This is an amendment to a solicitation for the Coralville Lake Ranger Building and Admin Repairs project. The amendment extends the proposal submission deadline from October 26, 2023 to November 1, 2023 at 2:00 PM CST. It also adds a schedule of prices table listing estimated costs for the base bid of rehabilitating the administrative office and visitor center and constructing a seven bay garage building, as well as optional additional work including expanding the garage building and demolishing an existing garage. Offerors are advised to complete unit price and amount fields for all line items in the schedule. The Department of the Army Corps of Engineers Engineering District Rock Island will evaluate proposals and reserves the right to exercise any or all optional line items after awarding the base contract.

View the file

Other files

File Type Posted
A22 - W912EK24R0002 Conformed Copy through AMND 0005.pdf PDF
A22 - Attachment J-22 - Spec Section 01 57 19 - Temporary Environmental Controls - 07 Sept. 2023.pdf PDF
A22 - Attachment J-12 - Statement of Work Appendix 7 - Visitor Center Requirements - 25 Oct. 2023.pdf PDF
A22 - Attachment J-24 - Spec Section 01 78 00 - Closeout Submittals - 07 Sept. 2023.pdf PDF
A22 - Attachment J-16 - Spec Section 01 32 01.00 10 - Project Schedule - 07 Sept. 2023.pdf PDF
A22 - Attachment J-5 - Section 01 10 00.00 20 - Statement of Work - Project Specific Requirements - 25 Oct. 2023.pdf PDF
A22 - Attachment J-19 - Spec Section 01 45 00.00 10 - Quality Control - 07 Sept. 2023.pdf PDF
A22 - Attachment J-23 - Spec Section 01 62 35 - Recycled Recovered Material - 07 Sept. 2023.pdf PDF
A22 - Attachment J-7 - Statement of Work Appendix 2 - ESA Abatement Documents - 25 Oct. 2023.pdf PDF
A22 - Attachment J-15 - Spec Section 00 73 05 - Special Contract Requirements - 07 Sept. 2023.pdf PDF
W912EK24R0002 - Question and Answer - 25 Oct. 2023.pdf PDF
A22 - Attachment J-10 - Statement of Work Appendix 5 - Visitor Center Displays - 25 Oct. 2023.pdf PDF
A22 - Attachment J-21 - Spec Section 01 50 02 - Temporary Construction Facilities - 07 Sept. 2023.pdf PDF
A22 - Attachment J-11 - Statement of Work Appendix 6 - Room Data Sheets - 25 Oct. 2023.pdf PDF
A22 - Attachment J-4 - Section M - Evaluation Factors for Award - 25 Oct. 2023.pdf PDF
A22 - Attachment J-3 - Section L - Instructions Conditions and Notices to Bidders - 25 Oct. 2023.pdf PDF
A22 - Attachment J-6 - Statement of Work Appendix 1 - Applicable Criteria - 25 Oct. 2023.pdf PDF
A22 - Attachment J-9 - Statement of Work Appendix 4 - Existing Condition Photographs - 25 Oct. 2023.pdf PDF
A22 - Attachment J-14 - Statement of Work Appendix 9 - Adjacency Matrices - 25 Oct. 2023.pdf PDF
A22 - Attachment J-17 - Spec Section 01 33 00 - Submittal Procedures - 07 Sept. 2023.pdf PDF
A22 - Attachment J-8 - Statement of Work Appendix 3 - Reference Documents - As-Builts - 25 Oct. 2023.pdf PDF
A22 - Attachment J-20 - Spec Section 01 45 00.15 10 - Resident Management System Contractor Mode - 07 Sept. 2023.pdf PDF
A22 - W912EK24R0002 AMND 0004.pdf PDF
A22 - Attachment J-18 - Spec Section 01 33 16.00 10 - Design Data-Design After Award - 07 Sept. 2023.pdf PDF
A22 - Attachment J-13 - Statement of Work Appendix 8 - Administration Building Septic Field - 25 Oct. 2023.pdf PDF
A22 - Attachment J-1 - Wage Rates - Johnson County - 13 Oct. 2023.pdf PDF
A22 - W912EK24R0002 Conformed Copy Through AMND 0003.pdf PDF
A22 - Attachment J-1 - Wage Rates - Johnson County - 01 Sept. 2023.pdf PDF
A22 - W912EK24R0002 AMND 0003.pdf PDF
A22 - W912EK24R0002 AMND 0001.pdf PDF
A22 - Attachment J-2 - Section 01 10 00.00 10 - Statement of Work - General Project Requirements - 10 Oct. 2023.pdf PDF
A22 - Attachment J-3 - Section L - Instructions Conditions and Notices to Bidders - 10 Oct. 2023.pdf PDF
A22 - W912EK24R0002.pdf PDF
A22 - Attachment J-4 - Section M - Evaluation Factors for Award - 10 Oct. 2023.pdf PDF
W912EK24R0002 - Question and Answer - 12 Oct. 2023.pdf PDF
A22 - W912EK24R0002 Conformed Copy Through AMND 0003.pdf PDF
A22 - W912EK24R0002 Conformed Copy Through AMND 0002.pdf PDF
A22 - W912EK24R0002 AMND 0002.pdf PDF
W912EK24R0002 Question and Answer - 26 Sept. 2023.pdf PDF
A22 - Attachment J-2 - Section 01 10 00.00 10 - Statement of Work - General Project Requirements - 01 Sept. 2023.pdf PDF
A22 - Attachment J-1 - Wage Rates - Johnson County - 18 Aug. 2023.pdf PDF
A22 - Attachment J-3 - Section L - Instructions Conditions and Notices to Bidders - 01 Sept. 2023.pdf PDF
A22 - Attachment J-4 - Section M - Evaluation Factors for Award - 01 Sept. 2023.pdf PDF
A22 - W912EK24R0002.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The reason for this amendment is to make the follow ing changes:

Extend the proposal submission time and due date from 2:00 PM CST on 26 October 2023 to 2:00 PM CST on 01 November 2023.

Add the Schedule of Prices

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Oct-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK24R0002

X 9B. DATED (SEE ITEM 11)

01-Sep-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Oct-2023

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS 1500 ROCK ISLAND D

ROCK ISLAND IL 61201

W912EK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EK24R0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 26-Oct-2023 02:00 PM to 01-Nov-2023 02:00 PM.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

SCHEDULE OF PRICES

SCHEDULE OF PRICES

27 October 2023

*This Schedule of Prices is for reference only during Phase I and will be completed by the most highly qualified Offeror(s) during Phase II.

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

BASE BID (Administrative Office and Visitor Center

Rehabilitation, and Construction of Seven Bay Garage Building)

0001 Design of Administrative Office and Visitor Center Rehabilitation and Seven Bay Garage Building

1 JOB XXXXXXXX $___________

0002 Construction of Administrative and Visitor Center Renovation

1 JOB XXXXXXXX $___________

0003 Construction of Site Work and Utilities for the Seven Bay Garage Building, complete to the five-foot line of the facilities below

1 JOB XXXXXXXX $___________

0004 Construction of Seven Bay Garage Building

1 JOB XXXXXXXX $___________

TOTAL OF ESTIMATED AMOUNTS OF BASE BID

(ITEM NOS. 0001 THROUGH 0004, INCL.)

OPTION A (Design and

Construction of Two Additional Bays (Nine Total) for Garage

Building )

0101 Design and Construction of Two Additional Bays (Nine Total) for Garage Building

TOTAL OF ESTIMATED AMOUNTS OF OPTION A

(ITEM NO. 0101, INCL.)

OPTION B (Design and

Construction of Two Additional Bays (Eleven Total) for Garage

Building )

0201 Design and Construction of Two Additional Bays (Eleven Total) for Garage Building

TOTAL OF ESTIMATED AMOUNTS OF OPTION B

(ITEM NO. 0201, INCL.)

OPTION C (Demolition of

Existing Garage)

0301 Demolition and Site Restoration of Existing Garage

TOTAL OF ESTIMATED AMOUNTS OF OPTION C

(ITEM NO. 0301, INCL.)

TOTAL OF ESTIMATED AMOUNTS BASE BID AND OPTIONS A THROUGH C

(ITEM NOS. 0001 THROUGH 0301, INCL.)

JOB = LUMP SUM

PLEASE ENSURE THAT UNIT PRICE AND AMOUNT LINES FOR ALL ITEMS

HAVE BEEN COMPLETED.

THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE ANY OR ALL

OPTIONS

AFTER THE DATE THE CONTRACTOR RECEIVES NOTICE TO PROCEED.

IF OPTION A IS EXERCISED, THE CONTRACT WILL BE EXTENDED 30

CALENDAR DAYS

IF OPTIONS B OR C ARE EXCERCISED, NO ADDITIONAL CALENDAR DAYS

WILL BE GRANTED.

OR

THE GOVERNMENT RESERVES THE RIGHT TO EXCERCISE OPTIONS AT ANY

TIME

WITHIN 90 DAYS AFTER AWARD OF THE BASE

BID.

IF OPTION A IS EXCERISED, THE CONTRACT WILL BE EXTENDED 30

CALENDAR DAYS

IF OPTIONS B OR C ARE EXCERCISED, NO ADDITIONAL CALENDAR DAYS

WILL BE GRANTED.

(End of Summary of Changes)