A22 - Attachment J-21 - Spec Section 01 50 02 - Temporary Construction Facilities - 07 Sept. 2023.pdf

PDF 40 KB Posted

Attached to
Coralville Lake Ranger Building and Admin Repairs
Solicitation number
W912EK24R0002
Issued by

About this file

This specification section outlines requirements for temporary construction facilities for the Coralville Lake Ranger Building and Admin Repairs project solicited by the Department of the Army Corps of Engineers Engineering District Rock Island. The contractor must prepare a site plan indicating any fenced areas and construction trailers along with ingress/egress routes and details for fence installation. Sanitation facilities for workers must be provided. A bulletin board displaying labor posters is required along with project and safety signs erected according to Corps of Engineers guidance. The contractor must maintain and protect traffic along affected roads, and construct and remove any necessary haul roads and barricades while limiting disruption to public access. Grass and vegetation within the site must be maintained throughout the project.

View the file

Other files

File Type Posted
A22 - W912EK24R0002 AMND 0005.pdf PDF
A22 - W912EK24R0002 Conformed Copy through AMND 0005.pdf PDF
A22 - Attachment J-22 - Spec Section 01 57 19 - Temporary Environmental Controls - 07 Sept. 2023.pdf PDF
A22 - Attachment J-12 - Statement of Work Appendix 7 - Visitor Center Requirements - 25 Oct. 2023.pdf PDF
A22 - Attachment J-24 - Spec Section 01 78 00 - Closeout Submittals - 07 Sept. 2023.pdf PDF
A22 - Attachment J-16 - Spec Section 01 32 01.00 10 - Project Schedule - 07 Sept. 2023.pdf PDF
A22 - Attachment J-5 - Section 01 10 00.00 20 - Statement of Work - Project Specific Requirements - 25 Oct. 2023.pdf PDF
A22 - Attachment J-19 - Spec Section 01 45 00.00 10 - Quality Control - 07 Sept. 2023.pdf PDF
A22 - Attachment J-23 - Spec Section 01 62 35 - Recycled Recovered Material - 07 Sept. 2023.pdf PDF
A22 - Attachment J-7 - Statement of Work Appendix 2 - ESA Abatement Documents - 25 Oct. 2023.pdf PDF
A22 - Attachment J-15 - Spec Section 00 73 05 - Special Contract Requirements - 07 Sept. 2023.pdf PDF
W912EK24R0002 - Question and Answer - 25 Oct. 2023.pdf PDF
A22 - Attachment J-10 - Statement of Work Appendix 5 - Visitor Center Displays - 25 Oct. 2023.pdf PDF
A22 - Attachment J-11 - Statement of Work Appendix 6 - Room Data Sheets - 25 Oct. 2023.pdf PDF
A22 - Attachment J-4 - Section M - Evaluation Factors for Award - 25 Oct. 2023.pdf PDF
A22 - Attachment J-3 - Section L - Instructions Conditions and Notices to Bidders - 25 Oct. 2023.pdf PDF
A22 - Attachment J-6 - Statement of Work Appendix 1 - Applicable Criteria - 25 Oct. 2023.pdf PDF
A22 - Attachment J-9 - Statement of Work Appendix 4 - Existing Condition Photographs - 25 Oct. 2023.pdf PDF
A22 - Attachment J-14 - Statement of Work Appendix 9 - Adjacency Matrices - 25 Oct. 2023.pdf PDF
A22 - Attachment J-17 - Spec Section 01 33 00 - Submittal Procedures - 07 Sept. 2023.pdf PDF
A22 - Attachment J-8 - Statement of Work Appendix 3 - Reference Documents - As-Builts - 25 Oct. 2023.pdf PDF
A22 - Attachment J-20 - Spec Section 01 45 00.15 10 - Resident Management System Contractor Mode - 07 Sept. 2023.pdf PDF
A22 - W912EK24R0002 AMND 0004.pdf PDF
A22 - Attachment J-18 - Spec Section 01 33 16.00 10 - Design Data-Design After Award - 07 Sept. 2023.pdf PDF
A22 - Attachment J-13 - Statement of Work Appendix 8 - Administration Building Septic Field - 25 Oct. 2023.pdf PDF
A22 - Attachment J-1 - Wage Rates - Johnson County - 13 Oct. 2023.pdf PDF
A22 - W912EK24R0002 Conformed Copy Through AMND 0003.pdf PDF
A22 - Attachment J-1 - Wage Rates - Johnson County - 01 Sept. 2023.pdf PDF
A22 - W912EK24R0002 AMND 0003.pdf PDF
A22 - W912EK24R0002 AMND 0001.pdf PDF
A22 - Attachment J-2 - Section 01 10 00.00 10 - Statement of Work - General Project Requirements - 10 Oct. 2023.pdf PDF
A22 - Attachment J-3 - Section L - Instructions Conditions and Notices to Bidders - 10 Oct. 2023.pdf PDF
A22 - W912EK24R0002.pdf PDF
A22 - Attachment J-4 - Section M - Evaluation Factors for Award - 10 Oct. 2023.pdf PDF
W912EK24R0002 - Question and Answer - 12 Oct. 2023.pdf PDF
A22 - W912EK24R0002 Conformed Copy Through AMND 0003.pdf PDF
A22 - W912EK24R0002 Conformed Copy Through AMND 0002.pdf PDF
A22 - W912EK24R0002 AMND 0002.pdf PDF
W912EK24R0002 Question and Answer - 26 Sept. 2023.pdf PDF
A22 - Attachment J-2 - Section 01 10 00.00 10 - Statement of Work - General Project Requirements - 01 Sept. 2023.pdf PDF
A22 - Attachment J-1 - Wage Rates - Johnson County - 18 Aug. 2023.pdf PDF
A22 - Attachment J-3 - Section L - Instructions Conditions and Notices to Bidders - 01 Sept. 2023.pdf PDF
A22 - Attachment J-4 - Section M - Evaluation Factors for Award - 01 Sept. 2023.pdf PDF
A22 - W912EK24R0002.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 50 02 - Page 1 of 3

SECTION 01 50 02

TEMPORARY CONSTRUCTION FACILITIES

07 September 2023

Table of Contents

1. OVERVIEW

1.1. GENERAL REQUIREMENTS

1.2. AVAILABILITY AND USE OF UTILITY SERVICES

1.3. BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN

1.4. PROTECTION AND MAINTENANCE OF TRAFFIC

1.5. MAINTENANCE OF CONSTRUCTION SITE

01 50 02 - Page 2 of 3

1. OVERVIEW

1.1. GENERAL REQUIREMENTS

1.1.1. Site Plan

Prepare a site plan indicating the proposed location and dimensions of any area to be fenced and used by the Contractor, the number of trailers to be used, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Also indicate if the use of a supplemental or other staging area is desired.

1.2. AVAILABILITY AND USE OF UTILITY SERVICES

1.2.1. See Section 00 72 00, Contract Clauses and Section 00 73 00, Special Contract

Requirements, for Utility Availability requirements.

1.2.2. Sanitation

Provide and maintain within the construction area minimum field-type sanitary facilities approved by the Contracting Officer. Government toilet facilities will not be available to Contractor's personnel.

1.2.3. Telephone

Make arrangements and pay all costs for desired telephone facilities.

1.3. BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN

1.3.1. Bulletin Board

Immediately upon beginning of onsite work, provide a weatherproof glass-covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, and other information approved by the Contracting Officer. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.

Display legible copies of the aforementioned data until work is completed. Remove the bulletin board from the site upon completion of the project.

1.3.2. Project and Safety Signs

Erect a project sign and a site safety sign with informational details as provided by the

Government at the Post award conference, within 15 days prior to any work activity on project site. Update the safety sign data daily, with light colored metallic or non-metallic numerals.

Remove the signs from the site upon completion of the project.

Engineer Pamphlet EP 310-1-6a contains the standardized layout and construction details for the signs. It can be found through a GOOGLE Search or try the US Army Corps of Engineers Techinfo

Website at http://www.hnd.usace.army.mil/techinfo/. Click on Publications then go to Engineer

Pamphlets and select EP 310-1-6a.

1.4. PROTECTION AND MAINTENANCE OF TRAFFIC

Provide access and temporary relocated roads as necessary to maintain traffic. Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Take measures for the protection and diversion of traffic, http://www.hnd.usace.army.mil/techinfo/

01 50 02 - Page 3 of 3 including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment and the work, and the erection and maintenance of adequate warning, danger, and direction signs, as required by the State and local authorities having jurisdiction.

Protect the traveling public from damage to person and property.

The Contractor's traffic on roads selected for hauling material to and from the site will interfere as little as possible with public traffic. Investigate the adequacy of existing roads and the allowable load limit on these roads. Repair any damage to roads caused by construction operations.

1.4.1. Haul Roads

The Contractor will, at its own expense, construct access and haul roads necessary for proper prosecution of the work under this contract. Construct haul roads with suitable grades and widths.

Avoid sharp curves, blind corners, and dangerous cross traffic. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and hauling roads will be subject to approval by the Contracting

Officer. Provide adequate lighting to assure full and clear visibility for full width of haul road and work areas during any night work operations. Remove haul roads designated by the Contracting

Officer upon completion of the work and restore those areas.

1.4.2. Barricades

Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades will be required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.

1.5. MAINTENANCE OF CONSTRUCTION SITE

Mow grass and vegetation located within the boundaries of the construction site for the duration of the project, from NTP to contract completion. Edge or neatly trim grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers from NTP to contract completion.

END OF SECTION 01 50 02