Amendment 0002.pdf

PDF 400 KB Posted

Attached to
LINCOLN HALL RENOVATION, BLDG. 607 Federal contract opportunity
Solicitation number
W912DS23R0009
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

This document contains an amendment to a solicitation for the renovation of Lincoln Hall at Building 607. The amendment provides responses to contractor questions to clarify the request for proposal. Key details include clarifying that all sidewalks, curbs, and utilities outside the 5-foot delineation line on drawings are to be included in CLIN 0002. It also specifies that various personnel, including assistant CQC managers, only need to be physically present during work in their specialty areas. Additionally, it confirms that Davis-Bacon wages are locked at time of award. The document aims to address contractor questions to refine the scope of work for the fixed-price renovation by the U.S. Army Corps of Engineers, New York District.

View the file

Other files for this federal contract opportunity

Other files attached to LINCOLN HALL RENOVATION, BLDG. 607, newest first.
File Type Posted
W912DS23R0009-0005.pdf PDF
Amendment 0004.pdf PDF
I-603 - FINISH MATERIAL SCHEDULE.pdf PDF
I-604 - FINISH MATERIAL SCHEDULE.pdf PDF
S-502.pdf PDF
A-202.pdf PDF
A-204.pdf PDF
A-401.pdf PDF
A-562 - MILLWORK DETAILS - BRIEFING ROOM.pdf PDF
Supplmental laydown area at Ordnance road.pptx PPTX presentation
A-429 - ENLARGED BRIEFING ROOM PLANS AND ELEVATIONS.pdf PDF
I-103 - LEVEL B1 FLOOR PLAN - FINISH.pdf PDF
I-602 - FINISH MATERIAL SCHEDULE.pdf PDF
L-502.pdf PDF
Amendment 0003.pdf PDF
21 30 00-001.2_R3 Fire Pump House Submittal (Cullum).pdf PDF
Lincoln Hall Specification Changes 22 JUN 2023.pdf PDF
C-001.pdf PDF
W912DS23R0009 0001.pdf PDF
CD101.pdf PDF
CS103.pdf PDF
2023.06.20 Lincoln Hall site walk through sign in sheet.pdf PDF
Lincoln Hall Drawing Changes 22 JUN 2023.pdf PDF
AS BUILT DRAWING 1A - Approximate Location of Knox BatteryAmend 1.pdf PDF
LH- H-101.pdf PDF
W912DS23R0009.pdf PDF
JA 006-23 Belden Brick.pdf PDF
JA 008-23-Ruabon Quarry Tile.pdf PDF
JA 010-23 Best Hardware Lock Cylinders and Cores.pdf PDF
Vol 1 WP Lincoln Hall Revised RTA Specifications 1 MAR 2023.pdf PDF
LH_VOLUME 03_Revised_RTA_2023-03-01.pdf PDF
Vol 2 WP Lincoln Hall Revised RTA Specifications 1 MAR 2023.pdf PDF
Vol 3 WP Lincoln Hall Revised RTA Specifications 1 MAR 2023.pdf PDF
LH_VOLUME 01_Revised_RTA_2023-03-01.pdf PDF
LH_VOLUME 04_Revised_RTA_2023-03-01.pdf PDF
JA 007-23 Distributed Antenna System.pdf PDF
JA 013-23 Monaco.pdf PDF
LH_VOLUME 02_Revised_RTA_2023-03-01.pdf PDF
JA 009-23 Avaya Switch.pdf PDF
JA 011-23 Ventrol AHU.pdf PDF
JA 012-23 Identiv Card Access System.pdf PDF
JA 014-23 Shark Meter.pdf PDF
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide responses to contractor RFIs.

NOTE: Offerors must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)

1. CONTRACT ID CODE PAGE OF PAGES

1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Jul-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS23R0009

X 9B. DATED (SEE ITEM 11)

07-Jun-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Jul-2023

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS23R0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.

1. Q. On Drawing CS101, keynote 39 calls for all work associated with sidewalks, curbs, and any utilities outside the 5 feet shall be CLIN 0002. This line divides notes 17 and 14 leaving only 1 foot outside the 5-foot line.

Do you only want 1 foot of concrete to be figured in CLIN 002? This also occurs at note 6 in the middle of the buildings. This also occurs at note 14 on the south side of the building. Please clarify the splitting of work for CLIN 0002.

A. "Keynote 39 states: CLIN 0002 - ALL WORK ASSOCIATED WITH THE SIDEWALKS, CURBS, AND ANY UTILITIES OUTSIDE THE 5 FT LINE. Utility work is differentiated at the 5' line but all sidewalks, curbs, ramps should be included in CLIN 0002 inside and outside of the 5' delineation mark. This includes answers to notes 17, 14 and 6. "

2. Q. In spec section 01 45 00.00 10 part 3.4.3 CQC Personnel, it is mentioned that there are additional personnel required to assist the CQC System Manager. 6 additional people, each with a different specialty, are being added to the mandatory staff that is already listed in spec section 01 30 00 Administrative Requirements. They are also to be hired by the prime Contractor directly and not through a supplier or a subcontractor. Please advise if the 6 additional personnel are to be full time on site during the construction process. If not, please advise.

A. These personnel must be physically present at the construction site during work on the specialized personnel's areas of responsibility.

3. Q. Please confirm if the Davis Bacon wages provided in the RFP are locked in the duration of the project or do we need to factor in wage rate escalations (which may be issued through new modification numbers after the bid due date) in our bid.

A. Davis Bacon wages are updated up to time of award and then locked for the duration of the project.

4. Q. Spec section 01 30 00 part 1.12.a.(2). indicates that if the Contractor subcontracts more than 70% of the contract value, two superintendents must be provided. Please advise if the 2 assistant superintendents required per part 1.7 [ of spec section 01 30 00] can replace the requirement for the additional superintendent. If not, please advise if the 2 superintendents must be present full time at the site for the duration of the project.

A. Yes, the 2 assistant superintendents required per part 1.7 [ of spec section 01 30 00] can replace the requirement for the additional superintendent.

5. Q. Please advise as to when the anticipated NTP date will be.

A. Notice to Proceed is expected to occur on or about 15 NOV 2023.

6. Q. Can you please provide a draft of the formal contract for review.

A. Please clarify the question.

7. Q. Please confirm all loose FFE in the building shall be removed by the owner.

A. This was clarified in AD drawing notes associated with amendment 1.

8. Q. Do the residential type appliances; E1 [Refrigerator], E2 [Microwave], E3[Coffee Pot] and E4 [ Mini- Refrigerator] fall under FF&E by others or will it be the responsibility of the GC to provide.

A. Not in contract, by other. GFGI items are on contract documents for information only.

9. Q. On drawing CS103 it calls out locations of contractor laydown area and jobsite trailers. Cullum Hall will still be under construction during this project. Please confirm that the only laydown area for this jobsite is the parking lot at Lincoln. Also, due to the size of the access road, the jobsite trailers will need to be placed by crane.

Please confirm that there can be a road shutdown scheduled to place the trailers.

A. See Amendment 1 for updated CS103. Trailer placement is Contractor's means and methods.

Coordination with USACE COR to confirm trailer location and road closures.

10. Q. Currently Cullum Hall’s temporary power is being pulled from Lincoln Hall’s switchgear. Please confirm that the existing switchgear at Lincoln will remain in place until Cullum Hall’s new switchgear can provide power for Cullum.

A. The temporary power for Cullum Hall installed in Lincoln Hall, room B210 off of the existing panel DBH(Breaker #1), is required to remain intact until the new switchgear for Cullum Hall is installed and active. This service is run in the existing tunnel between Cullum and Lincoln to room XB301 and up to room B210.

11. Q. Please confirm that the temporary power for Lincoln can be pulled from the NEW transformer at Cullum Hall once installed.

A. The end state is that the NEW Transformer supplies power to both buildings. The provision of temporary power is up to the contractor.

12. Q. "Specification 013000 states that the following key management personnel must be employed for the full duration of the contract.

Superintendent (1ea) Asst. Superintendent: (2ea) CQC Manager (1ea) Asst. CQC Manager Mechanical (1ea) Asst. CQC Manager Electrical (1ea) SSHO (1ea) Cyber Security Representative (1ea) Specification 014500.0010 states that the following Quality Control staff requirements, during progress of work, and must be directly employed by the prime contractor.

CQC Manager (1ea) Asst. CQC Manager Mechanical (1ea) Asst. CQC Manager Electrical (1ea) Asst. CQC Manager Structural (1ea) Asst. CQC Manager Architectural (1ea) SSHO (1ea) Please confirm the following:

1. Can one qualified Asst. CQC manager take on multiple roles? For example, mechanical and electrical.

2. Must the specialty Asst. CQC manager be employed during the duration of the contact or just during the installation of their specialty trade?"

A. "One qualified Asst. CQC manager can take on multiple roles if their experience and education meets the requirements. The specialty Asst. CQC manager must be physically present at the construction site during work on the specialized personnel's areas of responsibility to include commissioning. The specialty Asst CQC is to be a part of the project continuously but is not required to be on site when specialty activities are not ongoing. The Asst.

CQC with specialty must review the specific specialty submittals prior to submission.

13. Q. Cullum Hall will be under construction during a large portion of Lincoln. Please confirm that the access route on the north and east side of Lincoln will remain open for frequent material and equipment deliveries.

A. The intent is for the access route north and east of Lincoln to remain open, as depicted on CS103.

14. Q. As shown on drawing CS103, the sitework on the south side of Lincoln is currently within the construction limits of Cullum Hall. Cullum Hall will be under construction for a large portion of Lincoln. Please advise when this contract will have access to that area to perform scheduled work under this contract.

A. Access to the south side of Lincoln Hall will need to be coordinated with USACE COR working on the Cullum Hall Repair Project.

15. Q. The Temp power for the Trailers will require a transformer. Please confirm if this equipment is to be provided by others (CLP) and where the power is to be supplied from.

A. The Contractor will be responsible to contract directly with CLP to coordinate temporary power if power is pulled from somewhere other than Lincoln Hall.

16. Q. On the mechanical and plumbing schedules no make or model is given for the equipment or fixtures.

Please provide.

A. No make or models will be provided for mechanical and plumbing, all equipment shall meet applicable specification requirements.

17. Q. Please confirm that the building shall be completely unoccupied during construction and no phasing shall be required.

A. Lincoln Hall will be unoccupied during construction.

18. Q. Drawing CS103 States Government construction trailer will switch from Cullum to Lincoln personal once the project is complete. We assume at this point the Lincoln Hall awarded GC will be responsible for paying trailer rental costs. Please confirm. If this is correct, please advise as to the contract duration the Lincoln Hall GC will be responsible for carrying the Government trailer costs.

A. Please see revised CS103 as issued with Amendment 1. Government trailer will not be required for Lincoln Hall until JAN 2025, location to be provide at a later date.

19. Q. Please advise if an organizational approach/chart is a requirement of the Technical Proposal. Are we required to submit resumes with the technical proposal?

A. No - Refer to section 00 21 00 "Instructions" of the solicitation.

20. Q. Have demolition permits been filed?

A. No permits have been filed at this point. All permits required such as dig safe will be the contractor’s responsibility after award.

21. Q. Finish Plan Legend Shows "RUBBER TILE, RT-3" at Room 341 - PHOTO STUDIO. Interior Room Finish Schedule - Level 3 lists Room 341 - PHOTO STUDIO as being RT-4. Confirm which Rubber Tile to be at this location.

A. The photo studio should be RT-4 per the schedule. Finish plan will be revised for room 341.

22. Q. Who is the existing BMS vendor currently in the building.

A. The equipment mostly had standalone controls, and there was a Johnson Controls pneumatic controls system for some small things like damper operation. Project scope is to tie into basewide BMS as described in contract drawings and specifications.

23. Q. Is the GC required to furnish and install the Clocks and PA Systems in their entirety including all equipment, wiring, devices, terminations etc.?

A. A PA system is not required. The Master Clock system must be a complete and functional system based on West Point standard, per plan drawings and Diagram T-603 including notes.

24. Q. Please advise if any MC Cables are allowed in the walls as part of the project electrical roughing work.

A. Insulated conductors must be installed in conduits as indicated in spec section 262000 paragraph 3.1.3.

MC cable is not approved.

25. Q. Drawing AD-102- Please advise if windows at Level B2 are to be removed.

A. Yes, reference demolition keynote 19 on sheet AD-102 stating full window removal typical. Refer to A- 201, A-202, A-203, and A-204 for window types, and A-615 for window schedule.

26. Q. Specification Manual includes Section(s) 12 50 00.13 10 - Furniture and Furniture Installation & 12 59 00 - Systems Furniture. Section 12 50 00.13 10 references an FF&E Package Attachment & GSA Schedule. These items are NOT located in this section, as stated on page 1. Please provide these missing items.

A. FFE is Not in Contract. Specification 12 50 00 will be removed.

27. Q. Please provide water supply data and Fire Pump data for fire suppression system.

A. Water supply data and fire pump data are for the shared fire pump installed under the adjacent Cullum Hall project. The end state is that both Cullum Hall and Lincoln Hall will be fed from the shared fire pump located in the mechanical yard between the two buildings. See attached Cullum Hall pump house submittal/data.

28. Q. Is there a specification section that can be provided for Unistrut Framing? Drawing A-552 detail C1 Keynote 15 requires Unistrut framing system per delegated design to support MEP infrastructure.

A. Subcontractor providing delegated design needs to provide the design for the Unistrut. Contractor to provide shop drawing and calculations for DOR review.

29. Q. Specification Section 07 81 00; Part 2 section 2.4 calls out Spray Applied Intumescent Coating System FP-2. Please advise as to the location(s) that are to receive Intumescent Coatings.

A. Please see architecture drawings A-430 and A-554.

30. Q. Are J- Hooks permittable?

A. No. J-Hooks are not permitted per UFC.

31. Q. Typically, "Pressure testing an air barrier system for air tightness" is a specification and requirement on this type of project. There was no reference in the TOC/ Specifications. Please confirm if this will be a requirement of the project.

A. "Where placed, the spray foam insulation will also provide an effective air barrier providing improved air leakage performance. However, due to a variety of impractical and inaccessible conditions at the exterior wall and roof, the project does not include the detailing for a complete air barrier that would include air barrier transitions between building envelope planes like wall and roof planes or the wall planes and floor slabs. The requirement for pressure testing was removed from the project for those reasons."

32. Q. Is the existing [assumed] cementitious fireproofing to be considered "hot" requiring remediation?

A. Refer to the HAZMAT Survey included in contract specifications, volume 2, Division 2.

33. Q. "Level B3: Detail #6 on AD101 refers to SD101 for slab demolition. In mechanical room B301, there’s a portion marked on SD101, but not on AD101. Is this getting removed?

A. Yes, this slab area would be removed as noted in the structural drawings.

34. Q. On AD102 in mechanical room B218, will the upper and lower walls be removed as well? Detail #1 in this room only points to the wall along the corridor.

A. Dashed line means delete. The walls in these rooms are to be deleted. Also refer to structural demolition in this area to confirm areas of demolition.

35. Q. Detail #16 on AD102/B205 calls out ceramic tile removal, is there tiling to be removed in B204/206 as well (B204/206 are similar type rooms).

A. Yes - ceramic tile is to be removed in these rooms.

36. Q. Detail #18 on AD102 calls out removal of GWB furred partition/interior window trim, is there a specific location for this scope? (Most partition removals are annotated).

A. Furred partitions at the exterior wall are to be removed in occupied spaces starting at Stair A and ending with the existing restrooms. Note 18 shown is pointing to the north facing exterior wall.

37. Q. Detail #1 on AD103 calls out various partition walls for removal. We need clarification if all partition walls are getting removed.

A. Keynote 1 indicating to remove full height walls is shown as a typical situation that points to a typical dashed wall. Walls that are shown as dashed lines are to be removed. as indicated in the Demo legend at the bottom of the sheet.

38. Q. Detail #6 on AD103 calls for the removal of masonry wall areas along corridor B100B. All areas are clear except for the wall along room B122. Is this entire wall getting demolished or a section of it?"

A. The wall along B122 is to remain in its entirety. Coordinate with new work drawing A-103

39. Q. Detail #7 on AD103 calls for the removal of trim and windows (plural), but the drawing only points to one window. Are there other windows to be removed?

A. Note 7 and Note 15 on AD103 refer to all windows on the sheet.

40. Q. Detail #8 on AD103 calls for the removal of suspended acoustical tiles, grids and hangers and the note refers to the electrical drawing (ED103) for details on this removal. However, the area marked for removal on ED103 does not appear to be consistent with the removal on AD103.

A. On AD-103 Keynote 8 in Rooms B101, B102, B103, B104 and other rooms adjacent to B104 is not shown. In those rooms the ceiling is to be removed per Keynote 8.

(End of Summary of Changes)