This specification section outlines requirements for temporary construction facilities for the Coralville Lake Ranger Building and Admin Repairs project solicited by the Department of the Army Corps of Engineers Engineering District Rock Island. The contractor must prepare a site plan indicating any fenced areas and construction trailers along with ingress/egress routes and details for fence installation. Sanitation facilities for workers must be provided. A bulletin board displaying labor posters is required along with project and safety signs erected according to Corps of Engineers guidance. The contractor must maintain and protect traffic along affected roads, and construct and remove any necessary haul roads and barricades while limiting disruption to public access. Grass and vegetation within the site must be maintained throughout the project.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 50 02 - Page 1 of 3
SECTION 01 50 02
TEMPORARY CONSTRUCTION FACILITIES
07 September 2023
Table of Contents
1. OVERVIEW
1.1. GENERAL REQUIREMENTS
1.2. AVAILABILITY AND USE OF UTILITY SERVICES
1.3. BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN
1.4. PROTECTION AND MAINTENANCE OF TRAFFIC
1.5. MAINTENANCE OF CONSTRUCTION SITE
01 50 02 - Page 2 of 3
1. OVERVIEW
1.1. GENERAL REQUIREMENTS
1.1.1. Site Plan
Prepare a site plan indicating the proposed location and dimensions of any area to be fenced and used by the Contractor, the number of trailers to be used, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Also indicate if the use of a supplemental or other staging area is desired.
1.2. AVAILABILITY AND USE OF UTILITY SERVICES
1.2.1. See Section 00 72 00, Contract Clauses and Section 00 73 00, Special Contract
Requirements, for Utility Availability requirements.
1.2.2. Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities approved by the Contracting Officer. Government toilet facilities will not be available to Contractor's personnel.
1.2.3. Telephone
Make arrangements and pay all costs for desired telephone facilities.
1.3. BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN
1.3.1. Bulletin Board
Immediately upon beginning of onsite work, provide a weatherproof glass-covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, and other information approved by the Contracting Officer. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.
Display legible copies of the aforementioned data until work is completed. Remove the bulletin board from the site upon completion of the project.
1.3.2. Project and Safety Signs
Erect a project sign and a site safety sign with informational details as provided by the
Government at the Post award conference, within 15 days prior to any work activity on project site. Update the safety sign data daily, with light colored metallic or non-metallic numerals.
Remove the signs from the site upon completion of the project.
Engineer Pamphlet EP 310-1-6a contains the standardized layout and construction details for the signs. It can be found through a GOOGLE Search or try the US Army Corps of Engineers Techinfo
Website at http://www.hnd.usace.army.mil/techinfo/. Click on Publications then go to Engineer
Pamphlets and select EP 310-1-6a.
1.4. PROTECTION AND MAINTENANCE OF TRAFFIC
Provide access and temporary relocated roads as necessary to maintain traffic. Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Take measures for the protection and diversion of traffic, http://www.hnd.usace.army.mil/techinfo/
01 50 02 - Page 3 of 3 including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment and the work, and the erection and maintenance of adequate warning, danger, and direction signs, as required by the State and local authorities having jurisdiction.
Protect the traveling public from damage to person and property.
The Contractor's traffic on roads selected for hauling material to and from the site will interfere as little as possible with public traffic. Investigate the adequacy of existing roads and the allowable load limit on these roads. Repair any damage to roads caused by construction operations.
1.4.1. Haul Roads
The Contractor will, at its own expense, construct access and haul roads necessary for proper prosecution of the work under this contract. Construct haul roads with suitable grades and widths.
Avoid sharp curves, blind corners, and dangerous cross traffic. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and hauling roads will be subject to approval by the Contracting
Officer. Provide adequate lighting to assure full and clear visibility for full width of haul road and work areas during any night work operations. Remove haul roads designated by the Contracting
Officer upon completion of the work and restore those areas.
1.4.2. Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades will be required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
1.5. MAINTENANCE OF CONSTRUCTION SITE
Mow grass and vegetation located within the boundaries of the construction site for the duration of the project, from NTP to contract completion. Edge or neatly trim grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers from NTP to contract completion.
END OF SECTION 01 50 02