SECTION 01162 HAZARDOUS MATERIAL USAGE REQUIREMENTS

View the file

Other files

File Type Posted
P-153.pdf PDF
014-C-061.pdf PDF
01500.pdf PDF
261200r.pdf PDF
024-C-652.pdf PDF
018-C-204.pdf PDF
L-110.pdf PDF
003-G-021.pdf PDF
031-E-401.pdf PDF
033-E-602.pdf PDF
015-C-201.pdf PDF
P-406.pdf PDF
01420.pdf PDF
P-610.pdf PDF
013-C-055.pdf PDF
027-E-001.pdf PDF
011-C-053.pdf PDF
01310.pdf PDF
01350.pdf PDF
006-G-083.pdf PDF
004-G-081.pdf PDF
007-C-021.pdf PDF
010-C-052.pdf PDF
01320.pdf PDF
005-G-082.pdf PDF
L-109.pdf PDF
32 12 15.pdf PDF
022-C-301.pdf PDF
002-G-002.pdf PDF
01340.pdf PDF
021-C-211.pdf PDF
32 92 19.pdf PDF
009-C-051.pdf PDF
01700.pdf PDF
019-C-205.pdf PDF
01782.pdf PDF
01781.pdf PDF
017-C-203.pdf PDF
020-C-206.pdf PDF
025-C-653.pdf PDF
32 05 33.pdf PDF
026-C-671.pdf PDF
001-G-001.pdf PDF
01330.pdf PDF
32 17 24.00 10.pdf PDF
32 12 10.pdf PDF
030-E-203.pdf PDF
L-108.pdf PDF
SpecCover_TOC.pdf PDF
01600.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01162 - 1 MEAD & HUNT, Inc.

SECTION 01162 – HAZARDOUS MATERIAL USAGE REQUIREMENTS

PART 1 - GENERAL

1.1. DESCRIPTION

A. Conditions of the Contract and Division 1 apply to this Section.

1.2 HAZARDOUS MATERIAL USAGE

A. The contractor shall establish a Hazardous Material (HM) storage and distribution system when HM is to be used. All HM required to support the contract shall be reported to the Hazardous Material Pharmacy (HMP) using the Contractor HM Identification Form. The Contractor HM Identification Form will be provided to the Contractor at or prior to the Pre-Construction meeting.

Additional HM needed by the contractor shall be identified to the Contracting Officer’s Representative (COR) for approval by the HMP. Reference Attachment 01162A.

B. The contractor planning to use HM for the work shall register with the base HMP prior to start of work in order to support the installation’s compliance with Executive Order 12856, Federal Compliance with the Right-To-Know Laws and Pollution Prevention Requirements.

C. The contractor shall maintain Contractor HM Identification Form for HM on the job site for inspection/verification.

D. The COR will verify that the HM identified to HMP is the only HM in use on the job site.

E. The contractor shall be responsible for the following items:

a. Provide a list of each material and quantity of material for all proposed Hazardous Material (HM). HM shall be construed to mean any item that is:

1) A health hazard or physical hazard as defined in 29 CFR, 1910.1200(c).

2) Regulated in its disposal by EPA under 40 CFR.

3) Hazardous as defined by DOT regulations under 49 CFR.

4) Hazardous as defined by the Dangerous Goods Regulations of the International Air Transport Association.

F. Provide a material safety data sheet (MSDS) for each item on the HM list.

G. The contractor shall establish a construction specific HM storage and issue location that fully complies with Federal, State and Local environmental regulations. Materials issued shall be tracked for quantities used. Unused materials shall be inventoried and removed from the ANG installation prior to close out of the contract or expiration date of the HM. Reports of materials delivered, used and removed from the installation shall be submitted to the COR monthly and prior to contract close-out.

H. The contractor shall comply with all Federal, State, and Local environmental.

01162 - 2 MEAD & HUNT, Inc.

I. The contractor shall accompany the Bio-environmental Engineering Representative (BEE) and the (COR) on project close-out inspection to ensure all used/unused HM is removed from the installation. This requirement shall not be a punch list item and must be accomplished prior to the Government accepting beneficial occupancy of the facility or construction item. Reference Attachment 01162B.

01162 - 3 MEAD & HUNT, Inc.

ATTACHMENT 01162A

Contractor Hazardous Material Identification Form

Part I Date

This part is to be completed by Contractor prior to the construction start date, and shall be maintained on the job site.

Contractor Company: (name) Proposed work term: (date) to (date) Contractor Point of Contact: (full name or names, phone/pager numbers, emergency 24 hour contact number etc.)

HM to be used:

MFG./Product

M.S.D.S.

Attached

Quantity Used

Disposal Procedures

Use/Unused material removed from ANG installation

Note: This form is good for a one-month period and is to be submitted to the Hazardous Material Pharmacy. All Hazardous Material used thereafter will be identified to the Contracting Officer’s Representative for approval by the Hazardous Material Pharmacy. See Part II for Contractor close-out procedures. The Hazardous Material Pharmacy phone number is

(xxx) xxx-xxxx.

Approval Signatures:

COR (Contracting Officer Representative)

BEER (Bio-Environmental Engineering Representative)

EM (Environmental Manager)

SO (Safety Officer)

01162 - 4 MEAD & HUNT, Inc.

ATTACHMENT 01162B

Contractor Hazardous Material Identification Form Close-Out Procedures

Part II Date

Attach this form to Part I

The Contractor shall accompany the Contracting Officer Representative and Environmental Manager on the close-out inspection to ensure all used/unused HM was removed from the installation.

Closeout Approval Signatures:

COR (Contracting Officer Representative)

BEER (Bio-Environmental Engineering Representative)

EM (Environmental Manager)

Contractor

END OF SECTION