About this file

SECTION 01700 - EXECUTION REQUIREMENTS

View the file

Other files

File Type Posted
P-153.pdf PDF
014-C-061.pdf PDF
01500.pdf PDF
261200r.pdf PDF
024-C-652.pdf PDF
018-C-204.pdf PDF
L-110.pdf PDF
003-G-021.pdf PDF
031-E-401.pdf PDF
033-E-602.pdf PDF
015-C-201.pdf PDF
P-406.pdf PDF
01420.pdf PDF
P-610.pdf PDF
013-C-055.pdf PDF
027-E-001.pdf PDF
011-C-053.pdf PDF
01310.pdf PDF
01350.pdf PDF
006-G-083.pdf PDF
004-G-081.pdf PDF
007-C-021.pdf PDF
010-C-052.pdf PDF
01320.pdf PDF
005-G-082.pdf PDF
L-109.pdf PDF
32 12 15.pdf PDF
022-C-301.pdf PDF
002-G-002.pdf PDF
01340.pdf PDF
021-C-211.pdf PDF
32 92 19.pdf PDF
009-C-051.pdf PDF
019-C-205.pdf PDF
01782.pdf PDF
01781.pdf PDF
017-C-203.pdf PDF
020-C-206.pdf PDF
025-C-653.pdf PDF
32 05 33.pdf PDF
026-C-671.pdf PDF
001-G-001.pdf PDF
01330.pdf PDF
32 17 24.00 10.pdf PDF
32 12 10.pdf PDF
030-E-203.pdf PDF
01162.pdf PDF
L-108.pdf PDF
SpecCover_TOC.pdf PDF
01600.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01700 - 1 MEAD & HUNT, Inc.

SECTION 01700 - EXECUTION REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout.

2. Field engineering and surveying.

3. General installation of products.

4. Coordination of Government-installed products.

5. Progress cleaning.

6. Starting and adjusting.

7. Protection of installed construction.

8. Correction of the Work.

1.2 QUALITY ASSURANCE

A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed. Before beginning work, investigate and verify the existence and location of and other construction affecting the Work.

1. Before construction, verify the location and points of connection of utility services.

B. Existing Utilities: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction affecting the Work.

C. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

01700 - 2 MEAD & HUNT, Inc.

3.2 PREPARATION

A. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to COR. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify COR promptly.

B. General: Engage a land surveyor to lay out the Work using accepted surveying practices.

C. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by COR.

3.4 FIELD ENGINEERING

A. Identification: COR will identify existing benchmarks and control points.

B. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

1. Do not change or relocate existing benchmarks or control points without prior written approval of COR. Report lost or destroyed permanent benchmarks or control points promptly. Report the need to relocate permanent benchmarks or control points to COR before proceeding.

2. Replace lost or destroyed permanent benchmarks and control points promptly. Base replacements on the original survey control points.

3.5 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results.

Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that

01700 - 3 MEAD & HUNT, Inc.

adequate provisions are made for locating and installing products to comply with indicated requirements.

F. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by COR.

G. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

3.6 PROGRESS CLEANING

A. General: Maintain Project site free of waste materials and debris. Clean Project site and work areas continuously. No debris can be allowed to escape the work area by wind, jet blast, or any other cause. Additionally, no debris can be allowed to remain in locations where it could escape the work area by wind, jet blast, or other cause. Dispose of materials lawfully.

1. Containerize hazardous and unsanitary waste materials separately from other waste.

Mark containers appropriately and dispose of legally, according to regulations.

B. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

3.7 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction.

B. Restore permanent facilities used during construction to their original condition or better.

C. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

END OF SECTION

File details come from the government source that posted it. Updated .