This solicitation package outlines requirements for a maintenance dredging project. The U.S. Army Corps of Engineers seeks a contractor to dredge approximately 600,000 cubic yards of sediment from the Main and Port Newark Channels of Newark Bay in New Jersey to authorized depths between -40 and -50 feet MLLW plus one foot allowable overdepth using a mechanical dredge with a closed clamshell environmental bucket. The contractor must furnish upland placement sites for dewatering and disposal of dredged materials which are expected to consist primarily of silt and clay. Multiple barges and tugboats will also be needed to transport materials. The contractor must obtain and provide all necessary permits for dredging, transportation, dewatering, and final placement activities. Work is required to commence within five days of notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per day to minimize impacts to vessel traffic. The performance period is anticipated to be between August 2022 and March 2023. The estimated value of the contract is between $25-100 million. Bids for this unrestricted solicitation are due on [DATE].

View the file

Other files

File Type Posted
Abstract 22B0010.pdf PDF
TECHSPECS(revised)01 30 00AM0004.pdf PDF
6 of 6 NB22-AM-0004.pdf PDF
5 of 6 NB22-AM-0004.pdf PDF
2 of 6 NB22 - Gen Loc Map-AM-0004.pdf PDF
TECHSPECS(revised)01 11 00AM0004.pdf PDF
3 of 6 NB22-AM-0004.pdf PDF
Amendmet 0004 note.pdf PDF
Amendmetn 0004.pdf PDF
1 of 6 NB22 - Cover and Index-AM-0004.pdf PDF
W912DS22B0010 Amendment 0003.pdf PDF
OtherDocuments.pdf PDF
Newark Bay DO51 Upland Data Tables - Final.xlsx XLSX spreadsheet
J135936-2 Std_Tal_L4 Final Report.pdf PDF
J135978-2 Std_Tal_L4 Final Report.pdf PDF
180-135978-2_MEPsv_Pivot.xls XLS spreadsheet
J135751-2 Std_Tal_L4 Final Report.pdf PDF
W912DS22B0010 0002.pdf PDF
180-135936-2_MEPsv_Pivot.xls XLS spreadsheet
Newark Bay DO 51 Cover Letter.pdf PDF
180-135642-2_MEPsv_Pivot.xls XLS spreadsheet
180-135751-1_MEPsv_Pivot.xls XLS spreadsheet
J135642-2 Std_Tal_L4 Final Report.pdf PDF
180-135508-1_MEPsv_Pivot.xls XLS spreadsheet
180-135751-2_MEPsv_Pivot.xls XLS spreadsheet
180-135642-1_MEPsv_Pivot.xls XLS spreadsheet
180-135978-1_MEPsv_Pivot.xls XLS spreadsheet
180-135936-1_MEPsv_Pivot.xls XLS spreadsheet
J135508-1.pdf PDF
W912DS220B0010 0001.pdf PDF
03 - TECH SPECS (revised) - W912DS-22-B-0010.pdf PDF
03 - TECH SPECS - W912DS-22-B-0010.pdf PDF
W912DS22B0010.pdf PDF
06 - L_XYZ Data - 5137-3ftmed-mllw-ELEV.pdf PDF
04 - PLANS - W912DS-22-B-0010.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Maintenance Dredging of Newark Bay, NJ Federal Navigation Project NB22

10278-0090:

Contract drawings are as follows:

FY 2022

Maintenance Dredging of Newark Bay, New Jersey

Federal Navigation Project

SHEET NO. DESCRIPTION

Sheet 1 Cover and Index

Sheet 2 General Location Map, Coordinates, NOAA Chart, Benchmarks, & Typical

Cross Section Sheet 3 Dredging Area 1 (BASIC WORK)

Dredging Area 2 (OPTION 3)

Sheet 4 Dredging Area 3 (BASIC WORK)

Sheet 5 Dredging Areas 3 & 4 (BASIC WORK) Dredging Area 6 (OPTION 2)

Sheet 6 Dredging Area 5 (OPTION 1) & Dredging Area 6 (OPTION 2)

f. The Contractor shall check all drawings furnished to him immediately upon their receipt and shall promptly notify the Contracting Officer or Contracting Officer's Representative of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements unless dimensions are specified.

Large-scale drawings shall in general govern over small-scale drawings. Information and data provided in contract specifications shall govern over similar information and data specified in contract drawings. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have thereby been avoided (DOD FAR Suppl.

52.236-7002).

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

-- End of Section --

DOCUMENT 00 01 15 Page 3