01500.pdf
PDF 22 KB Posted
- Attached to
- Repair Military Taxiway located at the Portland Air National Guard Base, Portland, Oregon
- Solicitation number
- W912JV-09-R-0008
About this file
SECTION 01500 - TEMPORARY FACILITIES AND CONTROLS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P-153.pdf | ||
| 014-C-061.pdf | ||
| 261200r.pdf | ||
| 024-C-652.pdf | ||
| 018-C-204.pdf | ||
| L-110.pdf | ||
| 003-G-021.pdf | ||
| 031-E-401.pdf | ||
| 033-E-602.pdf | ||
| 015-C-201.pdf | ||
| P-406.pdf | ||
| 01420.pdf | ||
| P-610.pdf | ||
| 013-C-055.pdf | ||
| 027-E-001.pdf | ||
| 011-C-053.pdf | ||
| 01310.pdf | ||
| 01350.pdf | ||
| 006-G-083.pdf | ||
| 004-G-081.pdf | ||
| 007-C-021.pdf | ||
| 010-C-052.pdf | ||
| 01320.pdf | ||
| 005-G-082.pdf | ||
| L-109.pdf | ||
| 32 12 15.pdf | ||
| 022-C-301.pdf | ||
| 002-G-002.pdf | ||
| 01340.pdf | ||
| 021-C-211.pdf | ||
| 32 92 19.pdf | ||
| 009-C-051.pdf | ||
| 01700.pdf | ||
| 019-C-205.pdf | ||
| 01782.pdf | ||
| 01781.pdf | ||
| 017-C-203.pdf | ||
| 020-C-206.pdf | ||
| 025-C-653.pdf | ||
| 32 05 33.pdf | ||
| 026-C-671.pdf | ||
| 001-G-001.pdf | ||
| 01330.pdf | ||
| 32 17 24.00 10.pdf | ||
| 32 12 10.pdf | ||
| 030-E-203.pdf | ||
| 01162.pdf | ||
| L-108.pdf | ||
| SpecCover_TOC.pdf | ||
| 01600.pdf |
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01500 - 1 MEAD & HUNT, Inc.
SECTION 01500 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
1.2 USE CHARGES
A. General: Cost or use charges for temporary facilities shall be included in the Contract Sum.
B. Sewer Service: Pay sewer service use charges for sewer usage by all entities for construction operations.
C. Water Service: Pay water service use charges for water used by all entities for construction operations.
D. Electric Power Service: Pay electric power service use charges for electricity used by all entities for construction operations.
1.3 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.
PART 2 - PRODUCTS
2.1 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures, and as required by Base Fire Chief.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.
01500 - 2 MEAD & HUNT, Inc.
B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company, COR, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.
B. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
C. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.
1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.
3.3 SUPPORT FACILITIES INSTALLATION
A. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations, including, but not limited to any indicated on Drawings.
1. Provide dust-control treatment that is nonpolluting and nontracking. Reapply treatment as required to minimize dust.
B. Parking: Use designated areas of Government's existing parking areas for construction personnel.
C. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction.
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
1. Comply with work restrictions specified in Division 1 Section "Summary."
B. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to adjacent properties and walkways, according to requirements of authorities having jurisdiction.
1. Inspect, repair, and maintain erosion- and sedimentation-control measures during construction until permanent vegetation has been established.
01500 - 3 MEAD & HUNT, Inc.
C. Stormwater Control: Comply with authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.
D. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are property of Contractor.
2. Remove temporary paving not intended for or acceptable for integration into permanent paving.
END OF SECTION