf | ||
| 009-C-051.pdf | ||
| 01700.pdf | ||
| 019-C-205.pdf | ||
| 01782.pdf | ||
| 01781.pdf | ||
| 017-C-203.pdf | ||
| 020-C-206.pdf | ||
| 025-C-653.pdf | ||
| 32 05 33.pdf | ||
| 026-C-671.pdf | ||
| 001-G-001.pdf | ||
| 01330.pdf | ||
| 32 17 24.00 10.pdf | ||
| 32 12 10.pdf | ||
| 030-E-203.pdf | ||
| 01162.pdf | ||
| L-108.pdf | ||
| SpecCover_TOC.pdf | ||
| 01600.pdf |
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 32 92 19 Page 1
SECTION 32 92 19
SEEDING
10/06
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C 602 (2007) Agricultural Liming Materials
ASTM D 4427 (2007) Peat Samples by Laboratory Testing
ASTM D 4972 (2001; R 2007) pH of Soils
U.S. DEPARTMENT OF AGRICULTURE (USDA)
AMS Seed Act (1940; R 1988; R 1998) Federal Seed Act
DOA SSIR 42 (1996) Soil Survey Investigation Report No.
42, Soil Survey Laboratory Methods Manual, Version 3.0
1.2 DEFINITIONS
1.2.1 Stand of Turf
95 percent ground cover of the established species.
1.3 RELATED REQUIREMENTS
Section 31 00 00 EARTHWORK, and Section 32 05 33 LANDSCAPE ESTABLISHMENT applies to this section for pesticide use and plant establishment requirements, with additions and modifications herein.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Wood cellulose fiber mulch
Fertilizer
Include physical characteristics, and recommendations.
SECTION 32 92 19 Page 2
SD-06 Test Reports
Topsoil composition tests (reports and recommendations).
SD-07 Certificates
State certification and approval for seed
1.5 DELIVERY, STORAGE, AND HANDLING
1.5.1 Delivery
1.5.1.1 Seed Protection
Protect from drying out and from contamination during delivery, on-site storage, and handling.
1.5.1.2 Fertilizer and Lime Delivery
Deliver to the site in original, unopened containers bearing manufacturer's chemical analysis, name, trade name, trademark, and indication of conformance to state and federal laws. Instead of containers, fertilizer and lime may be furnished in bulk with certificate indicating the above information.
1.5.2 Storage
1.5.2.1 Seed, Fertilizer and Lime Storage
Store in cool, dry locations away from contaminants.
1.5.2.2 Topsoil
Prior to stockpiling topsoil, treat growing vegetation with application of appropriate specified non-selective herbicide. Allow sufficient time for herbicide to become inactive before seeding. Clear and grub existing vegetation three to four weeks prior to stockpiling topsoil.
1.5.2.3 Handling
Do not drop or dump materials from vehicles.
1.6 TIME RESTRICTIONS AND PLANTING CONDITIONS
1.6.1 Restrictions
Do not plant when the ground is frozen, snow covered, muddy, or when air temperature exceeds 90 degrees Fahrenheit.
1.7 TIME LIMITATIONS
1.7.1 Seed
Apply seed within twenty four hours after seed bed preparation.
SECTION 32 92 19 Page 3
PART 2 PRODUCTS
2.1 SEED
2.1.1 Classification
Provide State-certified seed of the latest season's crop delivered in original sealed packages, bearing producer's guaranteed analysis for percentages of mixtures, purity, germination, weedseed content, and inert material. Label in conformance with AMS Seed Act and applicable state seed laws. Wet, moldy, or otherwise damaged seed will be rejected. Field mixes will be acceptable when field mix is performed on site in the presence of the Contracting Officer.
2.1.2 Planting Dates
Planting Season Planting Dates
Season 1 September 15 to October 15
Planting season dates may be adapted according to weather conditions with approval of COR.
2.1.3 Seed Purity
Min. Min. Percent Max.
Percent Germination Percent
Pure Seed and Hard Seed Weed Seed
Grass Seed Mix 98 90 0.5
2.1.4 Seed Mixture by Weight
Planting Season Variety Percent (by Weight)
Season 1 Crossfire II 33
Mustang 3 33
Shortstop II 33
Seed Rate: 60 Lbs/Acre
Provide above listed varieties of turf-type, low to medium height, tall fescue or approved equals.
Proportion seed mixtures by weight.
2.2 TOPSOIL
2.2.1 On-Site Topsoil
Surface soil stripped and stockpiled on site and modified as necessary to meet the requirements specified for topsoil in paragraph entitled
"Composition." When available topsoil shall be existing surface soil stripped and stockpiled on-site in accordance with Section 31 00 00
EARTHWORK.
SECTION 32 92 19 Page 4
2.2.2 Off-Site Topsoil
Conform to requirements specified in paragraph entitled "Composition."
Additional topsoil shall be furnished by the Contractor.
2.2.3 Composition
Containing from 5 to 10 percent organic matter as determined by the topsoil composition tests of the Organic Carbon, 6A, Chemical Analysis Method described in DOA SSIR 42. Maximum particle size, 3/4 inch, with maximum 3 percent retained on 1/4 inch screen. The pH shall be tested in accordance with ASTM D 4972. Topsoil shall be free of sticks, stones, roots, and other debris and objectionable materials. Other components shall conform to the following limits:
Silt 25-50 percent
Clay 10-30 percent
Sand 20-35 percent pH 5.5 to 7.0
Soluble Salts 600 ppm maximum
2.3 SOIL CONDITIONERS
Add conditioners to topsoil as required to bring into compliance with
"composition" standard for topsoil as specified herein.
2.3.1 Lime
Commercial grade hydrate limestone containing a calcium carbonate equivalent
(C.C.E.) as specified in ASTM C 602 of not less than 110 percent.
2.3.2 Aluminum Sulfate
Commercial grade.
2.3.3 Sulfur
100 percent elemental
2.3.4 Iron
100 percent elemental
2.3.5 Peat
Natural product of peat moss derived from a freshwater site and conforming to ASTM D 4427. Shred and granulate peat to pass a 1/2 inch mesh screen and condition in storage pile for minimum 6 months after excavation.
2.3.6 Sand
Clean and free of materials harmful to plants.
2.3.7 Perlite
Horticultural grade.
SECTION 32 92 19 Page 5
2.3.8 Composted Derivatives
Ground bark, nitrolized sawdust, humus or other green wood waste material free of stones, sticks, and soil stabilized with nitrogen and having the following properties:
2.3.8.1 Particle Size
Minimum percent by weight passing:
No. 4 mesh screen 95
No. 8 mesh screen 80
2.3.8.2 Nitrogen Content
Minimum percent based on dry weight:
Fir Sawdust 0.7
Fir or Pine Bark 1.0
2.3.9 Gypsum
Coarsely ground gypsum comprised of calcium sulfate dihydrate 61 percent, calcium 22 percent, sulfur 17 percent; minimum 96 percent passing through
20 mesh screen, 100 percent passing thru 16 mesh screen.
2.3.10 Calcined Clay
Calcined clay shall be granular particles produced from montmorillonite clay calcined to a minimum temperature of 1200 degrees F. Gradation: A minimum
90 percent shall pass a No. 8 sieve; a minimum 99 percent shall be retained on a No. 60 sieve; and a maximum 2 percent shall pass a No. 100 sieve. Bulk density: A maximum 40 pounds per cubic foot.
2.4 FERTILIZER
2.4.1 Hydroseeding Fertilizer
Controlled release fertilizer, to use with hydroseeding and composed of pills coated with plastic resin to provide a continuous release of nutrients for at least 6 months and containing the following minimum percentages, by weight, of plant food nutrients.
16 percent available nitrogen
16 percent available phosphorus
16 percent available potassium
2.5 MULCH
Mulch shall be free from noxious weeds, mold, and other deleterious materials.
2.5.1 Wood Cellulose Fiber Mulch
Use recovered materials of either paper-based (100 percent) or wood-based
(100 percent) hydraulic mulch. Processed to contain no growth or germination-inhibiting factors and dyed an appropriate color to facilitate visual metering of materials application. Composition on air-dry weight
SECTION 32 92 19 Page 6 basis: 9 to 15 percent moisture, pH range from 5.5 to 8.2. Use with hydraulic application of grass seed and fertilizer.
2.6 WATER
Source of water shall be approved by Contracting Officer and of suitable quality for irrigation, containing no elements toxic to plant life.
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 EXTENT OF WORK
Provide soil preparation (including soil conditioners as required), fertilizing, seeding, and surface topdressing of all newly graded finished earth surfaces, unless indicated otherwise, and at all areas inside or outside the limits of construction that are disturbed by the Contractor's operations.
3.1.1.1 Topsoil
Provide 4 inches of off-site topsoil or existing soil to meet indicated finish grade. After areas have been brought to indicated finish grade, incorporate fertilizer, pH adjusters and soil conditioners into soil a minimum depth of 4 inches by disking, harrowing, tilling or other method approved by the Contracting Officer. Remove debris and stones larger than
3/4 inch in any dimension remaining on the surface after finish grading.
Correct irregularities in finish surfaces to eliminate depressions. Protect finished topsoil areas from damage by vehicular or pedestrian traffic.
3.1.1.2 Soil Conditioner Application Rates
Apply soil conditioners at rates as determined by laboratory soil analysis of the soils at the job site.
3.1.1.3 Fertilizer Application Rates
Apply fertilizer at rates as determined by laboratory soil analysis of the soils at the job site. For bidding purposes only apply at rates for the following:
Hydroseeding Fertilizer 6 pounds per 1000 square feet.
3.2 SEEDING
3.2.1 Seed Application Seasons and Conditions
Immediately before seeding, restore soil to proper grade. Do not seed when ground is muddy, frozen, snow covered or in an unsatisfactory condition for seeding. If special conditions exist that may warrant a variance in the above seeding dates or conditions, submit a written request to the
Contracting Officer stating the special conditions and proposed variance.
Apply seed within twenty four hours after seedbed preparation. Sow seed by approved sowing equipment. Sow one-half the seed in one direction, and sow remainder at right angles to the first sowing.
SECTION 32 92 19 Page 7
3.2.2 Seed Application Method
Seeding method shall be hydroseeding.
3.2.2.1 Hydroseeding
First, mix water and fiber. Wood cellulose fiber, paper fiber, or recycled paper shall be applied as part of the hydroseeding operation. Fiber shall be added at a minimum of 1,500 pounds, dry weight, per acre. Then add and mix seed and fertilizer to produce a homogeneous slurry. Seed shall be mixed to ensure broadcasting at the rate of 1.5 pounds per 1000 square feet.
When hydraulically sprayed on the ground, material shall form a blotter like cover impregnated uniformly with grass seed. Spread with one application with no second application of mulch.
3.2.3 Erosion Control Material
Install in accordance with manufacturer's instructions, where indicated or as directed by the Contracting Officer.
3.2.4 Watering
Start watering areas seeded as required by temperature and wind conditions.
Apply water at a rate sufficient to insure thorough wetting of soil to a depth of 2 inches without run off. During the germination process, seed is to be kept actively growing and not allowed to dry out. Continue watering until grass has been established.
3.3 PROTECTION OF TURF AREAS
Immediately after turfing, protect area against traffic and other use.
3.4 RESTORATION
Restore to original condition existing turf areas which have been damaged during turf installation operations at the Contractor's expense. Keep clean at all times at least one paved pedestrian access route and one paved vehicular access route to each building. Clean other paving when work in adjacent areas is complete.
-- End of Section --
File details come from the government source that posted it. Updated .