This amendment modifies solicitation W912EK24R0002 for repairs to the Coralville Lake Ranger Building and Administration Building. The contractor period of performance end date is decreased from 730 to 562 days, and the completion date is now assumed to be 562 calendar days after a notice to proceed is issued on or after February 9, 2024. The amendment updates wage rates, procurement sections, and adds multiple specifications and statement of work appendices relating to project requirements, displays, room data, and more.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this amendment is to make the follow ing changes:
Update the Period of Performance
Update FAR Clause 52.211-10 Alt I
Update Wage Rates
Update Section L
Update Section M
Add Section 01 10 00.00 20 Statement of Work and Appendices
Add Multiple Spec Sections
Update the Question and Answ er
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Oct-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK24R0002
X 9B. DATED (SEE ITEM 11)
01-Sep-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Oct-2023
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS 1500 ROCK ISLAND D
ROCK ISLAND IL 61201
W912EK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EK24R0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The contractor period of performance end date has decreased by 168 days from 730 days to 562 days.
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -
ALTERNATE I (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 562 consecutive calenday days. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 09
February 2024. The completion date will be extended by the number of calendar days after the above date that the
Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of clause)
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been modified:
LIST OF ATTACHMENTS
List of Attachments:
Attachment J-1, Wage Rates entitled, “Wage General Decision Number: IA20230068,”
Revised 13 October 2023
Attachment J-2, Statement of Work, “Section 01 10 00.00 10, Statement of Work – General
Project Requirements,” Revised 10 October 2023
Attachment J-3, Section L entitled, “Section L – Instructions, Conditions and Notices to
Bidders,” Revised 25 October 2023
Attachment J-4, Section M entitled, “Section M – Evaluation Factors for Award,” Revised 25
October 2023
Attachment J-5, Statement of Work, “Section 01 10 00.00 20, Statement of Work – Project
Specific Requirements,” Dated 25 October 2023
Attachment J-6, Statement of Work Appendix 1, “Applicable Criteria,” Dated 25 October 2023
Attachment J-7, Statement of Work Appendix 2, “ESA/Abatement Documents,” Dated 25
Attachment J-8, Statement of Work Appendix 3, “Reference Documents,” Dated 25 October
Attachment J-9, Statement of Work Appendix 4, “Existing Condition Photographs,” Dated 25
Attachment J-10, Statement of Work Appendix 5, “Visitor Center Displays,” Dated 25 October
Attachment J-11, Statement of Work Appendix 6, “Room Data Sheets,” Dated 25 October 2023
Attachment J-12, Statement of Work Appendix 7, “Visitor Center Requirements,” Dated 25
Attachment J-13, Statement of Work Appendix 8, “Administration Building Septic Field,”
Dated 25 October 2023
Attachment J-14, Statement of Work Appendix 9, “Adjacency Matrices,” Dated 25 October
Attachment J-15, Spec Section 00 73 05, “Special Contract Requirements,” Dated 07
September 2023
Attachment J-16, Spec Section 01 32 01.00 10, “Project Schedule,” Dated 07 September 2023
Attachment J-17, Spec Section 01 33 00, “Submittal Procedures,” Dated 07 September 2023
Attachment J-18, Spec Section 01 33 16.00 10, “Design Data-Design After Award,” Dated 07
Attachment J-19, Spec Section 01 45 00.00 10, “Quality Control,” Dated 07 September 2023
Attachment J-20, Spec Section 01 45 00.15 10, “Resident Management System Contractor
Mode,” Dated 07 September 2023
Attachment J-21, Spec Section 01 50 02, “Temporary Construction Facilities,” Dated 07
Attachment J-22 , Spec Section 01 57 19, “Temporary Environmental Controls,” Dated 07
Attachment J-23, Spec Section 01 62 35, “Recycled Recovered Material,” Dated 07 September
Attachment J-24, Spec Section 01 78 00, “Closeout Submittals,” Dated 07 September 2023
(End of Summary of Changes)