W9124J-17-R-0006
ATTACHMENT #6
CLIN Structure
White Sands Missile Range, NM
4 January 2017
CLIN* Description Completion Date** Planned Award Schedule Contractor Proposed Price
CLIN 0001
(INFO)
Development of PMP and other General Project Plans.*
Completion of Required Project Plans
30 Days from task order award for Draft PMP, 30 days of receipt of comments for Final Initial PMP.
Total of 90 calendar days from Task Order Award
General Project Plans POP established in PMP IAW PWS
Completion of other general project plans driven by requirements for site specific CLINs and shall not impact performance of those CLINs.
Upon award of the task order Not Separately Priced
CLIN 0002
Conduct groundwater monitoring program at site WSMR-70 (sampling for calendar year 2018)
This is ER,A-funded
Completion of groundwater monitoring report.
POP 12 months to monitor plus 6 months for Report
Groundwater monitoring report – 30 June 2019.
Upon award of the task order
Optional CLIN 1002
Conduct groundwater monitoring program at site WSMR-70 (sampling for calendar year 2019)
This is ER,A-funded monitoring report.
Period of Performance (POP):
12 months to monitor plus 6 months for Report
Groundwater monitoring report – 30 June 2020.
NLT 30 November 2018
Optional CLIN 2002 monitoring program at site WSMR-70 (sampling for calendar year 2020) monitoring report.
POP 12 months to monitor plus 6 months for Report
Groundwater monitoring report – 30 June 2021.
NLT 30 November 2019
Optional CLIN 3002 monitoring program at site WSMR-70 (sampling for calendar year 2021)
This is ER,A-funded
Completion of groundwater monitoring report.
POP 12 months to monitor plus 6 months for Report
Groundwater monitoring report – 30 June 2022.
NLT 30 November 2020
CLIN 0003
RCRA Facility Investigation at
WSMR-33, WSMR-
60, WSMR-79
RFI report
Within 36 months of Task Order Award
Upon award of the task order
Optional CLIN 0004
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-33
Administrative complete determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of RFI Report for WSMR-33 under CLIN
Optional CLIN 0005
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-60
This is ER,A-funded
Administrative complete determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of RFI Report for WSMR-60 under CLIN
Optional CLIN 0006
Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-79
determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of RFI Report for WSMR-79 under CLIN
CLIN 0007
Accelerated Corrective Action at
WSMR-67
Final Report
Within 36 months of task order award
Upon task order award
Optional CLIN 0008
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-67
determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of Final Report for WSMR-67 under CLIN
CLIN 0009
Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR- 30,
WSMR-32, WSMR-
56, WSMR-58,
WSMR-73, WSMR-
81, WSMR-82,
CCWS-04
determination
Within 24 months from award of the task order
Upon task order award.
CLIN 0010
Implementation of approved Corrective Action Complete Petition with Controls for 12 months for WSMR-
30, WSMR-32,
WSMR-56, WSMR-
58, WSMR-73,
WSMR-81, WSMR-
82, CCWS-04
Final report on the implementation.
Within 12 months of approval of the Petition in CLIN 0009
NLT 60 days following COR approval of the Final CAC Petition.
CLIN 0011
Closure Report for
CCWS-71
This is CC-funded
LTM and Reporting
Within 48 months from award of the CLIN
Upon Task Order Award
CLIN 0012
CMRA
(INFO)
Perform CMR Reporting in according with the PWS
12 Months from Award of
CLIN
Upon Task Order Award Not Separately Priced
CLIN 1012
CMRA
(INFO)
Perform CMR Reporting in according with the PWS
12 Months from Award of
CLIN
12 Months from Award of CLIN
Not Separately Priced
CLIN 2012
CMRA
(INFO)
Perform CMR Reporting in according with the PWS
12 Months from Award of
CLIN
12 Months from Award of CLIN
Not Separately Priced
CLIN 3012
CMRA
(INFO)
Perform CMR Reporting in according with the PWS
12 Months from Award of
CLIN
12 Months from Award of CLIN
Not Separately Priced
CLIN 4012
CMRA
(INFO)
Perform CMR Reporting in according with the PWS
12 Months from Award of
CLIN
12 Months from Award of CLIN
Not Separately Priced
TOTAL $
*Note 1: The PMP shall be updated within 30 calendar days of anniversary of the award of the contract or more frequently if circumstances warrant an update.