W912DS24B0002 Amend 0008.pdf
PDF 870 KB Posted
- Solicitation number
- W912DS24B0002
About this file
This document is an amendment to a solicitation for the construction of the South Shore of Staten Island, Area E, Hurricane Sandy Coastal Storm Risk Management Project in Richmond County, New York. The amendment makes changes to the plans, reissues the bid schedule, and extends the bid opening date to April 18, 2024.
The solicitation is for a firm-fixed-price construction contract valued between $100 million to $175 million. The project includes construction of large interior drainage ponds, stormwater drainage structures, and relocation of existing sanitary sewers. The contract period of performance is 1,279 calendar days from the notice to proceed. The solicitation will be issued via an unrestricted Invitation for Bids (IFB) and the North American Industrial Classification Standard (NAICS) code is 237990 - Other Heavy and Civil Engineering Construction.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
-- Make some changes to the Plans (Draw ings).
-- Reissue the Bid Schedule in its entirety, to be used for the Bid Opening.
-- Extend the Bid Opening date to 18 April 2024 at 2:00pm EDT.
NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, or by signing Block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 40
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Apr-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS24B0002
X 9B. DATED (SEE ITEM 11)
22-Dec-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Apr-2024
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS24B0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0008
To Bidders: Use the following Bid Schedule in this Amendment 0008 for your bid on 18 April 2024 at 2:00pm EDT. The following Bid Schedule replaces the one posted with Amendment 0007.
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT
PRICE AMOUNT
0001 117 Cubic Yard
Concrete Pipe Collars FFP Includes concrete, stone and Graffiti Resistant Coating for pipe collars.
Quantity is ESTIMATED. FOB: Destination
PSC CD: C219
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT
PRICE
AMOUNT 1,612 Cubic Yard
Concrete (Non-structural) FFP Includes un-reinforced concrete for forebays, scour holes, intake sumps and micropool.
Quantity is ESTIMATED. FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003 407 Linear
Foot
16" DIP
FFP
Includes pipe material, excavation, and pipe bedding for surface pond inlets.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
AMOUNT
16" Flap Gate
FFP
Includes flap gate, excavation, and bedding for surface pond inlets.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0004 9 Each
0005 233 Linear
Foot
18" DIP
FFP
Includes pipe material, excavation, and pipe bedding for surface pond inlets.
Quantity is ESTIMATED.
FOB: Destination
AMOUNT
18" Flap Gate
Includes flap gate, excavation, and bedding for surface pond inlets.
0006 6 Each
0007 322 Linear
Foot Berm Box Sewer
FFP
All work necessary to install precast box sewer including excavation piles, pile testing and materials.
4' x 2' Flap Gate
Includes flap gate, excavation, and bedding for surface pond inlets.
0008 8 Each
0009 158 Ton
Debris Removal and Disposal
FFP
Includes removal and disposal of debris, refuse, construction waste, demolition debris, abandoned equipment, and other non-soil materials.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0010 181,281 Square
Yard Clearing, Grubbing and Removals
FFP
Includes felling, trimming, and cutting of trees and satisfactory disposal of trees and other vegetation designated for removal.
Quantity is ESTIMATED.
Tree Removal
FFP
Includes tree removal from 6" to above 24" DBH and disposal.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0012 297,350 Cubic
Yard Excavation
FFP
Includes all labor, materials, equipment and work for excavation, dewatering and on-site transportation of excavated materials from Ponds. This item also includes over excavation for the ponds (~1ft) and areas for phragmites removal.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
0011 239 Each
0013 422,775 Ton
Handling, Transportation, & Disposal of Non-Hazardous Contaminated Soil
FFP
Includes all labor, materials, equipment and work for handling, hauling and disposal of contaminated materials. All material excavated from ponds shall be considered contaminated, non-hazardous material until proven otherwise by testing and sampling results.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
AMOUNT
Sampling & Testing of Contaminated/Potentially Hazardous Soil for Disposal Parameters
FFP
Includes all labor, materials, equipment and work for the collection and testing of soil sample sets to determine disposal parameters and appropriate handling and disposal methods.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
0014 750 Set
W912DS24B000
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0015 1 Job
Handling, Transportation, & Disposal of Hazardous Contaminated Soils
FFP
Includes all labor, materials, equipment and work for handling, hauling and disposal for soils determined to have hazardous concentrations of contaminants in accordance with the drawings and specifications. Contractor is to verify that the work is performed by an approved contractor.
Use of this CLIN will be based on contractor submitted results of soil sampling and testing. Payment under this CLIN will be based on contractor submitted invoices/receipts and proof of payment. Payment will only be for the increase in unit price above CLIN 0013.
THIS BID ITEM IS NOT TO EXCEED $1,000,000.
FOB: Destination
$1,000,000
NET AMT
AMOUNT
As-Builts
FFP
AS-BUILT "Contractor shall complete the Record ("As-Builts") CAD submittal as required by Specification Section 01 78 00 CLOSEOUT SUBMITTALS for Record Drawings ("As-Builts") Requirements, $200,000.
FOB: Destination
$200,000
NET AMT
0016 1 Job
0017 15,500 Cubic
Yard Fill
FFP
Includes all labor, materials, equipment and work for fill and grading at the Ponds.
Trees
Includes all excavation and preparation of planting pits and beds, adding soil amendments, furnishing plants, digging, inspecting, planting, pruning, staking, guying, anchoring, wrapping, mulching, fertilizing, liming, discing, raking, tilling, harrowing, mowing, material, watering and maintaining all plant material and seeded areas. The price bid shall also include the costs of all rough and fine grading, all specified soils necessary and required for the satisfactory completion of all landscaping work and all other work incidental thereto in accordance with the plans and specifications to the satisfaction of the Contracting Officer.
0018 2,040 Each
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0019 195,200 Each
Herbaceous Plants (Plugs)
FFP
Includes all excavation and preparation of planting pits and beds, adding soil amendments, furnishing plants, digging, inspecting, planting, pruning, staking, guying, anchoring, wrapping, mulching, fertilizing, liming, discing, raking, tilling, harrowing, mowing, material, watering and maintaining all plant material and seeded areas. The price bid shall also include the costs of all rough and fine grading, all specified soils necessary and required for the satisfactory completion of all landscaping work and all other work incidental thereto in accordance with the plans and specifications to the satisfaction of the Contracting Officer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
AMOUNT
Shrubs
FFP
Includes all excavation and preparation of planting pits and beds, adding soil amendments, furnishing plants, digging, inspecting, planting, pruning, staking, guying, anchoring, wrapping, mulching, fertilizing, liming, discing, raking, tilling, harrowing, mowing, material, watering and maintaining all plant material and seeded areas. The price bid shall also include the costs of all rough and fine grading, all specified soils necessary and required for the satisfactory completion of all landscaping work and all other work incidental thereto in accordance with the plans and specifications to the satisfaction of the Contracting Officer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
0020 2,415 Each
0021 147,459 Square
Yard Seeding
FFP
Includes furnished seed, seeding areas, liming, discing, raking, tilling, harrowing, mowing, material, watering and maintaining all seeded areas.
0022 60,427 Cubic
Yard Top Soil
FFP
Include the cost of all labor, materials and equipment necessary to prepare topsoil areas, furnish, mix, place and incorporate topsoil and compost, and all other work incidental thereto, in accordance with the plans and specifications to the satisfaction of the Contracting Officer.
AMOUNT
Vector and Pest Control
FFP
Includes the cost for all labor, materials, equipment and incidental expenses necessary or required to complete the work in accordance with the plans and specifications to the satisfaction of the Engineer.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0024 147,459 Square
Yard Jute Mesh
FFP
Includes the cost for all labor, materials, equipment and incidental expenses necessary or required to complete the work in accordance with the plans and specifications to the satisfaction of the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
0023 1 Job
AMOUNT
Invasive Plant Removal and Treatment
FFP
The quantity to be measured for payment shall be work days for invasive plant removal and herbicide treatment. Crew (2 people).
FOB: Destination
NET AMT
AMOUNT
Tree and Root Pruning
FFP
Includes completion of general tree pruning and all mobilization and incidental costs, including the disposal of wood chips.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0025 1 Job
0026 600 Each
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0027 49,184 Linear
Foot Goose Exclusion Fence
FFP
Includes the total number of linear feet of fence furnished, installed, maintained and accepted in accordance with the Plans and Specifications and the directions of the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
AMOUNT
Deer Cage
FFP
Includes the cost to furnish all materials, labor, and equipment necessary to install the deer fence specified herein as required by the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
0028 4,455 Each
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0029 11,406 Linear
Foot Construction Limit Fence
FFP
The quantity to be measured for payment shall be the total number of linear feet of construction limit fence furnished, installed and maintained in accordance with the Plans and Specifications and the directions of the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0030 14,282 Square
Yard Slope Stabilization Mat
FFP
Includes per square yard of slope stabilization mat installed shall constitute full compensation for all labor, material, and equipment and incidental expenses necessary to complete the work as shown on the contract drawings and in accordance with the specifications to the satisfaction of the Engineer.
Quantity is ESTIMATED.
AMOUNT
Tree Guard
FFP
Includes the cost for all labor, materials and equipment required for installation of temporary wooden tree guards.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
AMOUNT
SWPPP Permit Compliance
FFP
Includes material for, installation of, and maintenance of: sediment traps, stabilized construction entrances, silt fences, dirtbags, portable sediment tanks, and other temporary erosion and sediment controls; as required for SWPP permit compliance.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0031 277 Each
0032 1 Job
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0033 1 Job
Not Available
FFP
This CLIN is not available.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0034 8,961 Linear
Foot Black Chain Link Fence
FFP
Includes linear feet furnished and installed in accordance with the plans, specifications and directions of the Engineer.
Quantity is ESTIMATED.
FOB: Destination
Not Available
AMOUNT
Permanent Signs on Steel Rail Posts
FFP
The quantity of 0.080" Gauge Aluminum Signs to be paid for under this item must be the total number of signs, fabricated and installed on steel posts or delivered in accordance with the plans, specifications and directions of the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
AMOUNT
0.020" Temporary Signs
FFP
The quantity of 0.020" Gauge Aluminum Signs to be paid for under this item must be the total number of signs, fabricated and installed at the designated locations or delivered to DEP, in accordance with the plans, specifications and directions of the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0035 60 Each
0036 72 Each
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0037 10,779 Square
Foot Permanent Maintenance Accessway (Pavers)
FFP
Includes installation and materials (concrete pavers, geotextile, gravel, sand and topsoil) for 12' wide accessways and weir chamber accessway.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0038 55,108 Square
Foot Permanent Maintenance Accessway (Gravel)
FFP
Includes installation and materials (geotextile, gravel, sand and topsoil) for 6', 10' and 12' wide accessways and gravel berms, compacted earth fill for accessway berms is covered under Bid Item 17.
Quantity is ESTIMATED.
AMOUNT
Survey Monuments
FFP
Includes unit price per survey monument, and shall include the cost of all labor, materials, equipment, and all work incidental thereto, necessary to complete this item in accordance with the plans and specifications and to the satisfaction of the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
AMOUNT
Fence Swing Gate
FFP
Includes fabricating and installing swing gate and posts, furnishing modified Lock, and fabricating and furnishing steel plate lock cover in accordance with the plans, specifications and directions of the Engineer, the Contractor shall receive the unit price bid.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0039 86 Each
0040 13 Each
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0041 1,652 Square
Yard Reno Mattress
FFP
Includes all excavation, grading and geotextile fabric necessary to install the total square yards of reno mattress as directed by the Engineer.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0042 1 Job
Quintard Street Structures
FFP
All work necessary to construct Headwall #1, Box Sewer #1 & #2, Weir Chamber # 1 and Junction Chamber # 1 & 2 at Quintard Street, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, sheeting and bracing, structural concrete, foundation construction, piles, pile testing, crushed stone, stone facing, pipe fittings, flap gate, sidewalk restoration, pavement demolition and replacement, and maintenance and protection of traffic (MPT) in accordance with the Contract Drawings and Specifications.
AMOUNT
Sand Lane North Structures
FFP
All work necessary to construct Headwall #2, Box Sewer #3, and Junction Chamber # 3 at Sand Lane and Quincy Ave, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, sheeting and bracing, structural concrete, foundation construction, piles, pile testing, crushed stone, stone facing, pipe fittings, flap gate, pavement demolition and replacement, and maintenance and protection of traffic (MPT) in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
AMOUNT
Sand Lane South Structures
FFP
All work necessary to construct Weir Chamber #2, Box Sewer #4 & 6, and Junction Chamber # 4, 8 & 9 at Sand Lane and Father Capodanno Blvd., including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, sheeting and bracing, structural concrete, foundation construction, piles, pile testing, crushed stone, stone facing, pipe fittings, flap gate, pavement demolition and replacement, and maintenance and protection of traffic (MPT) in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0043 1 Job
0044 1 Job
AMOUNT
Pearsall Street Structures
FFP
All work necessary to construct Headwall #3, Box Sewer #5 and Junction Chamber # 5 & 7 at Pearsall St., including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, sheeting and bracing, structural concrete, foundation construction, piles, pile testing, crushed stone, stone facing, pipe fittings, flap gate, sidewalk restoration, pavement demolition and replacement, and maintenance and protection of traffic (MPT) in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
AMOUNT
Mallory Avenue - Storm Network
FFP
All work necessary to install storm sewer network along Mallory Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 18” ESVP and 24” RCP, piles, pile testing, flap gate, catch basin, manholes, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0045 1 Job
0046 1 Job
AMOUNT
McLaughlin St North - Storm Network
FFP
All work necessary to install storm sewer network along McLaughlin Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 18” ESVP, piles, pile testing, flap gate, manholes excavation, dewatering, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
AMOUNT
McLaughlin St South - Storm Network
FFP
All work necessary to install storm sewer network along McLaughlin Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 24" RCP, piles, pile testing, flap gate, manholes, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0047 1 Job
0048 1 Job
AMOUNT
Wentworth Avenue - Storm Network
FFP
All work necessary to install storm sewer network along Wentworth Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 24” RCP, piles, pile testing, flap gate, catch basins, manhole, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
AMOUNT
Orlando Street - Storm Network FFP
FFP
All work necessary to install storm sewer network at the end of Orlando Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 4’-0” W X 2’-0” H RCP, piles, pile testing, flap gate and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0049 1 Job
0050 1 Job
AMOUNT
Oceanside Avenue - Storm Network
FFP
All work necessary to install storm sewer network along Oceanside Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 18” ESVP, piles, pile testing, flap gate, catch basins, manhole, pavement restoration and MPT in accordance with the Contract Drawings and Specifications
FOB: Destination
NET AMT
AMOUNT
Agnes Place - Storm Network
FFP
All work necessary to install storm sewer network along Agnes Place, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 24” RCP, piles, pile testing, flap gate, catch basin, manhole, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0051 1 Job
0052 1 Job
AMOUNT
Andrew Street - Storm Network
FFP
All work necessary to install storm sewer network along Andrew Street, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, Junction Chamber #6, 38"W X 24"H Elliptical RCP, piles, pile testing, flap gate, catch basin, manhole, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
AMOUNT
Vulcan Street - Storm Network
FFP
All work necessary to install storm sewer network along Vulcan St, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 18" ESVP, piles, pile testing, flap gate, catch basin, manhole, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0053 1 Job
0054 1 Job
AMOUNT
Lansing Avenue - Sanitary Network
FFP
All work necessary to install sanitary sewer network along Lansing Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 18” ESVP, piles, pile testing, manhole, existing utility removal, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
AMOUNT
Oceanside Avenue & Quintard Street Sanitary Network
FFP
All work necessary to install sanitary sewer network along Oceanside Avenue, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 30” RCP, 24” RCP, 18” ESVP, piles, pile testing, manhole, existing utility removal, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0055 1 Job
0056 1 Job
AMOUNT
Sand Lane North - Sanitary Network
FFP
All work necessary to install sanitary sewer network along Sand Lane North, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, crushed stone, 8” ESVP, piles, pile testing, manhole, utility removal, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0058 11,431 Linear
Foot Television Inspection of Sewer
FFP
All labor, materials, equipment, and work necessary for the number of linear feet of existing sewers (regardless of the sizes) actually inspected to the satisfaction of the Contracting Office, measured along the centerline of the sewer through the manholes. CCTV Inspection for pre and post sewer installation.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
0057 1 Job
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0059 11,431 Linear
Foot Sewer Cleaning
FFP
All labor, materials, equipment, and work necessary for the number of linear feet of existing sewers (regardless of the sizes) actually cleaned of loose debris, grease, oil, and silt to the satisfaction of the Contracting Office, measured along the centerline of the sewer through the manholes.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0060 600 Linear
Foot 8" Water Main
FFP
All work necessary to install water main hydrants, 6” hydrant valves, 6” DIP Class 56 hydrant connections, and 8”x6” 3-way connections including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, pipe material, valves, vaults, fittings, utility removal, pipe bedding, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
Quantity is ESTIMATED.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0061 450 Linear
Foot 20" Water Main
FFP
All work necessary to install water main hydrants, 6” hydrant valves, 6” DIP Class 56 hydrant connections, and 20”x6” 3-way connections including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, pipe material, valves, vaults, fittings, utility removal, pipe bedding, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0062 34 Linear
Foot 12" Water Main
FFP
All work necessary to install water main, including but not limited to excavation, dewatering, backfilling, hauling and soil disposal, support of excavation, pipe material, valves, vaults, fittings, utility removal, pipe bedding, pavement restoration and MPT in accordance with the Contract Drawings and Specifications.
Quantity is ESTIMATED.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0063 1 Job
Supplies/Service
FFP
Bond, Mobilization/Demobilization, Government Field Office Trailers, and Other Costs (by exception only): Other costs to complete the work including (but not limited to) bond, mobilization/demobilization, and Government field office trailers. Other costs may be included by exception only if they are not specifically captured elsewhere in the bid schedule. General conditions or job/field office overhead shall NOT be included under this line item and will not be paid as a separate activity; these costs shall be included within the unit cost of all other line items.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0064 1 Job
Handling, Transportation and Disposal of PCB Contaminated Soil
FFP
Includes all labor, materials, equipment and work for handling, hauling and disposal of PCB contaminated materials. All material excavated from ponds shall be considered contaminated, non-hazardous material until proven otherwise by testing and sampling results.
Use of this CLIN will be based on contractor submitted results of soil sampling and testing. Payment under this CLIN will be based on contractor submitted invoices/receipts and proof of payment. Payment will only be for the increase in unit price above CLIN 0013.
THIS BID ITEM IS NOT TO EXCEED $1,000,000.
Quantity is ESTIMATED.
FOB: Destination
$1,000,000
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0065 3,600 Square
Foot Bank Stabilization
FFP
Includes all labor, materials, equipment and work for installation of bank stabilization.
Quantity is ESTIMATED.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0066 1 Job
OPTION – Landscape Construction Maintenance
FFP
Includes all maintenance for landscape establishment and exterior plants after acceptance of all work by the Contracting Officer in accordance with the contract drawings and specifications. An additional 730 calendar days will be added to the contract period of performance for maintenance work to be performed under this CLIN only. This additional time will NOT increase the period of performance to complete work performed under any other CLIN. Separate contract milestones will be established for Construction Completion and Landscape Maintenance Completion under Specification Section 01 30 00. This option may be exercised at any time during the base contract period of performance.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0067 1 Job
OPTION – Additional Insurance
FFP
Additional Insurance in accordance with Specifications Section 01 30 00 paragraph 1.5.1.
The amount of bid will be the maximum amount payable. Actual payment will be based on actual costs.
Section 00 20 00 - Instructions for Procurement
TOTALS
TOTALS:
CLIN 0001 $
CLIN 0002 $
CLIN 0003 $
CLIN 0004 $
CLIN 0005 $
CLIN 0006 $
CLIN 0007 $
CLIN 0008 $
CLIN 0009 $
CLIN 0010 $
CLIN 0011 $
CLIN 0012 $
CLIN 0013 $
CLIN 0014 $
CLIN 0015 $ 1,000,000
CLIN 0016 $ 200,000
CLIN 0017 $
CLIN 0018 $
CLIN 0019 $
CLIN 0020 $
CLIN 0021 $
CLIN 0022 $
CLIN 0023 $
CLIN 0024 $
CLIN 0025 $
CLIN 0026 $
CLIN 0027 $
CLIN 0028 $
CLIN 0029 $
CLIN 0030 $
CLIN 0031 $
CLIN 0032 $
CLIN 0033 $ Not Available
CLIN 0034 $
CLIN 0035 $
CLIN 0036 $
CLIN 0037 $
CLIN 0038 $
CLIN 0039 $
CLIN 0040 $
CLIN 0041 $
CLIN 0042 $
CLIN 0043 $
CLIN 0044 $
CLIN 0045 $
CLIN 0046 $
CLIN 0047 $
CLIN 0048 $
CLIN 0049 $
CLIN 0050 $
CLIN 0051 $
CLIN 0052 $
CLIN 0053 $
CLIN 0054 $
CLIN 0055 $
CLIN 0056 $
CLIN 0057 $
CLIN 0058 $
CLIN 0059 $
CLIN 0060 $
CLIN 0061 $
CLIN 0062 $
CLIN 0063 $
CLIN 0064 $ 1,000,000
CLIN 0065 $
CLIN 0066 $
CLIN 0067 $
TOTAL CLINs 0001-0067 $
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 11-Apr-2024 02:00 PM to 18-Apr-2024 02:00 PM.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .