This document contains questions and answers related to solicitation number W912EK24R0002 for Coralville Lake Ranger Building and Admin Repairs. The project involves a two-phase design-build requirement for renovation of an administrative office and visitor center as well as new construction of a garage with storage. Phase I proposals are due by the date and time specified in the solicitation. Phase II will involve preparation of proposals by the most highly qualified offerors selected from Phase I. A 20% bid guarantee or $3 million, whichever is less, will be required with Phase II proposals but not Phase I. Local, state and federal permits as well as workplans will be necessary for planned geotechnical drilling work. The U.S. Army Corps of Engineers is the contracting agency.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question ID Contrator Question USACE Answer 0001 I am looking to get a set of plans for this project coming up. As a two-phase design-build requirement, a set of
For Volume 2 Specialized Experience, is the maximum number of projects that can be included four (4) per building type for a total of eight (8)?
No.
A maximum of four (4) total projects can be included in an Offeror's Volume 2 Specialized Experience submission.
NOTE - There is a minimum of one (1) each project for each facility type(s) or their equivalent, similar commercial or institutional type:
Renovation of Administrative Office and Visitor Center, New Construction of a Garage with Storage.
We are putting together a proposal for geotechnical and materials testing/inspection services for a design-build contractor to include in their bid for the Coralville Lake Ranger Building and Admin Repairs project. Since USACE is the property owner, we are wondering, will a formal workplan be required and/or will there be any permitting requirements for the geotechnical drilling for the project?
All applicable local, state, and federal permits will be required for planned work to include permitting.
Workplans will be required.
Is this a design and construction project or are they 2 separate portions of the project?
As a two-phase design-build requirement, design and construction are both part of the same project.
The solicitation is occuring in two separate phases.
Phase I proposals are what are due by the due date and time listed in the RFP. If selected for Phase II as a most highly qualified offeror, you will be notified of your ability to participate and provided additional time to prepare a Phase II proposal.
I see that there is a 20% guarantee or $3,000,000. Does this need to be submitted with the initial proposals being submitted next week or is this requested during the next phase of bidding?
Bid Guarantee - The 20% of the bid price or $3,000,000.00 guarantee (whichever is less), in accordance with (IAW) FAR clause 52.228-1, is only required during Phase II proposal submission. A letter proving evidence of ability to obtain bonding, IAW Section L - Instructions, Conditions and Notices to Bidders, Subsection L.4.1.1, is required during Phase I proposal submission.
Q&A Below is new as of RFP Amendment 0003, dated 12 October 2023