MFR Liquidated Damages YAQF192039 Repair Airfield Lighting rev 1.pdf

PDF 201 KB Posted

Attached to
Repair Airfield Lighting System Volk Field CRTC
Solicitation number
W912J226RA011
Issued by

About this file

This is a Memorandum for Record (MFR) documenting the Contracting Officer's justification and rate calculation for liquidated damages in a federal construction contract.

The MFR covers Project YAQF 192039, a repair of the Airfield Lighting System at CRTC Volk Field. The Contracting Officer determined that timely completion is critical to mission readiness, as delays would cause airfield downtime disrupting operational capabilities and incurring additional labor costs. The Government will include FAR 52.211-12 (Liquidated Damages – Construction) in the solicitation and resulting contract. The calculated daily liquidated damages rate is $2,129.11 per calendar day plus a one-time legal services fee of $153.00. This rate was established through a detailed cost analysis including: Contracting Officer time (3 hours daily at $100.29/hour = $300.87); Contract Specialist time (1 hour daily at $92.73/hour = $92.73); Contracting Officer Representative time (2 hours daily at $141.47/hour = $282.94); Architect/Engineer contracted services (1 hour daily at $152.57/hour = $152.57); and a daily airfield downtime flat rate of $1,300.00. All hourly rates represent fully burdened civilian salaries including locality and fringe benefits based on the current OPM General Schedule. The Contracting Officer determined this rate represents a fair, reasonable, and conservative forecast of damages the Government will suffer from contractor delay.

View the file

Other files

File Type Posted
Question Document 6.0 W912J2-26-R-A011 Repair Airlfield Lighting System 06 Aug 26.docx DOCX document
Question Document 5.0 W912J2-26-R-A011 Repair Airlfield Lighting System 04 Aug 26.docx DOCX document
Revised CG113 - 073126.pdf PDF
Question Document 4.0 W912J2-26-R-A011 Repair Airlfield Lighting System 31Jul26.docx DOCX document
Solicitation Amendment W50S9H26RA0110001 SF 30.pdf PDF
Question Document 3.0 W912J2-26-R-A011 Repair Airlfield Lighting System 24Jul26.docx DOCX document
Solicitation Amendment - W50S9H26RA0110001.pdf PDF
Question Document 2.0 W912J2-26-R-A011 Repair Airlfield Lighting System 24Jul26.docx DOCX document
APPENDIX G - EXHIBITS 22JUL2026.pdf PDF
Site Visit PreProposal Conference Sign In Sheet 15 July 2026.pdf PDF
RFP Pre-proposal slides W912J2-26-R-A011 final.pptx PPTX presentation
ATTACHMENT B - Design Drawings YAQF192039 Volk Field CRTC_Repair Airfield Lighting REVISED Submittal Plans 06-30-26.pdf PDF
Question Document 1.0 W912J2-26-R-A011 Repair Airlfield Lighting System 14Jul26.docx DOCX document
APPENDIX G - EXHIBITS.pdf PDF
SFS Form1 - Blank.pdf PDF
ATTACHMENT F - YAQF192039 REPAIR AIRFIELD LIGHTING SYSTEM - Single Source Doc - Cummins Power Generation.pdf PDF
ATTACHMENT E - YAQF192039 REPAIR AIRFIELD LIGHTING SYSTEM - Single Source Doc - Monaco Fire Alarm.pdf PDF
ATTACHMENT G - YAQF192039 REPAIR AIRFIELD LIGHTING SYSTEM - Single Source Doc - Best Access Systems Locks and Cores.pdf PDF
ATTACHMENT B - Design Drawings - YAQF192039 Volk Field CRTC_Repair Airfield Lighting Final Plans 03-06-26.pdf PDF
Solicitation - W50S9H26RA011 Standard Form 1442 8Jul26.pdf PDF
ATTACHMENT C - Hazardous Materials Assessment - 2601801_VolkField-ElectricalVaultBuilding-HMA Report-FINAL_2026_05_04.pdf PDF
APPENDIX G - EXHIBITS.pdf PDF
ATTACHMENT A - General Requirement and Technical Specifications - YAQF192039 Volk Field Repair Airfield Lighting Revised 30Jun26.pdf PDF
ATTACHMENT D - Wage Determination - WD WI20260011 05182026.txt TXT text file
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEMORANDUM FOR RECORD (MFR)

SUBJECT: Justification and Rate Calculation for the Use of Liquidated Damages

PROJECT: YAQF 192039 Repair Airfield Lighting System SRM

PROJECT: YAQF 192039 Repair Airfield Lighting System SRM

REFERENCE: FAR 11.501 (Policy), FAR 11.502 (Procedures), and FAR 36.206 (Liquidated Damages in Construction)

1. PURPOSE:

The purpose of this memorandum is to document the Contracting Officer’s justification for including the Liquidated Damages clause (FAR 52.211-12) in the subject solicitation, and to establish the daily liquidated damages rate as a reasonable forecast of the actual harm the Government will incur due to contractor delay.

2. JUSTIFICATION FOR USE (FAR 11.501):

Timely completion of the subject project is critical to the mission readiness of the installation. A delay in the completion of this repair will cause airfield downtime disrupting CRTC Volk Field mission capabilities as well as additional labor costs for personnel.

While the Government will undoubtedly suffer financial and operational harm from a delay, the exact extent or amount of these damages is difficult or impossible to estimate with absolute precision at the time of contract formation. Therefore, assessing liquidated damages is both appropriate and necessary to protect the Government's interests.

3. RATE CALCULATION WORKSHEET (FAR 11.502):

The daily rate calculated below is not a penalty. It is a reasonable estimate of the daily costs the Government will incur for extended inspection, project superintendence, and contract administration if the contractor fails to complete the work by the established schedule. There is also a one-time charge of $153.00 for legal services that will Apply.

Note: The hourly rates below represent fully burdened civilian salaries (including locality and fringe benefits) based on the current OPM General Schedule.

Cost Category / Personnel Estimated Daily Effort (Hours)

Fully Burdened Hourly Rate

Total Daily Damages

A. Contracting Officer / NH-4 3 $100.29 $300.87

B. Contract Specialist / E7 1 $92.73 $92.73

C. Contracting Officer Representative / O4

2 $141.47 $282.94

D. Architect/Engineer Services / Contracted

1 $152.57 $152.57

E. Airfield Downtime N/A (Daily Flat Rate) N/A $1,300.00

TOTAL ESTIMATED DAILY COST:

$2,129.11

4. DETERMINATION:

Based on the calculation worksheet above, the Government has determined that the calculated rate of $2129.11 per calendar day plus a one-time fee of $153.00 for legal services is a fair, reasonable, and conservative forecast of the damages the Government will suffer.

PROJECT: YAQF 192039 Repair Airfield Lighting System SRM

Therefore, the Contracting Officer will insert FAR 52.211-12, Liquidated Damages – Construction, into the solicitation and resulting contract, stipulating a rate of $2,129.11 for each calendar day of delay plus one-time legal services fee of $153.00.

Zachary R. Tevis Contracting Officer

2026-06-29T10:08:12-0500
TEVIS.ZACHARY.RYAN.1239025885