DIVISION 2 ITEM P-610 STRUCTURAL PORTLAND CEMENT CONCRETE
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P-153.pdf | ||
| 014-C-061.pdf | ||
| 01500.pdf | ||
| 261200r.pdf | ||
| 024-C-652.pdf | ||
| 018-C-204.pdf | ||
| L-110.pdf | ||
| 003-G-021.pdf | ||
| 031-E-401.pdf | ||
| 033-E-602.pdf | ||
| 015-C-201.pdf | ||
| P-406.pdf | ||
| 01420.pdf | ||
| 013-C-055.pdf | ||
| 027-E-001.pdf | ||
| 011-C-053.pdf | ||
| 01310.pdf | ||
| 01350.pdf | ||
| 006-G-083.pdf | ||
| 004-G-081.pdf | ||
| 007-C-021.pdf | ||
| 010-C-052.pdf | ||
| 01320.pdf | ||
| 005-G-082.pdf | ||
| L-109.pdf | ||
| 32 12 15.pdf | ||
| 022-C-301.pdf | ||
| 002-G-002.pdf | ||
| 01340.pdf | ||
| 021-C-211.pdf | ||
| 32 92 19.pdf | ||
| 009-C-051.pdf | ||
| 01700.pdf | ||
| 019-C-205.pdf | ||
| 01782.pdf | ||
| 01781.pdf | ||
| 017-C-203.pdf | ||
| 020-C-206.pdf | ||
| 025-C-653.pdf | ||
| 32 05 33.pdf | ||
| 026-C-671.pdf | ||
| 001-G-001.pdf | ||
| 01330.pdf | ||
| 32 17 24.00 10.pdf | ||
| 32 12 10.pdf | ||
| 030-E-203.pdf | ||
| 01162.pdf | ||
| L-108.pdf | ||
| SpecCover_TOC.pdf | ||
| 01600.pdf |
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STRUCTURAL PORTLAND CEMENT CONCRETE P-610-1
DIVISION 2
ITEM P-610 STRUCTURAL PORTLAND CEMENT CONCRETE
DESCRIPTION
610-1.1 This item shall consist of reinforced structural portland cement concrete, prepared and constructed in accordance with these specifications, at the locations and of the form and dimensions shown on the plans.
MATERIALS
610-2.1 GENERAL. Only approved materials, conforming to the requirements of these specifications, shall be used in the work. They may be subjected to inspection and tests at any time during the progress of their preparation or use. The source of supply of each of the materials shall be approved by the COR before delivery or use is started. Representative preliminary samples of the materials shall be submitted by the Contractor, when required, for examination and test. Materials shall be scored and handled to insure the preservation of their quality and fitness for use and shall be located to facilitate prompt inspection. All equipment for handling and transporting materials and concrete must be clean before any material or concrete is placed therein.
In no case shall the use of pit-run or naturally mixed aggregates be permitted. Naturally mixed aggregate shall be screened and washed, and all fine and coarse aggregates shall be stored separately and kept clean. The mixing of different kinds of aggregates from different sources in one storage pile or alternating batches of different aggregates will not be permitted.
Aggregates shall be tested for deleterious reactivity with alkalies in the cement that may cause excessive expansion of the concrete. Acceptance of aggregates shall be based upon satisfactory evidence furnished by the Contractor that the aggregates, combined with other mixture constituents, do not produce excessive expansion in the concrete. This evidence shall include service records of concrete of comparable properties under similar conditions or exposure and certified records of tests by a testing laboratory that meets the requirements of ASTM C 1077. Tests shall be made in accordance with ASTM
C 1260. Test specimens shall be produced using all components (e.g. coarse aggregate, fine aggregate, cement and fly ash…) to be included in the produced concrete. If the mean expansion of the test specimens, tested in accordance with ASTM C 1260, does not exceed 0.10 % at 16 days from casting the aggregates shall be accepted. If the mean expansion at 16 days is greater than 0.10% but less than
0.15%, the aggregate may be accepted based upon satisfactory service records and acceptance of the aggregate by a State Highway Department specifically addressing Alkali-Silica Reactivity. If the expansion is greater than 0.15%, the aggregate shall not be accepted for use.
610-2.2 COARSE AGGREGATE. The coarse aggregate for concrete shall meet the requirements of
ASTM C 33. Crushed stone aggregate shall have a durability factor, as determined by ASTM C 666, greater than or equal to 95. The COR may consider and reserve final approval of other State classification procedures addressing aggregate durability.
STRUCTURAL PORTLAND CEMENT CONCRETE P-610-2
Coarse aggregate shall be well graded from coarse to fine and shall meet one of the gradations shown in
Table 1, using ASTM C 136.
610-2.3 FINE AGGREGATE. The fine aggregate for concrete shall meet the requirements of ASTM C
33.
The fine aggregate shall be well graded from fine to coarse and shall meet the requirements of Table 2 when tested in accordance with ASTM C 136:
TABLE 1. GRADATION FOR COARSE AGGREGATE
Percentage by Weight Passing Sieves Sieve Designation (square openings) 2” 1-1/2” 1” 3/4'' 1/2'' 3/8'' No.4
No. 4 to 3/4 in.
90-
20-
0-10
No. 4 to 1 in. 100 90-
25-
0-10
TABLE 2. GRADATION FOR FINE AGGREGATE
Sieve Designation
(square openings)
Percentage by Weight
Passing Sieves
3/8 inch
No. 4
No. 16
No. 30
No. 50
No. 100
95-100
45-80
25-55
10-30
2-10
Blending will be permitted, if necessary, in order to meet the gradation requirements for fine aggregate.
Fine aggregate deficient in the percentage of material passing the No. 50 mesh sieve may be accepted, provided that such deficiency does not exceed 5% and is remedied by the addition of pozzolanic or cementitious materials other than portland cement, as specified in 610-2.6 on admixtures, in sufficient quantity to produce the required workability as approved by the COR.
610-2.4 CEMENT. Cement shall conform to the requirements of ASTM C 150 - Type I.
The Contractor shall furnish vendors' certified test reports for each carload, or equivalent, of cement shipped to the project. The report shall be delivered to the COR before permission to use the cement is granted. All such test reports shall be subject to verification by testing sample materials received for use on the project.
STRUCTURAL PORTLAND CEMENT CONCRETE P-610-3
610-2.5 WATER. The water used in concrete shall be free from sewage, oil, acid, strong alkalies, vegetable matter, and clay and loam. If the water is of questionable quality, it shall be tested in accordance with AASHTO T 26.
610-2.6 ADMIXTURES. The use of any material added to the concrete mix shall be approved by the
COR. Before approval of any material, the Contractor shall be required to submit the results of complete physical and chemical analyses made by an acceptable testing laboratory. Subsequent tests shall be made of samples taken by the COR from the supply of the material being furnished or proposed for use on the work to determine whether the admixture is uniform in quality with that approved.
Pozzolanic admixtures shall be fly ash or raw or calcined natural pozzolons meeting the requirements of
ASTM C 618.
Air-entraining admixtures shall meet the requirements of ASTM C 260. Air-entraining admixtures shall be added at the mixer in the amount necessary to produce the specified air content.
Water-reducing, set-controlling admixtures shall meet the requirements of ASTM C 494, Type A, water-reducing or Type D, water-reducing and retarding. Water-reducing admixtures shall be added at the mixer separately from air-entraining admixtures in accordance with the manufacturer's printed instructions.
610-2.7 STEEL REINFORCEMENT. Reinforcing shall consist of steel bars or welded steel fabric conforming to the requirements of ASTM A 184, ASTM A 704, or ASTM A 185 as appropriate.
610-2.8 COVER MATERIALS FOR CURING. Curing materials shall conform to one of the following specifications:
Waterproof paper for curing concrete ASTM C 171
Polyethylene Sheeting for Curing Concrete ASTM C 171
Liquid Membrane-Forming Compounds for Curing Concrete ASTM C 309, Type 2
CONSTRUCTION METHODS
610-3.1 GENERAL. The Contractor shall furnish all labor, materials, and services necessary for, and incidental to, the completion of all work as shown on the drawings and specified herein. All machinery and equipment owned or controlled by the Contractor, which he proposes to use on the work, shall be of sufficient size to meet the requirements of the work, and shall be such as to produce satisfactory work; all work shall be subject to the inspection and approval of the COR. Contractor shall dispose of wash water in accordance with Section 01340 Environmental Requirements, Subsection 1.8 Wash Water
610-3.2 CONCRETE COMPOSITION. The concrete shall develop a compressive strength of 3,500 psi in
28 days as determined by test cylinders made in accordance with ASTM C 31 and tested in accordance with ASTM C 39. The concrete shall contain not less than 550 pounds of cement per cubic yard. The concrete shall contain 5 percent of entrained air, plus or minus 1 percent, as determined by ASTM C 231 and shall have a slump of not more than 4 inches as determined by ASTM C 143.
STRUCTURAL PORTLAND CEMENT CONCRETE P-610-4
610-3.3 ACCEPTANCE SAMPLING AND TESTING. Concrete for each structure will be accepted on the basis of the compressive strength specified in paragraph 3.2. The concrete shall be sampled in accordance with ASTM C 172. Compressive strength specimens shall be made in accordance with
ASTM C 31 and tested in accordance with ASTM C 39.
Concrete cylindrical test specimens shall be made in accordance with ASTM C 31 and tested in accordance with ASTM C 39. The Contractor shall cure and store the test specimens under such conditions as directed. The COR will make the actual tests on the specimens at no expense to the
Contractor.
610-3.4 PROPORTIONING AND MEASURING DEVICES. When package cement is used, the quantity for each batch shall be equal to one or more whole sacks of cement. The aggregates shall be measured separately by weight. If aggregates are delivered to the mixer in batch trucks, the exact amount for each mixer charge shall be contained in each batch compartment. Weighing boxes or hoppers shall be approved by the COR and shall provide means of regulating the flow of aggregates into the batch box so that the required and exact weight of aggregates can be readily obtained.
610-3.5 CONSISTENCY. The consistency of the concrete shall be checked by the slump test specified in
ASTM C 143.
610-3.6 MIXING. Concrete may be mixed at the construction site, at a central point, or wholly or in part in truck mixers. The concrete shall be mixed and delivered in accordance with the requirements of ASTM C
94.
610-3.7 MIXING CONDITIONS. The concrete shall be mixed only in quantities required for immediate use. Concrete shall not be mixed while the air temperature is below 40°F without permission of the
COR. If permission is granted for mixing under such conditions, aggregates or water, or both, shall be heated and the concrete shall be placed at a temperature not less than 50°F nor more than 100°F. The
Contractor shall be held responsible for any defective work, resulting from freezing or injury in any manner during placing and curing, and shall replace such work at his/her expense.
Retempering of concrete by adding water or any other material shall not be permitted.
The delivery of concrete to the job shall be in such a manner that batches of concrete will be deposited at uninterrupted intervals.
610-3.8 FORMS. Concrete shall not be placed until all the forms and reinforcements have been inspected and approved by the COR. Forms shall be of suitable material and shall be of the type, size, shape, quality, and strength to build the structure as designed on the plans. The forms shall be true to line and grade and shall be mortar-tight and sufficiently rigid to prevent displacement and sagging between supports. The Contractor shall bear responsibility for their adequacy. The surfaces of forms shall be smooth and free from irregularities, dents, sags, and holes.
The internal ties shall be arranged so that, when the forms are removed, no metal will show in the concrete surface or discolor the surface when exposed to weathering. All forms shall be wetted with
STRUCTURAL PORTLAND CEMENT CONCRETE P-610-5
water or with a non-staining mineral oil, which shall be applied shortly before the concrete is placed.
Forms shall be constructed so that they can be removed without injuring the concrete or concrete surface. The forms shall not be removed before the expiration of at least 30 hours from vertical faces, walls, slender columns, and similar structures; forms supported by falsework under slabs, beams, girders, arches, and similar construction shall not be removed until tests indicate that at least 60% of the design strength of the concrete has developed.
610-3.9 PLACING REINFORCEMENT. All reinforcement shall be accurately placed, as shown on the plans, and shall be firmly held in position during concreting. Bars shall be fastened together at intersections. The reinforcement shall be supported by approved metal chairs. Shop drawings, lists, and bending details shall be supplied by the Contractor when required.
610-3.10 EMBEDDED ITEMS. Before placing concrete, any items that are to be embedded shall be firmly and securely fastened in place as indicated. All such items shall be clean and free from coating, rust, scale, oil, or any foreign matter. The embedding of wood shall be avoided. The concrete shall be spaded and consolidated around and against embedded items.
610-3.11 PLACING CONCRETE. All concrete shall be placed during daylight, unless otherwise approved. The concrete shall not be placed until the depth and character of foundation, the adequacy of forms and falsework, and the placing of the steel reinforcing have been approved. Concrete shall be placed as soon as practical after mixing and in no case later than 1 hour after water has been added to the mix. The method and manner of placing shall be such to avoid segregation and displacement of the reinforcement. Troughs, pipes, and chutes shall be used as an aid in placing concrete when necessary.
Dropping the concrete a distance of more than 5 feet, or depositing a large quantity at one point, will not be permitted. Concrete shall be placed upon clean, damp surfaces, free from running water, or upon properly consolidated soil.
The concrete shall be compacted with suitable mechanical vibrators operating within the concrete. When necessary, vibrating shall be supplemented by hand spading with suitable tools to assure proper and adequate compaction. Vibrators shall be manipulated so as to work the concrete thoroughly around the reinforcement and embedded fixtures and into corners and angles of the forms. The vibration at any joint shall be of sufficient duration to accomplish compaction but shall not be prolonged to the point where segregation occurs. Concrete deposited under water shall be carefully placed in a compact mass in its final position by means of a tremie, a closed bottom dump bucket, or other approved method and shall not be disturbed after being deposited.
610-3.12 CONSTRUCTION JOINTS. When the placing of concrete is suspended, necessary provisions shall be made for joining future work before the placed concrete takes its initial set. For the proper bonding of old and new concrete, such provisions shall be made for grooves, steps, keys, dovetails, reinforcing bars or other devices as may be prescribed. The work shall be arranged so that a section begun on any day shall be finished during daylight of the same day. Before depositing new concrete on or against concrete that has hardened, the surface of the hardened concrete shall be cleaned by a heavy steel broom, roughened slightly, wetted, and covered with a neat coating of cement paste or grout.
STRUCTURAL PORTLAND CEMENT CONCRETE P-610-6
610-3.13 EXPANSION JOINTS. Expansion joints shall be constructed at such points and of such dimensions as may be indicated on the drawings. The premolded filler shall be cut to the same shape as that of the surfaces being joined. The filler shall be fixed firmly against the surface of the concrete already in place in such manner that it will not be displaced when concrete is deposited against it.
610-3.14 DEFECTIVE WORK. Any defective work discovered after the forms have been removed shall be immediately removed and replaced. If any dimensions are deficient, or if the surface of the concrete is bulged, uneven, or shows honeycomb, which in the opinion of the COR cannot be repaired satisfactorily, the entire section shall be removed and replaced at the expense of the Contractor.
610-3.15 SURFACE FINISH. All exposed concrete surfaces shall be true, smooth, and free from open or rough spaces, depressions, or projections. The concrete in horizontal plane surfaces shall be brought flush with the finished top surface at the proper elevation and shall be struck-off with a straightedge and floated. Mortar finishing shall not be permitted, nor shall dry cement or sand-cement mortar be spread over the concrete during the finishing of horizontal plane surfaces.
When directed, the surface finish of exposed concrete shall be a rubbed finish. If forms can be removed while the concrete is still green, the surface shall be pointed and wetted and then rubbed with a wooden float until all irregularities are removed. If the concrete has hardened before being rubbed, a carborundum stone shall be used to finish the surface. When approved, the finishing can be done with a rubbing machine.
610-3.16 CURING AND PROTECTION. All concrete shall be properly cured and protected by the
Contractor. The work shall be protected from the elements, flowing water, and from defacement of any nature during the building operations. The concrete shall be cured as soon as it has sufficiently hardened by covering with an approved material. Water-absorptive coverings shall be thoroughly saturated when placed and kept saturated for a period of at least 3 days. All curing mats or blankets shall be sufficiently weighted or tied down to keep the concrete surface covered and to prevent the surface from being exposed to currents of air. Where wooden forms are used, they shall be kept wet at all times until removed to prevent the opening of joints and drying out of the concrete. Traffic shall not be allowed on concrete surfaces for 7 days after the concrete has been placed.
610-3.17 DRAINS OR DUCTS. Drainage pipes, conduits, and ducts that are to be encased in concrete shall be installed by the Contractor before the concrete is placed. The pipe shall be held rigidly so that it will not be displaced or moved during the placing of the concrete.
610-3.18 COLD WEATHER PROTECTION. When concrete is placed at temperatures below 40°F , the
Contractor shall provide satisfactory methods and means to protect the mix from injury by freezing. The aggregates, or water, or both, shall be heated in order to place the concrete at temperatures between
50°F and 100°F.
Calcium chloride may be incorporated in the mixing water when directed by the COR. Not more than 2 pounds of Type 1 nor more than 1.6 pounds of Type 2 shall be added per bag of cement. After the concrete has been placed, the Contractor shall provide sufficient protection such as cover, canvas, STRUCTURAL PORTLAND CEMENT CONCRETE P-610-7 framework, heating apparatus, etc., to enclose and protect the structure and maintain the temperature of the mix at not less than 50°F until at least 60% of the designed strength has been attained.
610-3.19 FILLING JOINTS. All joints that require filling shall be thoroughly cleaned, and any excess mortar or concrete shall be cut out with proper tools. Joint filling shall not be started until after final curing and shall be done only when the concrete is completely dry. The cleaning and filling shall be carefully done with proper equipment and in a manner to obtain a neat looking joint free from excess filler.
TESTING REQUIREMENTS
ASTM C 31 Making and Curing Test Specimens in the Field
ASTM C 39 Compressive Strength of Cylindrical Concrete Specimens
ASTM C 136 Sieve Analysis of Fine and Coarse Aggregates
ASTM C 138 Density (Unit Weight), Yield, and Air Content (Gravimetric) of Concrete
ASTM C 143 Slump of Hydraulic Cement Concrete
ASTM C 231 Air Content of Freshly Mixed Concrete by the Pressure Method
MATERIAL REQUIREMENTS
ASTM A 184 Specification for Fabricated Deformed Steel Bar or Rod Mats for Concrete
Reinforcement
ASTM A 185 Steel Welded Wire Fabric, Plain, for Concrete Reinforcement
ASTM A 497 Steel Welded Wire Fabric, Deformed, for Concrete Reinforcement
ASTM A 615 Deformed and Plain Billet-Steel Bars for Concrete Reinforcement
ASTM C 33 Concrete Aggregates
ASTM C 94 Ready-Mixed Concrete
ASTM C 150 Portland Cement
ASTM C 171 Sheet Materials for Curing Concrete
ASTM C 172 Sampling Freshly Mixed Concrete
ASTM C 260 Air-Entraining Admixtures for Concrete
ASTM C 309 Liquid Membrane-Forming Compounds for Curing Concrete
STRUCTURAL PORTLAND CEMENT CONCRETE P-610-8
ASTM C 494 Chemical Admixtures for Concrete
ASTM C 595 Blended Hydraulic Cements
ASTM C 618 Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use as a Mineral
Admixture in Concrete
ASTM D 1751 Specification for Preformed Expansion Joint Fillers for Concrete Paving and
Structural Construction (Non-extruding and Resilient Bituminous Types)
ASTM D 1752 Specification for Preformed Sponge Rubber and Cork Expansion Joint Fillers for
Concrete Paving and Structural Construction
AASHTO T 26 Quality of Water to be Used in Concrete
END OF ITEM P-610