About this file

SECTION 01340 ENVIRONMENTAL REQUIREMENTS

View the file

Other files

File Type Posted
P-153.pdf PDF
014-C-061.pdf PDF
01500.pdf PDF
261200r.pdf PDF
024-C-652.pdf PDF
018-C-204.pdf PDF
L-110.pdf PDF
003-G-021.pdf PDF
031-E-401.pdf PDF
033-E-602.pdf PDF
015-C-201.pdf PDF
P-406.pdf PDF
01420.pdf PDF
P-610.pdf PDF
013-C-055.pdf PDF
027-E-001.pdf PDF
011-C-053.pdf PDF
01310.pdf PDF
01350.pdf PDF
006-G-083.pdf PDF
004-G-081.pdf PDF
007-C-021.pdf PDF
010-C-052.pdf PDF
01320.pdf PDF
005-G-082.pdf PDF
L-109.pdf PDF
32 12 15.pdf PDF
022-C-301.pdf PDF
002-G-002.pdf PDF
021-C-211.pdf PDF
32 92 19.pdf PDF
009-C-051.pdf PDF
01700.pdf PDF
019-C-205.pdf PDF
01782.pdf PDF
01781.pdf PDF
017-C-203.pdf PDF
020-C-206.pdf PDF
025-C-653.pdf PDF
32 05 33.pdf PDF
026-C-671.pdf PDF
001-G-001.pdf PDF
01330.pdf PDF
32 17 24.00 10.pdf PDF
32 12 10.pdf PDF
030-E-203.pdf PDF
01162.pdf PDF
L-108.pdf PDF
SpecCover_TOC.pdf PDF
01600.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01340 - 1 MEAD & HUNT, Inc.

SECTION 01340 – ENVIRONMENTAL REQUIREMENTS

PART 1 - GENERAL

1.1 STORMWATER

A. Provide all permits, plans, training, fees associated with stormwater quality subject to state DEQ and base commander approval.

1.2 CONSTRUCTION PERMIT(S)

A. Provide all plans, training, fees and applications needed to obtain a state of Oregon 1200-C stormwater permit for construction areas > 1 acre in area prior to construction subject to state DEQ and base commander approval. Provide permit termination notice to the DEQ subject to state and base commander approval.

1. Guidance: Guidance for completion of stormwater plans, permit applications and filing fees can be found at these internet web addresses:

a. Permit Guidance:

http://www.deq.state.or.us/wq/wqpermit/Gen1200CGuidance.pdf

b. Permit Fact Sheet:

http://www.deq.state.or.us/wq/wqpermit/SWM-KWM-443.pdf

c. Termination Notice: http://www.deq.state.or.us/wq/wqpermit/1200CtermNotice.pdf

d. Fee Schedule:

http://www.deq.state.or.us/wq/wqpermit/StormWaterFeesTable.htm

1.3 EXISTING BASE STORMWATER PERMIT COMPLIANCE

A. The contractor shall provide all preventative and protective measures needed to control stormwater runoff from the construction site in a manner to insure compliance with the base 1200-COLS permit (copies of this permit are available from the COR above) to the satisfaction of the contracting officer and base environmental officer.

1.4 HAZARDOUS MATERIALS

A. The contractor shall register all hazardous materials brought on base with the base HAZMART by submitting the attached form to the base HAZMART to their satisfaction 5-days prior to the hazardous material arriving on base (HAZMART POC: LeRoy Zent phone 503-335-4299):

01340 - 2 MEAD & HUNT, Inc.

01340 - 3 MEAD & HUNT, Inc.

1.5 Hazardous Materials Storage

A. Store all hazardous materials in accordance with Article 80 of the Oregon Uniform Fire Code.

Insure all hazardous materials stored outdoors are placed in secondary containment in accordance with 40 Code of Federal Regulations 112:

http://www.access.gpo.gov/nara/cfr/waisidx_02/40cfr112_02.html

1.6 Hazardous Waste

A. All hazardous waste generated from the use of hazardous materials becomes the property of the government to dispose of. The contractor shall make the base environmental office (142 FW/EM, phone 503-335-4462) aware of all hazardous waste accumulation and disposal requirements through the AF Form 3952 process (see paragraph 2). The contractor will be required to accumulate hazardous waste on site in an approved container and location and request disposal from the environmental office with 2-weeks notice.

1.7 Building Demolition Waste

A. In the event that the contractor could not offer hazardous building components to be re-used upon removal, the contractor shall collect, containerize and dispose of these components in a manner approved by the base commander or base environmental officer. The contractor shall submit their collection, containerization, and disposal plan to the base commander or base environmental officer through the contracting officer for approval. Hazardous building components considered shall include (as a minimum):

1. Refrigerant reclaimed from air conditioning equipment (required to be removed by a licensed operator of EPA registered recovery equipment)

2. Florescent light tubes

3. Lighting ballasts (except those with factory markings “NON-PCB”)

4. Transformers

5. Mercury Switches (including thermostats)

6. Lead based paint

7. Asbestos

8. Oil Water separators and contained sludge/liquids

9. Storage tanks (underground or above ground)

1.8 Wash Water

A. Washing on base property of any equipment or vehicles is strictly prohibited. This prohibition applies to all concrete trucks and attachments. The contractor may submit a zero-discharge concrete truck washing operation for approval, where all concrete and wash water is contained and properly disposed of off base.

01340 - 4 MEAD & HUNT, Inc.

1.9 Groundwater

A. The contractor shall obtain approval for dewatering from the base commander through the contracting officer prior to dewatering. This approval will be granted if the contractor can show if existing contaminated groundwater plumes will not be impacted by contractor proposed dewatering. The contractor shall submit an engineering proposal to the base commander for approval showing hydraulic calculations from a registered profession hydrologist for proposed dewatering influence on existing groundwater contaminant plumes indicated at this web site under “Feasibility Study” : http://www.142fw.ang.af.mil/resources/

B. Disposal of all groundwater removed by the contractor for dewatering shall be by discharge to sanitary sewer under a batch discharge permit issued by the base environmental office. The contractor shall submit a request for a dewatering discharge permit to sanitary sewer to the base environmental office at least 2-weeks prior to the proposed discharge date. Within this two

(2) week period, the contractor will be asked to provide laboratory analytical testing required by the city of Portland based on their case by case determinations.

1.10 Excavating at Contaminated Sites

A. The contractor shall provide appropriate training and air monitoring to excavate at sites with contaminated soils or groundwater. Appropriate training and air monitoring shall be as determined by the contractor to meet OSHA requirements for contaminants and their extents represented in the “Feasibility Study” at this web site: http://www.142fw.ang.af.mil/resources/

B. Before conducting any work, the contractor shall determine if excavation will take place at any of the sites in this “Feasibility Study” and provide the appropriate training and air monitoring for contractor personnel. In the event that excavated materials in areas identified as contaminated cannot be backfilled to the same location, the contractor shall provide disposal at a location approved by the base commander and the contracting officer.

1.11 Spill Notification

A. The contractor shall notify the base command post at 503-335-4911 upon spilling any quantity of hazardous materials/waste. Spill Containment Control and Countermeasures shall be provided by the contractor in accordance with 20 CFR 112.

1.12 Asbestos

A. Prior to disturbing any existing building components, the contractor shall review the existing assessment for asbestos entitled, “Asbestos Management Plan, Portland ANG Base, Portland, Oregon” available through the base civil engineer (POC: Michael Collins, phone 503-335-4466).

This plan will assist the contractor in making a determination if and where asbestos is believed to be present in the building. Based on the results of this contractor review, the contractor shall provide adequate protection to the environment and their workers as defined by Oregon DEQ and OSHA. In the event that the contractor encounters any unforeseen materials believed to contain asbestos, the contractor shall notify the contracting officer immediately.

1.13 Environmental Management System (EMS)

A. The contractor shall obtain the base EMS policy letter from this web site:

http://www.142fw.ang.af.mil/resources/ and require all contractor personnel associated with this

01340 - 5 MEAD & HUNT, Inc.

project to read it. The contractor shall submit a record to the contracting officer stating that all personnel associated with this contract (general and subcontractors) have read the EMS policy.

PART 2 - PRODUCTS (Not Used.)

PART 3 - EXECUTION (Not Used.)

END OF SECTION

File details come from the government source that posted it. Updated .