W912EK24R0002 - Question and Answer - 25 Oct. 2023.pdf
PDF 441 KB Posted
- Solicitation number
- W912EK24R0002
About this file
This document contains questions and answers related to solicitation number W912EK24R0002 for the Coralville Lake Ranger Building and Admin Repairs project. The U.S. Army Corps of Engineers is seeking a design-build contractor to renovate an administrative office and visitor center, and construct a new garage with storage. A more detailed scope of work will be provided in Phase Two of the solicitation. For the Phase One proposal, offerors should include a maximum of four specialized experience projects total, with at least one project for each required facility type. All applicable local, state, and federal permits will be required for planned geotechnical work. Design and construction services are both included in the single design-build contract. The 20% bid guarantee or $3 million, whichever is less, is only required with Phase Two proposals. Phase One proposals are due by October 26, 2023 per the latest amendment. The expected completion time for the project is 562 calendar days from notice to proceed.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question ID Contrator Question USACE Answer
I am looking to get a set of plans for this project coming up.
Please let me know how & where.
As a two-phase design-build requirement, a set of construction plans will not be developed by USACE for this project. A more detailed Scope of Work is pending and will be posted to SAM.gov when complete as part of the Phase two requirements package.
For Volume 2 Specialized Experience, is the maximum number of projects that can be included four (4) per building type for a total of eight (8)?
No.
A maximum of four (4) total projects can be included in an Offeror's Volume 2 Specialized Experience submission.
NOTE - There is a minimum of one (1) each project for each facility type(s) or their equivalent, similar commercial or institutional type:
Renovation of Administrative Office and Visitor Center, New Construction of a Garage with Storage.
We are putting together a proposal for geotechnical and materials testing/inspection services for a design-build contractor to include in their bid for the Coralville Lake Ranger Building and Admin Repairs project. Since USACE is the property owner, we are wondering, will a formal workplan be required and/or will there be any permitting requirements for the geotechnical drilling for the project?
All applicable local, state, and federal permits will be required for planned work to include permitting.
Workplans will be required.
Is this a design and construction project or are they 2 separate portions of the project?
As a two-phase design-build requirement, design and construction are both part of the same project.
The solicitation is occuring in two separate phases.
Phase I proposals are what are due by the due date and time listed in the RFP. If selected for Phase II as a most highly qualified offeror, you will be notified of your ability to participate and provided additional time to prepare a Phase II proposal.
I see that there is a 20% guarantee or $3,000,000. Does this need to be submitted with the initial proposals being submitted next week or is this requested during the next phase of bidding?
Bid Guarantee - The 20% of the bid price or $3,000,000.00 guarantee (whichever is less), in accordance with (IAW) FAR clause 52.228-1, is only required during Phase II proposal submission. A letter proving evidence of ability to obtain bonding, IAW Section L - Instructions, Conditions and Notices to Bidders, Subsection L.4.1.1, is required during Phase I proposal submission.
Q&A Below is new as of RFP Amendment 0003, dated 12 October 2023
W912EK24R0002 - Coralville Lake Ranger Building and Admin Repairs, dated 26 September 2023
I looked at all of the assets attached to the proposal and did not see a blueprint for either building. Is there a way to get that so I can provide it to the contractor?
Reference Section 01 10 00.00 20 (added via RFP Amendment 0004) and corresponding appendices for project specific requirements.
Also, is there an expected time frame for when this project needs to be completed?
Reference block 11 and/or clause FAR 52.211-10 Alt.
I of the most recent conformed copy of the RFP SF 1442 for contract completion time. The current contract completion is 562 calendar days after receiving the notice to proceed. The contract completion is subject to change with any future amendments.
Do I still have until the 26th of October to get this proposal to you?
Please reference block 13 of the most recent conformed copy of the RFP SF 1442 for proposal due date and time.
Q&A Below is new as of RFP Amendment 0004, dated 25 October 2023