ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
W912HV-15-B-0001 12/5/2014 3/10/2015 1 2
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
U.S. Army Engineer District, Japan I CERTIFY that I have opened, read, and Norman G. Mackie APO AP 96338-5010 recorded on this abstract all offers Assistant Bid Opening Officer received in response to this solicitation. SIGNATURE DATE SIGNED
9. OFFERS
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE NO. 1 NO. 2
FY14 SOCOM PN 78024, Special Operations Force (SOF) (Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR
Facility Augmentation, Torii Station, Okinawa, Japan A. HIRED LABOR Prime Projects Intn'l Nishimatsu Construction
B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)
(Without Profit) ILC (¥255,000,000) Bid Bond (¥255,000,000)
6. NUMBER OF AMENDMENTS ISSUED x C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
Six (6) (Including Profit) Yes Yes
7A. ITEM
NUMBER 7B. DESCRIPTION OF OFFERED ITEM
7C. EST.
QUANTITY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT
BASE BID ITEMS
0001 Special Operations Forces Augmentation (Utility Building, Perimeter Road Extension, Fuel Tank, Water storage tanks, Parking Lot Area B & C, Trash Enclosure and all Associated Utility Work and Site Improvements) - Construction 1 JOB ¥944,228,000 ¥1,074,278,868 ¥742,024,000
Company Operations Facility (COF) - Construction 1 JOB ¥1,906,800,000 ¥4,262,256,298 ¥2,039,799,000
Maritime Operations Facility (MOF) - Construction 1 JOB ¥815,470,000 ¥1,107,939,841 ¥681,075,000
0004 Concrete Hardstand - Construction 1 JOB ¥128,062,000 ¥466,035,747 ¥249,331,000
Site Utilities, 1.5 meters outside bldgs - Construction 1 JOB ¥795,631,000 ¥1,074,275,498 ¥641,471,000
TOTAL BASE SCHEDULE ¥4,590,191,000 ¥7,984,786,252 ¥4,353,700,000
OPTION BID ITEMS
Combat Readiness Training Facility (CRTF) - Construction 1 JOB ¥887,401,000 ¥1,366,522,253 ¥854,528,000
0007 Overhead Protection Canopy - Construction 1 JOB ¥95,385,000 ¥182,968,874 ¥107,730,000
Parachute Landing Fall Platform - Construction 1 JOB ¥28,035,000 ¥44,204,160 ¥11,563,000
0009 Concrete West Guardhouse - Construction 1 JOB ¥6,841,000 ¥24,043,760 ¥8,056,000
Climate Controlled Storage Facility (CCSF) - Construction 1 JOB ¥265,431,000 ¥420,049,557 ¥252,829,000
Branch Road Extension, Parking Lot Area A and C (Northeast) - Construction 1 JOB ¥149,382,000 ¥318,491,810 ¥91,276,000
Access Road, Access Control Gate to Perimeter Road, and East Guardhouse - Construction 1 JOB ¥71,643,000 ¥89,953,940 ¥14,044,000
Procure and Install a complete and usable Security Equipment (IDS, ESS (Access Control and CCTV), Including wiring. 1 JOB ¥53,304,000 ¥371,797,530 ¥315,406,000
Procure and Install a complete and usable Audio Visual Equipment and system for Company Operations Facility (COF). 1 JOB ¥10,429,000 ¥36,605,010 ¥35,924,000
Procure and Install a complete and usable Audio Visual Equipment and system for Combat Readiness Training Facility (CRTF). 1 JOB ¥3,178,000 ¥21,449,740 ¥12,082,000
Procure and Install a complete and usable Fixtures, Furnishings & Equipment - FF&E for Company Operations Facility (COF) 1 JOB ¥333,337,000 ¥255,038,994 ¥160,441,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for Martitime Operations Facility (MOF) 1 JOB ¥59,225,000 ¥56,338,374 ¥71,901,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for Combat Readiness Training Facility (CRTF) 1 JOB ¥143,958,000 ¥170,823,016 ¥118,058,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for Climate Controlled Storage Facility (CCSF) 1 JOB ¥7,786,000 ¥5,055,119 ¥1,906,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for East Guardhouse Building (EGB) 1 JOB ¥462,000 ¥777,168 ¥278,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for West Guardhouse Building (WGB) 1 JOB ¥462,000 ¥777,168 ¥278,000
TOTAL OPTION ITEMS (ITEM NOS. 0006
THROUGH 0021 ¥2,116,259,000 ¥3,364,896,473 ¥2,056,300,000
TOTAL BID ITEMS (ITEM NOS. 0001
THROUGH 0021) ¥6,706,450,000 ¥11,349,682,725 ¥6,410,000,000
ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
W912HV-15-B-0001 12/5/2014 3/10/2015 2 2
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
U.S. Army Engineer District, Japan I CERTIFY that I have opened, read, and Norman G. Mackie APO AP 96338-5010 recorded on this abstract all offers Assistant Bid Opening Officer received in response to this solicitation. SIGNATURE DATE SIGNED
9. OFFERS
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE NO. 3 NO. 4
FY14 SOCOM PN 78024, Special Operations Force (SOF) (Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR
Facility Augmentation, Torii Station, Okinawa, Japan A. HIRED LABOR Tokyu Construction
B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)
(Without Profit) Bid Bond (¥255,000,000)
6. NUMBER OF AMENDMENTS ISSUED x C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
Six (6) (Including Profit) Yes
7A. ITEM
NUMBER 7B. DESCRIPTION OF OFFERED ITEM
7C. EST.
QUANTITY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT
BASE BID ITEMS
0001 Special Operations Forces Augmentation (Utility Building, Perimeter Road Extension, Fuel Tank, Water storage tanks, Parking Lot Area B & C, Trash Enclosure and all Associated Utility Work and Site Improvements) - Construction 1 JOB ¥1,088,110,000
Company Operations Facility (COF) - Construction 1 JOB ¥2,748,000,000
Maritime Operations Facility (MOF) - Construction 1 JOB ¥918,720,000
0004 Concrete Hardstand - Construction 1 JOB ¥221,530,000
Site Utilities, 1.5 meters outside bldgs - Construction 1 JOB ¥600,440,000
TOTAL BASE SCHEDULE ¥5,576,800,000
OPTION BID ITEMS
Combat Readiness Training Facility (CRTF) - Construction 1 JOB ¥907,520,000
0007 Overhead Protection Canopy - Construction 1 JOB ¥147,370,000
Parachute Landing Fall Platform - Construction 1 JOB ¥13,260,000
0009 Concrete West Guardhouse - Construction 1 JOB ¥10,740,000
Climate Controlled Storage Facility (CCSF) - Construction 1 JOB ¥299,510,000
Branch Road Extension, Parking Lot Area A and C (Northeast) - Construction 1 JOB ¥79,100,000
Access Road, Access Control Gate to Perimeter Road, and East Guardhouse - Construction 1 JOB ¥29,300,000
Procure and Install a complete and usable Security Equipment (IDS, ESS (Access Control and CCTV), Including wiring. 1 JOB ¥309,930,000
Procure and Install a complete and usable Audio Visual Equipment and system for Company Operations Facility (COF). 1 JOB ¥33,120,000
Procure and Install a complete and usable Audio Visual Equipment and system for Combat Readiness Training Facility (CRTF). 1 JOB ¥11,420,000
Procure and Install a complete and usable Fixtures, Furnishings & Equipment - FF&E for Company Operations Facility (COF) 1 JOB ¥300,630,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for Martitime Operations Facility (MOF) 1 JOB ¥51,560,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for Combat Readiness Training Facility (CRTF) 1 JOB ¥126,370,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for Climate Controlled Storage Facility (CCSF) 1 JOB ¥2,150,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for East Guardhouse Building (EGB) 1 JOB ¥610,000
Procure and Install a complete and usable Furniture, Fixtures & Equipment - FF&E for West Guardhouse Building (WGB) 1 JOB ¥610,000
TOTAL OPTION ITEMS (ITEM NOS. 0006
THROUGH 0021 ¥2,323,200,000
TOTAL BID ITEMS (ITEM NOS. 0001
THROUGH 0021) ¥0 ¥7,900,000,000 ¥0