This document is an "Approval in Principle" review letter from ABS Global Engineering regarding the structural drawings for a deck cargo barge. The key details are:
The review was conducted for compliance with the ABS Rules for Building and Classing Steel Barges, 2022 and the ABS Rules for Building and Classing Marine Vessels, 2022. ABS performed a statement of compliance review for the hull structure to meet ABS Ice Class C0 requirements per the client's request, though the U.S. Army Corps of Engineers does not require the ice belt design to satisfy low temperature requirements. ABS provided technical comments regarding the deck plating material, connection details, and longitudinal stiffener arrangements, which were addressed through revisions to the drawings. ABS stated they would be prepared to class the final design of the barge once the detailed engineering drawings and documents are submitted for full approval review.
View the file
Other files for this federal contract opportunity
Show all 40
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABS Global Engineering 275 Slater Street, Suite 1003 | Ottawa (ON), K1P 5H9 | Canada
Task – T2483246 Class No.: TBD Shipyard: TBD / Hull No.: TBD Flag: United States of America Subject: Deck Cargo Barge
Attention: Mr. Joshua Sebastian, The Shearer Group, Inc. (442598)
The document shown in the attached list is reviewed in accordance with the applicable requirements of the following:
• ABS Rules for Building and Classing Steel Barges, 2022.
• ABS Rules for Building and Classing Marine Vessels, 2022.
Please note our review is based on the following conditions:
1. At your request, we have carried out an “Approval in Principle” review of the documents in the attached list.
2. The hull structural drawings are also subjected to a Statement of Compliance review for compliance with ABS Ice Class C0 as per your request.
3. The primary objective of this review is to establish compliance in principle with the applicable ABS Rules, insofar as they relate to the details submitted, that when all other requirements have been satisfactorily met, the barge will be eligible for the proposed Class notations: À A1, Barge, Great Lake Service.
4. It is also to be noted that before final approval can be granted, the proposed design will need to be verified against the Rules, Regulations and Standards applicable at the time that the contract for construction is signed or the keel is laid, as applicable.
5. The markups made on the document are to be incorporated in the final design that will be submitted for approval.
6. Please note that our review at this time in no way precludes any future amendments which may be deemed necessary due to submittal of additional information, clarification or drawing revisions during detailed engineering review for the subject design.
7. ABS would be prepared to class the final design of this concept when the relevant design drawings, calculations and documents are submitted for review on completion of the detailed engineering, and after ABS surveyors have attended the fabrication survey during the construction and installation. Subsequent maintenance of Class will be subject to satisfactory in-service inspection by ABS Surveyors as required for Classification.
8. Main Deck structure reviewed for an uniformly distributed deck loading of 3,000 lbf/ft2.
Comments S-013 through S-016 are closed with this review.
Electronically published by ABS Ottawa.
Reference T2483246, dated 19-DEC-2023.
275 Slater Street, Suite 1003 | Ottawa (ON), K1P 5H9 | Canada
For any clarifications, contact Aldo Martino at (343) 633-1424 or amartino@eagle.org.
Very truly yours, Jihed Boulares Director, Engineering
Electronically Signed by: Aldo Martino
Electronically published by ABS Ottawa.
mailto:amartino@eagle.org
275 Slater Street, Suite 1003 | Ottawa (ON), K1P 5H9 | Canada
Documents List
Drawing No. Rev. Title Status
888-B301-01 3 Midship Section Reviewed 888-B301-02 3 Welding Schedule Reviewed 888-B305-01 3 Deck & Bottom Plating Reviewed 888-B307-01 3 Shell Plating Reviewed 888-B309-01 3 Transverse Structure Reviewed with remarks 888-B311-01 3 Longitudinal Structure Reviewed
Electronic copies of the documents, appropriately stamped, are available in the ABS Client Portal.
Comments List:
Thread No. Comment Text Facilities Action
S-013 888-B305-01 - Deck & Bottom Plating , 888-B301-
01 - Midship Section , 888-B307-01 - Shell Plating
, 888-B309-01 - Transverse Structure , 888-B311-
01 - Longitudinal Structure
TBD
[Closed]
Technical
ABS
Comment
We note your request for a Statement of Compliance review of the structural drawings in accordance with applicable requirements for the Ice
Class C0. In this regard, the following items require further design change
(or) clarification.
1. The material and material grade are to comply with ABS MVR 6-1-
5/33. Grade of material for the deck plating and gunwale, sheer strake and deck stringer are to be revised.
2. Connection details in way of the upper turn of the bilge, which is within the ice belt zone, is to be made flush so as to avoid any damage during operations in first year ice.
3. Side shell longitudinals' collar plates in way of transverse webs are to be either shifted close to side shell, or a full collar plate is to be provided as to avoid soft patch within the ice belt region.
4. End connections in way of the webs and stiffeners within ice belt region are to be well developed. These members are to be attached and bracketed such that the Rule required net shear area in way of these end connections are satisfied. Refer to ABS MVR 6-
1-5/13.5 & 15.
Customer Reply
Comment 1: Per US Army Corps of Engineers MDC, the Government does not require the ice belt design, or material selected, to satisfy the low temperature requirements as stated in the ABS Rules. Request the material requirements, as specified in ABS MVR 6-1-5/33, to be except from the Statement of Compliance of Ice Class C0. Comments 2 & 3: We
275 Slater Street, Suite 1003 | Ottawa (ON), K1P 5H9 | Canada respectfully disagree. This detail is in accordance with standard barge design. This detail is the same as another Ice Classed barge designed through MDC, the CELRE Crane Barge Harvey Replacement.”
ABS Reply We have received your confirmation of a statement of compliance review, and we have no objection to the proposed material grade. Rest of the comment remains open pending submission and review of revised drawings as per email communication.
ABS Reply ABS has received updated drawing and notes statement of compliance regarding material grade. Comment closed.
S-014 888-B309-01 - Transverse Structure TBD [Closed]
Technical
ABS
Comment
The intermediate bottom shell longitudinal stiffeners in way of the bow region noted to terminate at Fr. 4 as per the bottom plan (888-B305-01, Sheet 2). The typical section does not show relevant end connection details for the intermediate stiffeners. In this regard, additional details for the bottom structure in way of Fr. 4 are to be included in the drawing for review.
Customer Reply
Please see revision 3 of 888-B309-01 Transverse Structure, submitted
11/21/2023.
ABS Reply ABS has received the updated revision detailing bottom structure at frame
4. Comment closed.
S-015 888-B311-01 - Longitudinal Structure TBD [Closed]
Technical
ABS
Comment
It is noted that there is no shear connection provided between the deck transverse and the centerline longitudinal bulkhead for the bulkhead to be considered as an effective support for the considered span and provided section modulus (ABS SBR 5-1-1/7). In this regard, a collar plate is to be provided as shown in the Detail 3-23C (on Page 3) of the drawing.
Customer Reply
Per clients request the CL long'l BHD deck and bottom cutouts have been removed. Please see revision 3 of 888-B311-01 Longitudinal Structure, submitted 11/21/2023.
ABS Reply ABS Has received updated drawing showing that cutouts have been removed. comment closed.
S-016 888-B307-01 - Shell Plating TBD [Closed]
Technical
ABS
Comment
We note your request for a Statement of Compliance review of the structural drawings in accordance with applicable requirements for the Ice
Class C0. Bow arrangement does not include deep or intercostal stringers as required by ABS MVR 6-1-5/13.9. Please revise.
275 Slater Street, Suite 1003 | Ottawa (ON), K1P 5H9 | Canada
Customer Reply
Section of rules sited is applicable to Transversely Framed vessels. As our vessel is longitudinally framed we have complied with rules as specified in
ABS MVR 6-1-5/15 for Longitudinally Framed vessels. Section 15 does not require deep or intercostal stringers.
ABS Reply Comment remains open pending submission and review of revised drawing for the bow area as per email communication.
ABS Reply Updated bow arrangement has been received. Comment closed