This pre-solicitation notice describes an upcoming indefinite delivery, indefinite quantity multiple award task order contract for design-build construction services. The contract will support the U.S. Army Medical Command's Medical Sustainment, Restoration and Modernization program across the continental United States, Alaska, and Hawaii over a five-year period with a total capacity of $240 million. Services will include design, renovation, alteration, repair, and construction of medical facilities. Offerors must have experience with performance-based requirements and working in active healthcare facilities. The acquisition will use a two-phase selection process inviting up to five proposals to phase two. The anticipated solicitation release is June 14, 2019 with proposals due around July 23, 2019 and up to five contracts to be awarded.
Solicitation Phase I
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS ACQUISITION IS A 100% SMALL BUSINESS (SB) SET-ASIDE FIRM FIXED PRICE (FFP) INDEFINITE DELIVERY/INDEFINITE QUANTITY (IDIQ), MULTIPLE AWARD TASK ORDER CONTRACT (MATOC) FOR DESIGN-BUILD (DB) CONSTRUCTION SERVICES. THIS WILL BE FOR VARIOUS FACILITIES IN SUPPORT OF U.S. ARMY MEDICAL COMMAND (MEDCOM) MEDICAL SUSTAINMENT, RESTORATION AND MODERATION (MSRM) PROGRAM WITH A CAPACITY OF $240M. THE CONTRACT DURATION WILL BE FOR A BASE ORDERING PERIOD OF FIVE (5) YEARS, NAICS
CODE IS 236220, SMALL BUSINESS SIZE STANDARD IS $36.5M.
THIS DB CONSTRUCTION MATOC WILL BE PROCURED THROUGH A TWO PHASE DESIGN-BUILD SELECTION PROCEDURES AS AN REQUEST
FOR PROPOSAL (RFP) AND A TOTAL SMALL BUSINESS (SB) SET ASIDE.
LAKISHA D. VANCE 501.324.5720
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
11-Jul-2019
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________1826 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.228-15
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________3 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________12 Aug 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
USACE, LITTLE ROCK (W9127S)
700 W. CAPITOL AVE, RM 7315
LITTLE ROCK AR 72201-3225
W9127S
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
(501) 324-5196FAX:TEL: (501) 340-5720 TEL: FAX:
W9127S19R6002 205
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 1 Years
BASE - ARMY DESIGN-BUILD MATOC 2.0
FFP
THIS IS A FIVE (5) YEAR BASE PERIOD FOR THE INDEFINITE
DELIVERY/INDEFINITE QUANTITY (IDIQ) FOR THE SUPPORT OF THE
US ARMY MEDICAL COMMAND (MEDCOM), MEDICAL SUSTAINMENT
RESTORATION AND MODERNIZATION (MSRM) MISSION. THE
MULTIPLE AWARD TASK ORDER CONTRACT (MATOC) IS FOR
DESIGN-BUILD CONSTRUCTION SERVICES FOR CONUS-WIDE TO
INCLUDE AK AND HI. THE MINIMUN GUARANTEE WILL BE $10,000.00
AT THE END OF THE FIVE YEAR CONTRACT DURATION IF NO AWARD
OF A TASK ORDER IS REALIZED.
FOB: Destination
MAX
NET AMT
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 1826 dys. ADC 1 MEDICAL SUPPORT BRANCH
GREG YADA
P.O. BOX 867 700 WEST CAPITAL
LITTLE ROCK AR 72203
501 324 5720 FOB: Destination
967275
Section 00 21 00 - Instructions
NOTICE TO OFFERORS
INSTRUCTIONS, CONDITIONS, & NOTICES TO OFFERORS
1.0 DECRIPTION OF THE PROGRAM
2.0 GENERAL PROCEDURES/REQUIREMENTS
3.0 INTRODUCTION NOTICE TO OFFERORS
4.0 PREPARING PROPOSALS
5.0 GENERAL INSTRUCTIONS
6.0 SUMMARY
1.0 DECRIPTION OF THE PROGRAM
This acquisition is a 100% Small Business (SB) set-aside firm fixed price (FFP) indefinite delivery/indefinite quantity (ID/IQ), multiple award task order (MATOC), for design-build (DB) construction services. This will be for various facilities in support of U.S. Army Medical Command (MEDCOM) medical sustainment, restoration and moderation (MSRM) program with capacity of $240M.
The contract duration will be for a base ordering period of five (5) years. The NAICS code is 236220 and the small business size standard is $36.5 million.
This SB DB construction MATOC will be procured through a two phase design-build selection procedures as a request for proposal (RFP) with a total small business (SB) set aside that has been determined by the SBA that competition will be limited to eligible SB firms capable of participating in the CONUS, AK and HI locations. Other than SB participants are deemed ineligible to submit offers.
2.0 GENERAL PROCEDURES/REQUIREMENTS
PRELIMINARY REVIEW
Proposals shall describe the capability of the Offeror to perform the requirements of the Solicitation. Proposals should be specific and complete in every detail; and should be prepared simply and economically, providing a straightforward and concise description of capabilities to satisfactorily perform the requirements. Proposals should be practical, legible, clear, and coherent.
In order to effectively and equitably evaluate all proposals, the Procuring Contracting Officer must receive information containing sufficient detail to allow review and evaluation by the Government. The price proposals will be separated from the technical proposals. Technical proposals will be provided to the designated Technical Evaluation Team and Price Proposals will be provided to the designated Price Evaluation Advisors, with both teams under the direct guidance and oversight of Procuring Contracting Officer. Proposal clarity, organization, and cross-referencing are mandatory. Failure to submit and organize proposals as requested may adversely affect an Offeror's evaluation.
3.0 INTRODUCTION NOTICE TO OFFERORS
This section is designed to provide the offeror with instructions to complete and deliver a complete competitive proposal in response to this request for proposals (RFP). Oral proposals are not solicited for Phase one (I). The selection procedures to be used will be a two-phase approached IAW FAR Subpart
36.3. The two-phase selection procedure authorized under 10 U.S.C. 2305a allows Offerors to submit information related to specialized experience, technical competence, capability to perform, past performance, teaming arrangements and/or other information requested in Phase I. Based on information submitted in Phase I, the Source Selection Authority (SSA) will select no more than five (5) of the most qualified offerors to advance onto Phase two (II) in the competition and are subsequently invited to submit technical design products as part of the technical proposals for evaluation during Phase II.
All proposals must be complete and timely to be considered.
3.1 Acquisition Method:
The method of acquisition for this procurement considers the “Best Value” continuum, wherein a Best Value source selection process will be utilized in accordance with the Federal Acquisition Regulation (FAR) Subpart 15.101. Award will be made to the proposals that represents the best value to the Government as determined by the Source Selection Authority. In this acquisition method, evaluation and price trade off, if conducted, are highly subjective in nature. The proposal determined to be the Best Value may not be the lowest price or the highest technically rated proposal. The decision will involve a comparison and trade-off analysis of the combination of non-cost strengths, weaknesses, and risks, the evaluated cost/price offered in each proposal, and judgment as to which proposal provides the best combination. As a result Offerors must provide their best proposal with all required information in the required format. Information provided must be complete, clear and legible to obtain the best evaluation rating possible.
3.2. Contract Cost Ceiling Limitation for Design and Construction Costs:
The design and construction costs will be subject to the funds available for each Task Order. The current capacity for the design and construction cost for this five (5) year MATOC is $240M.
The total MATOC award shall not exceed the anticipated capacity amount of $240M for this contract. Offerors are notified that they are under no obligation to approach this ceiling. The Government will track capacity availability in order not to exceed the $240M.
3.3. The solicitation process is known as the “Request for Proposals” or the acronym:
“RFP”. Interested firms or joint venture entities (referred to as “Offerors”) may submit certain specified performance capability proposals, demonstrating their capability to successfully execute the contract resulting from this solicitation. The Government will evaluate the performance capability proposals in accordance with the criteria described herein.
3.4. The Government will evaluate the proposals, in accordance with the criteria described in Section 00 21 00 in the solicitation (and below, Evaluating Factors for Award), and award a firm-fixed-price design- build construction contract to the responsible offeror whose proposal conforms with all the terms and conditions of the solicitation and whose proposal is determined to represent the overall best value to the Government considering all factors, sub-factors, and price. Price will not be rated, but will be evaluated for reasonableness.
3.5. The proposal must describe the capability of the Offeror to perform the work, describe the Offeror’s understanding of the requirements contained in the solicitation and set forth full, accurate, and complete information as required by the Request for Proposals (RFP).
The proposal should be prepared simply and economically in the prescribed format and be complete, legible, clear and coherent.
3.6. The Government included Federal Acquisition Regulation (FAR) clause 52.215- 1(without Alternate I”, Instructions to Offerors, in this RFP. This clause states that the Government intends to make award based on initial offers, but reserves the right to conduct discussions with all Offerors determined to be part of the competitive range or those being selected to continue to Phase II, should the Source Selection Authority deem discussions necessary.
3.7. Oral Presentations:
The Government may conduct oral presentations after selection of Phase 2 Offerors.
Location, assigned dates and times for each potential offeror will be provided at a later date if it is determined oral presentations are necessary.
3.8. Offerors will not be participating in a sealed bid procurement process under this acquisition method. Issuance of this Request for Proposal does not constitute an award commitment on the part of the Government.
3.9 Contract Type:
An award of a firm-fixed-price design-build construction contract requiring delivery and installation is contemplated for this Acquisition.
4.0 PREPARING PROPOSALS
Proposal submittal information is located in each phase section (00 22 16).
5.0 GENERAL INSTRUCTIONS
Submit proposals initially on the most favorable terms from a price and technical standpoint. Do not assume that firms will be contacted or afforded an opportunity to clarify, discuss or revise their proposals. Submit one original proposals, three (3) hard copies of their proposal and three (3) CD/DVD electronic copies in .pdf format. Note that the Government will not evaluate any material that exceeds the page limits, where indicated below.
6.0 SUMMARY
6.1 Project Title: Indefinite Delivery/Indefinite Quantity (IDIQ), US Army
MEDCOM Medical Sustainment, Restoration and Modernization (MSRM) Program
6.2 Location: Continental United States (CONUS), Alaska (AK) and Hawaii (HI)
6.3 Proposed Contract Type: Multiple Award Task Order Contract Firm Fixed price.
6.4 Design-Build: Yes
6.5 Source Selection Process: Best Value, Trade-Off, IAW FAR 15.101-1
6.6 Firms Which Submitted Proposals: The RFP is Small Business Set-Aside
CLAUSES INCORPORATED BY FULL TEXT
52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)
(a) Definitions. As used in this provision--
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.
“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.
Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show--
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, or revision, of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government's interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(End of provision)
52.215-20 REQUIREMENTS FOR COST OR PRICING DATA OR INFORMATION OTHER THAN
CERTIFIED COST OR PRICING DATA (OCT 2010)
(a) Exceptions from certified cost or pricing data. (1) In lieu of submitting certified cost or pricing data, offerors may submit a written request for exception by submitting the information described in the following subparagraphs. The Contracting Officer may require additional supporting information, but only to the extent necessary to determine whether an exception should be granted, and whether the price is fair and reasonable.
(i) Identification of the law or regulation establishing the price offered. If the price is controlled under law by periodic rulings, reviews, or similar actions of a governmental body, attach a copy of the controlling document, unless it was previously submitted to the contracting office.
(ii) Commercial item exception. For a commercial item exception, the offeror shall submit, at a minimum, information on prices at which the same item or similar items have previously been sold in the commercial market that is adequate for evaluating the reasonableness of the price for this acquisition. Such information may include--
(A) For catalog items, a copy of or identification of the catalog and its date, or the appropriate pages for the offered items, or a statement that the catalog is on file in the buying office to which the proposal is being submitted. Provide a copy or describe current discount policies and price lists (published or unpublished), e.g., wholesale, original equipment manufacturer, or reseller. Also explain the basis of each offered price and its relationship to the established catalog price, including how the proposed price relates to the price of recent sales in quantities similar to the proposed quantities;
(B) For market-priced items, the source and date or period of the market quotation or other basis for market price, the base amount, and applicable discounts. In addition, describe the nature of the market;
(C) For items included on an active Federal Supply Service Multiple Award Schedule contract, proof that an exception has been granted for the schedule item.
(2) The offeror grants the Contracting Officer or an authorized representative the right to examine, at any time before award, books, records, documents, or other directly pertinent records to verify any request for an exception under this provision, and the reasonableness of price. For items priced using catalog or market prices, or law or regulation , access does not extend to cost or profit information or other data relevant solely to the offeror's determination of the prices to be offered in the catalog or marketplace.
(b) Requirements for certified cost or pricing data. If the offeror is not granted an exception from the requirement to submit certified cost or pricing data, the following applies:
(1) The offeror shall prepare and submit certified cost or pricing data, data other than certified cost or pricing data, and supporting attachments in accordance with the instructions contained in Table 15-2 of FAR 15.408, which is incorporated by reference with the same force and effect as though it were inserted here in full text. The instructions in Table 15-2 are incorporated as a mandatory format to be used in this contract, unless the Contracting Officer and the Contractor agree to a different format and change this clause to use Alternate I.
As soon as practicable after agreement on price, but before contract award (except for unpriced actions such as letter contracts), the offeror shall submit a Certificate of Current Cost or Pricing Data, as prescribed by FAR 15.406-2.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price (FFP) contract resulting from this solicitation.
52.216-27 SINGLE OR MULTIPLE AWARDS. (OCT 1995)
The Government may elect to award a single delivery order contract or task order contract or to award multiple delivery order contracts or task order contracts for the same or similar supplies or services to two or more sources under this solicitation.
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
The Contractor shall comply with the requirements of 29 CFR Part 3, which are hereby incorporated by reference in this contract.
(End of clause)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER
TRADE AGREEMENTS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American -- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested-- (i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT-- CONSTRUCTION MATERIALS (MAY
2014) - ALTERNATE I (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American-- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute or Balance shall submit the request with its offer, including the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from US Army Corps of Engineers Contracting Devision Attention: Donald P. Tam 700 West Capitol Ave, Room 7315 Little Rock, AR 72201-3225
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-28 PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997)
(a) Proposals must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a proposal must initial each erasure or change appearing on any proposal form.
(b) The proposal form may require offerors to submit proposed prices for one or more items on various bases, including--
(1) Lump sum price;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of paragraphs (b)(1) through (b)(3) of this provision.
(c) If the solicitation requires submission of a proposal on all items, failure to do so may result in the proposal being rejected without further consideration. If a proposal on all items is not required, offerors should insert the words “no proposal” in the space provided for any item on which no price is submitted.
(d) Alternate proposals will not be considered unless this solicitation authorizes their submission.
SECTION 00 22 16 - PHASE I PROPOSAL SUBMISSION REQUIRMENTS AND EVALUATION
CRITERIA
PHASE I
GENERAL REQUIREMENTS
1. INQUIRIES
OFFEROR'S QUESTIONS AND COMMENTS
Questions and/or comments relative to these documents should be submitted via e-mail to:
Contract Specialist – Primary POC
U.S. Army Corps of Engineers, Little Rock District
ATTN: Lakisha Vance
700 W. Capitol Ave, Rm 7315
Little Rock, AR 72201
Phone: 501-340-1264
Email: Lakisha.D.Vance@usace.army.mil
Bidder Inquiry
Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via:
Bidder Inquiry in ProjNet at http://www.projnet.org/projnet
To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page identified above, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.
From this page you may view all bidder inquiries or add inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W9127S19R6002
The Bidder Inquiry Key is: 6C8S9Y-83X7JW
The Phase I Review is open from 11 July 2019; 8:00am CT to 2 August 2019; 4:30pm CT.
The Bidder Inquiry System will be unavailable for new inquires ten (10) calendar days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award mailto:Lakisha.D.Vance@usace.army.mil http://www.projnet.org/projnet will NOT be available after receipt of proposals.
Oral explanations or instructions are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.
As this is a competitive negotiation acquisition, there is no public bid opening and no information will be given out as to the number of Offerors or the results of the competition until all awards are made.
2. DIRECTIONS FOR SUBMITTING PROPOSALS:
1. Proposal Submittals:
Submit proposals to:
CONTRACTING DIVISION
USACE, LITTLE ROCK (W9127S)
700 W. CAPITOL AVE, RM 7315
LITTLE ROCK AR 72201-3225
2. The Packaging:
The Proposals shall be marked:
Proposals for Solicitation Number: W9127S19R6002 -PHASE I- US ARMY MEDCOM MSRM, MATOC DB CONSTRUCTION SERVICES “DO NOT OPEN
Submission Deadline:
Offer Closing Date: 12 August 2019, Offer Closing Time: 2:00PM CT Proposals shall be received by the Corps of Engineers no later than the time and date specified.
3. Proposal Format
Phase 1 and 2 – General Definitions and Requirements
The following provide definitions and requirements that are common to both Phase 1 and Phase 2 proposals.
QUALITY. To provide effective and equitable evaluations of all proposals, the Procuring Contracting
Officer must receive information containing sufficient detail to allow review and evaluation by the
Government. Proposal clarity, organization, and cross-referencing are mandatory and represent the
Offeror’s ability to deliver contract materials that match these qualities. Failure to submit and organize proposals as requested will adversely affect an Offeror's evaluation.
COVER SHEET. A cover sheet identifying the Offeror (name, address, point of contact), project description, and solicitation number shall be provided. This sheet does is not to be numbered and does not count again sheet/page count limits. Only the information specified above is to be provided on this page, additional information, charts, data, figures, etc. will not be considered in evaluation.
TABLE OF CONTENTS (TOC). The proposal’s second sheet shall be a detailed TOC. The details shall be TAB and section titles and locations only. If more than one binder is used, the complete table of contents shall be included in each. Offers that violate these rules unnecessarily delay the evaluation process and may be rejected by the Government after the initial evaluation without receiving any further consideration. Only the information specified above is to be provided on the TOC page, additional information, charts, data, figures, etc. will not be considered in evaluation and may be cause for rejection.
The table of contents sheet is not to be numbered and does not count toward the page limitations.
TABS. Written proposal materials shall be submitted in standard three ring loose-leaf binders. Proposals shall be tabbed and labeled as specified in a manner to afford easy identification from a Table of
Contents. Provide all information in tabbed sections. Neither appendices nor attachments are permitted and will not be evaluated. Poor organization and clarity of contents violate these rules and unnecessarily delay the evaluation process. In this case, the proposal may be rejected by the Government after the initial evaluation without receiving any further consideration
FONT SIZE. Shall be normal spaced not be less than 10 point.
SHEET. A sheet refers to a physical piece of paper for printed hard copies. Unless instructed otherwise
(example, cover sheet), all sheets shall be dated and numbered.
PAGE. Page refers to a unit of content that may be printed on one side of a sheet of paper for hard copy.
PAGE LIMITS. Proposals shall not exceed the page limits described for proposal sections. Exceeding page limitations will result in truncation of the offending section and have a negative effect on content, clarity, quality evaluation.
SHEET-PAGE EXAMPLE. An 8 ½ x11 sheet of paper contains one (1) page of content if printed only on one side, or two (2) pages of content if printed front and back. So if a section’s limitation states 6 pages without any further guidance, the section may consist of 6 sheets of paper with printing on one side or 3 sheets of paper, double sided prints.
SHEET SIZE. Sheet shall be 8-1/2 inches x 11 inches. However, drawings, charts, or other graphics may be submitted, sheets no larger than 11 inches x 17 inches and folded to 8-1/2 inches x 11 inches. 11 x
17 inch sheet will be counted as two pages and can only be printed on one side.
NUMBER OF COPIES. Offerors shall submit an original and three (3) hard copies of their proposal and three (3) CD/DVD electronic copies in .pdf format.
ELECTRONIC SUBMISSIONS. If in the future a project under this MATOC requires, or the MATOC program changes to, electronic submissions only: a printed electronic submission must meet the requirements defined by sheet-page, sheet size, sheet numbers, and be legible to be accepted. Documents that require ‘view zooming’ for legibility will not be accepted. If a dispute arises, a printed copy on required page size will be the determinate of legibility.
PHASE 1
Proposal Submission Requirements, Evaluation Criteria and Basis of Award for Design-Build (D-
B) Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple-Award Task Order Contract
(MATOC) in support of U.S. Army Medical Command (MEDCOM) Medical
Sustainment,Restoration and Modernization (MSRM) Program
PHASE 1 - GENERAL REQUIREMENTS
U.S. Army Medical Command (MEDCOM) is responsible for managing the programming, planning, design, construction, outfitting and sustainment for their Maintenance, Repair, and Renewal program.
Under MEDCOM, the U.S. Army Health Facility Planning Agency (HFPA)/Assistant Chief of Staff for
Facilities (G9) through lower commands, Regional Health Commands or RHCs (Atlantic –A, Central – C, Pacific – P) direct this activity. The U.S. Corps of Engineers Little Rock District (CESWL) is part of the
USACE team that executes the program. CESWL supports Continental U.S. (CONUS) projects including those in Alaska and Hawaii.
The scope of work for the resultant MATOC contract will primarily be associated with the design, renovation/alteration of existing active medical and laboratory facilities, but may also include major repair and new construction.