Exhibit_1.pdf

PDF 35 KB Posted

Attached to
Kuwait Air Defense Improvements Federal contract opportunity
Solicitation number
W912ER-16-R-0008
Issued by
Department of the Army Corps of Engineers Engineering District Middle East

About this file

Exhibit 1

View the file

Other files for this federal contract opportunity

Other files attached to Kuwait Air Defense Improvements, newest first.
File Type Posted
AM_8_Specifications_ _Attachment.pdf PDF
AM_8_VOLUME_2_DRAWING.pdf PDF
AM_8_VOLUME_3_DRAWING_.pdf PDF
W912ER-16-R-0008-0008.pdf PDF
AM_7_Proposal_Schedule_.pdf PDF
ATTACHMENT_3_Relevancy_Matrix.pdf PDF
W912ER-16-R-0008-0007.pdf PDF
AM_6_Specifications_19_Aug_16.pdf PDF
AM_6_VOLUME_2_DRAWINGS_19_Aug_16.pdf PDF
AM_6_VOLUME_1_DRAWINGS_19_Aug_16.pdf PDF
AM_6_VOLUME_4_DRAWINGS_19_Aug_16.pdf PDF
W912ER-16-R-0008-0006.pdf PDF
AM_6_Cost_Breakdown_19_Aug_16.pdf PDF
AM_6_VOLUME_3_DRAWINGS_19_Aug_16.pdf PDF
W912ER-16-R-0008-0005.pdf PDF
W912ER-16-R-0008-0004.pdf PDF
AM_4_Cost_Breakdown.pdf PDF
AM_4_VOLUME_2_DRAWING.pdf PDF
AM_4_Proposal_Schedule_.pdf PDF
Exhibit_1.pdf PDF
AM_4_Specifications.pdf PDF
AM_4_VOLUME_3_DRAWING.pdf PDF
AM_3_VOLUME_1_DRAWING.pdf PDF
AM_3_VOLUME_2_DRAWING.pdf PDF
Exhibit_1.pdf PDF
AM_3_Specifications_28_Jul_16.pdf PDF
AM_3_VOLUME_4_DRAWING.pdf PDF
W912ER-16-R-0008-0003.pdf PDF
AM_3_VOLUME_3_DRAWING.pdf PDF
W912ER-16-R-0008-0002.pdf PDF
Appendix_D_Attachment.pdf PDF
Attachment_2_Prime_Construction_Experience_Form.pdf PDF
Attachment_1_Experience_Overview_Sheet.pdf PDF
Amendment_W912ER-16-R-0008-0001.pdf PDF
Attachment_3_Relevancy_Matrix.pdf PDF
Volume_1_Specifications.pdf PDF
Proposal_Schedule.pdf PDF
Volume_3_Specifications.pdf PDF
W912ER-16-R-0008.pdf PDF
Volume_3_Drawings.pdf PDF
Volume_4_Drawings.pdf PDF
Volume_2_Specifications.pdf PDF
Volume_2_Drawings.pdf PDF
Volume_1_Drawings.pdf PDF
DRAFT_443309_-_VOLUME_3_03-31-16.pdf PDF
DRAFT_CDC_Vol_2_of_3_11-Jan-15.pdf PDF
DRAFT_443309_-_VOLUME_4_03-31-16.pdf PDF
DRAFT_CDC_Vol_3_of_3_11-Jan-15.pdf PDF
DRAFT_443309_-_VOLUME_1_03-31-16.pdf PDF
DRAFT_443309_-_VOLUME_2_03-31-16.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN 0001: Site Topographical/Geotech Survey

AIR DEFENSE ICC FACILITIES #3 Performance Period:

Site Topographical/Geotech Survey for ALL THREE PROJECT Sites in accordance with the Contract Documents.

N/A

Chart #1: Air Defense Facilities #3

AIR DEFENSE ICC FACILITIES #3 Performance Period:

0002 Mobilization and Demobilization in Accordance with the Contract Documents 515

0003 Investigative Analysis/Reports in Accordance with the Contract Documents 515

0004 Construct a Screen Room Building in Accordance with the Contract Documents 515

0005 Renovate Air Operations Center Improvements in Accordance with the Contract Documents 515

0006 Construct Electrical Distribution System in Accordance with the Contract Documents 515

Construct Data and Telephone Communication Distribution System in Accordance with the Contract Documents

Chart #2: Air Defense Facilities #3 Optional Bid items

AIR DEFENSE ICC FACILITIES #3 Performance Period

OPTION 1: Replace Raised Access Flooring System in Accordance with the Contract Documents

0051 OPTION 2: Replace HVAC Units in Accordance with the Contract Documents 515

Chart #3: Air Defense Site #6

AIR DEFENSE SITE #6 Performance Period:

0008 Mobilization and Demobilization in Accordance with the Contract Documents 700

0011 Construct a Guard House Building in Accordance with the Contract Documents 515

Construct Engagement Control Station (ECS) with Concrete Ramps in Accordance with the Contract Documents

0013 Construct Guard Towers in Accordance with the Contract Documents 515

0014 Construct Frequency Converter Buildings in Accordance with the Contract Documents 515

0015 Construct Equipment Pads and Alaska Barriers in Accordance with the Contract Documents 515

Construct Fuel Truck Parking and Fuel Tank Storage with the Sunshades in Accordance with the Contract Documents

0020 Construct Telecommunication Tower in Accordance with the Contract Documents 515

Construct Power Plant Facility including but not limited to Generators, Transformers, Controls, Switchgears, etc.; in Accordance with the Contract Documents

Construct Security Fence, Entry Control Points and Force Protection Systems in Accordance with the Contract Documents

Construct Sewer Collection and Distribution System including Leach Field in Accordance with the Contract Documents

Construct Power and Lighting Distribution System including out site pole lighting in Accordance with the Contract Documents

Construct Data and Telephone Communication Distribution System in Accordance with the

Chart #4: Air Defense Site #6

0009 Construct a Headquarters Building in Accordance with the Contract Documents 700

0010 Construct a Toilet Building in Accordance with the Contract Documents 700

0016 Construct Storage Facility and Storage Pad in Accordance with the Contract Documents 700

0017 Construct Car Parking with Sunshade in Accordance with the Contract Documents 700

0018 Construct Truck Parking with Sunshade in Accordance with the Contract Documents 700

0022 Construct Roads and Sidewalks in Accordance with the Contract Documents 700

Perform Demolition, Site Work, Site Development, Strom Drainage in Accordance with the Contract Documents

0027 Construct CCTV Security System in Accordance

Chart #5: Air Defense Site #6 Optional Bid Items

0052 OPTION 3: Construct Prayer Gathering Building in Accordance with the Contract Documents 700

0053 OPTION 4: Construct Car Parking and Shelter in Accordance with the Contract Documents 700

OPTION 5: Construct Maintenance High-bay Facility in Accordance with the Contract Documents

OPTION 6: Additional Construct Cost to Paved Gravel Perimeter Patrol Road and Service Drive in Accordance with the Contract Documents

Chart #6: Air Defense Site #7

AIR DEFENSE SITE #7 Performance Period:

0029 Mobilization and Demobilization in Accordance with the Contract Documents 700

0032 Construct a Guard House Building in Accordance with the Contract Documents 515

Construct Engagement Control Station (ECS) with Concrete Ramps in Accordance with the Contract Documents

0034 Construct Guard Towers in Accordance with the Contract Documents 515

0035 Construct Frequency Converter Buildings in Accordance with the Contract Documents 515

0036 Construct Equipment Pads and Alaska Barriers in Accordance with the Contract Documents 515

Construct Fuel Truck Parking and Fuel Tank Storage with the Sunshades in Accordance with the Contract Documents

0041 Construct Telecommunication Tower in Accordance with the Contract Documents 515

Construct Power Plant Facility including but not limited to Generators, Transformers, Controls, Switchgears, etc.; in Accordance with the Contract Documents

Construct Security Fence, Entry Control Points and Force Protection Systems in Accordance with the Contract Documents

Construct Sewer Collection and Distribution System including Leach Field in Accordance with the Contract Documents

Construct Power and Lighting Distribution System including out site pole lighting in Accordance with the Contract Documents

Construct Data and Telephone Communication Distribution System in Accordance with the

Chart #7: Air Defense Site #7

0030 Construct a Headquarters Building in Accordance with the Contract Documents 700

0031 Construct a Toilet Building in Accordance with the Contract Documents 700

0037 Construct Storage Facility and Storage Pad in Accordance with the Contract Documents 700

0038 Construct Car Parking with Sunshade in Accordance with the Contract Documents 700

0039 Construct Truck Parking with Sunshade in Accordance with the Contract Documents 700

0043 Construct Roads and Sidewalks in Accordance with the Contract Documents 700

Perform Demolition, Site Work, Site Development, Strom Drainage in Accordance with the Contract Documents

0048 Construct CCTV Security System in Accordance

Chart #8: Air Defense Site#7

OPTION 7: Construct Headquarters Building Additional Wing in Accordance with the Contract Documents

0057 OPTION 8: Construct Prayer Gathering Building in Accordance with the Contract Documents 700

0058 OPTION 9: Construct Car Parking and Shelter in Accordance with the Contract Documents 700

OPTION 10: Construct Maintenance High-bay Facility in Accordance with the Contract Documents

OPTION 11: Construct Anti-Vehicle Ditch and Berm around exterior Fence in Accordance with the Contract Documents

File details come from the government source that posted it. Updated .