ATTACHMENT__5_Past_Performance_Questionnaire_W9124J-17-R-0006_4_Jan_2017.doc

DOC document 45 KB Posted

Attached to
Environmental Remediation Multiple Award IDIQ FY18
Solicitation number
W9124J-17-R-0006
Issued by

About this file

ATTACHMENT #5 Past Performance Questionnaire W9124J-17-R-0006_4 JAN 2017

View the file

Other files

File Type Posted
ATTACHMENT__1_Basic_PWS_W9124J-17-R-0006_ERMA_IDIQ_FY18_REVISED_24_FEB_17.pdf PDF
AMENDMENT_0004_W9124J-17-R-0006_EMRA_IDIQ_FY18.pdf PDF
CONFORMED_SECTION_K_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
QUESTIONS_in_Response_to_AMENDMENT_0003_16_FEB_17-USG_RESPONSE_24_FEB_17_W9124J-17-R-0006_ERMA_IDIQ_FY18_.pdf PDF
ATTACHMENT__6_WSMR_LIVE_TO_CLIN_Structure_W9124J-17-R-0006_REVISED_15_Feb_2017.pdf PDF
ATTACHMENT__1_Basic_PWS_W9124J-17-R-0006_ERMA_IDIQ_FY18_REVISED_15_FEB_2017.pdf PDF
ATTACHMENT__4_SCA_Wage_Determination_W9124J-17-R-0006_ERMA_IDIQ_FY18_25Jan17_.pdf PDF
QUESTIONS_in_to_Response_AMENDMENT_0002_9_FEB_17-USG_RESPONSE_16_FEB_17_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
AMENDMENT_0003_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
RFP_5_JAN_2017_QUESTIONS-USG_RESPONSE_8_FEB_17_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
ATTACHMENT__6_WSMR_LIVE_TO_CLIN_Structure_W9124J-17-R-0006_REVISED_23_Jan_2017.pdf PDF
AMENDMENT_0002_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
ATTACHMENT__6_WSMR_LIVE_TO_CLIN_Structure_W9124J-17-R-0006_REVISED_23_Jan_2017_wTrackChanges.pdf PDF
ATTACHMENT__1_Basic_PWS_W9124J-17-R-0006_ERMA_IDIQ_FY18_REVISED_30_Jan_17.pdf PDF
AMENDMENT_0001_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
ATTACHMENT__2a_APPENDIX_A_WSMR_PRS_W9124J-17-R-0006_ERMA_IDIQ_FY18_4_Jan_2017.pdf PDF
ATTACHMENT__2b_APPENDIX_B_WSMR_ATOPSEC_W9124J-17-R-0006_ERMA_IDIQ_FY18_4_Jan_2017.pdf PDF
ATTACHMENT__4_SCA_Wage_Determination_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
ATTACHMENT__2c_APPENDIX_C_WSMR_Site_Summary_W9124J-17-R-0006_EMRA_IDIQ_FY18_4_Jan_2017.pdf PDF
ATTACHMENT__2_WSMR_PWS_W9124J-17-R-0006_ERMA_IDIQ_FY18_4_Jan_2017.pdf PDF
ATTACHMENT__1_Basic_PWS_W9124J-17-R-0006_ERMA_IDIQ_FY18_4_Jan_2017.pdf PDF
RFP_W9124J-17-R-0006_ERMA_IDIQ_FY18_5_JAN_2017.pdf PDF
ATTACHMENT__8_SAMPLE_FORMAT_Questions&Answers_W9124J-17-R-0006_ERMA_IDIQ_FY18.xlsx XLSX spreadsheet
ATTACHMENT__6_WSMR_LIVE_TASK_ORDER_CLIN_Structure_W9124J-17-R-0006_4_Jan_2017.pdf PDF
ATTACHMENT__3_QASP_W9124J-17-R-0006_ERMA_IDIQ_FY18_4_Jan_2017.pdf PDF
ATTACHMENT__7_Financial_Institution_Reference_Sheet_W9124J-17-R-0006_4_Jan_2017.docx DOCX document
WSMR_SITE_VISIT_1_and_2_NOV_2016_QUES_W9124J-17-R-0006_ERMA_IDIQ_FY18_USG_RESP_6_Dec_2016.pdf PDF
REVISED_DRAFT_RFP_W9124J-17-R-0006_ERMA_IDIQ_FY18_6_December_2016.pdf PDF
ATTACHMENT__2_REVISED_DRAFT_WSMR_PWS_W9124J-17-R-0006_ERMA_IDIQ_FY18_6_Dec_2016.pdf PDF
ATTACHMENT__6_REVISED_DRAFT_WSMR_CLIN_Structure_W9124J-17-R-0006_2_Dec_2016.pdf PDF
DRAFT_RFP_dated_4_Oct_2016_QUESTIONS-ANSWERS_16_Nov_2016_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
SITE_VISIT_SLIDES_Presented_1_Nov_2016_W9124J-17-R-0006_WSMR _NM_DRAFT_LIVE_TASK_ORDER.pdf PDF
SITE_VISIT_ATTENDEE_LIST_1_Nov_2016_and_2_Nov_2016_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
SITE_VISIT_INFORMATION_1_Nov_2016_and_2_Nov_2016_W9124J-17-R-0006_ERMA_IDIQ_FY18.pdf PDF
WSMR_SITE_VISIT_PARKING_AREA_Hwy70_to_Las_Cruces_Gate.pdf PDF
WSMR_SITE_VISIT_Routes_to_WSMR_Main_Post.pdf PDF
ATTACHMENT__2c_DRAFT_APPENDIX_C_WSMR_Site_Summary_W9124J-17-R-0006_ERMA_IDIQ_FY18_3_Oct_2016.pdf PDF
ATTACHMENT__2b_DRAFT_APPENDIX_B_WSMR_ATOPSEC_W9124J-17-R-0006_ERMA_IDIQ_FY18_3_Oct_2016.pdf PDF
DRAFT_RFP_W9124J-17-R-0006_ERMA_IDIQ_FY18_4_OCT_2016.pdf PDF
ATTACHMENT__8_SAMPLE_FORMAT_Questions Answers_W9124J-16-R-0071_ERMA_IDIQ_FY18.xlsx XLSX spreadsheet
ATTACHMENT__7_Financial_Institution_Reference_Sheet_W9124J-17-R-0006_23_Sep_2016.docx DOCX document
ATTACHMENT__4_SCA_Wage_Determination_W9124J-17-R-0006_ERMA_IDIQ_FY18.docx.pdf PDF
ATTACHMENT__5_DRAFT_Past_Performance_Questionnaire_W9124J-17-R-0006_23_Sep_2016.doc DOC document
ATTACHMENT__6_DRAFT_WSMR_CLIN_Structure_W9124J-17-R-0006_11_Apr_2016.pdf PDF
ATTACHMENT__2_DRAFT_WSMR_PWS_LIVE_TO_W9124J-17-R-0006_ERMA_IDIQ_FY18_3_Oct_2016.pdf PDF
ATTACHMENT__2a_DRAFT_APPENDIX_A_WSMR_PRS_W9124J-17-R-0006_ERMA_IDIQ_FY18_25_Feb_2016.pdf PDF
ATTACHMENT__3_DRAFT_QASP_W9124J-16-R-0071_ERMA_IDIQ_FY18_27_Sep_2016.pdf PDF
ATTACHMENT__1_DRAFT_Basic_PWS_W9124J-17-R-0006_ERMA_IDIQ_FY18_1_Sep_2016.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9124J-17-R-0006

ATTACHMENT #5

4 January 2017

INSTRUCTIONS TO THE REFERENCE FOR COMPLETING

THE PAST PERFORMANCE QUESTIONNAIRE

Handwritten completion of this questionnaire is acceptable, if legible.

Please include evaluation of Contractor's performance based solely on the performance for which the contractor was/is liable. Do not let factors beyond the control of the Contractor which have resulted in performance delays or other problems bias the evaluation of the contractor's performance. In completing the questionnaire please circle a letter corresponding to your rating, or "N/A" if you are unable to provide an evaluation for any area. Please provide clear and concise narrative explanations (both positive and negative) for your answers. This is especially important for any rating above or below “satisfactory”. If more space is needed than is provided, you may use the back of the questionnaire or attach additional sheets.

The following is a definition of the scoring system used:

Exceptional: Performance meets contractual requirements and exceeds many to the Owner’s benefit. The contractual performance of the element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good: Performance meets contractual requirements and exceeds some to the Owner’s benefit. The contractual performance of the element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Satisfactory: Performance meets contractual requirements. The contractual performance of the area being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal: Performance does not meet some contractual requirements. The contractual performance of the element being assessed evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

(To be completed and returned by the “Reference”)

I. CONTRACTOR/CONTRACT IDENTIFICATION

a) Contractor (Company/Division):

b) Contract Number/Identification:

c) Contract Title (Brief Description of Work and Location):

d) Contract Type:

e) Owner: Federal/State/Local Government or Private/Commercial

f) Period of Performance:

g) Original Dollar Amount of Contract:

h) Number of Modifications:

i) Dollar Amount at Completion (or current amount, if not complete):

II. PAST PERFORMANCE/QUALITY EVALUATION:

Quality of Product or Service - Assess the contractor’s conformance to contract requirements, specifications and standards of good workmanship (e.g., commonly accepted technical, professional, environmental, or safety and health standards):

EX FORMCHECKBOX

VG FORMCHECKBOX

S FORMCHECKBOX

M FORMCHECKBOX

UNSAT FORMCHECKBOX

N/A FORMCHECKBOX

Comments:

Schedule - Assess the timeliness of the contractor against the completion of the contract, task orders, milestones, delivery schedules, administrative requirements and overall responsiveness (e.g., efforts that contribute to or effect the schedule variance):

EX FORMCHECKBOX

VG FORMCHECKBOX

S FORMCHECKBOX

M FORMCHECKBOX

UNSAT FORMCHECKBOX

N/A FORMCHECKBOX

Comments:

Business Relationships - Assess the integration and coordination of all activity needed to execute the contract, specifically the timeliness, completeness and quality of problem identification, corrective actions plans, proposal submittals, the contractor’s history of reasonable and cooperative behavior, customer satisfaction, and the timely award and management of subcontracts. Additionally, please comment as to whether the contractor met small/small disadvantaged and women-owned business participation goals:

EX FORMCHECKBOX

VG FORMCHECKBOX

S FORMCHECKBOX

M FORMCHECKBOX

Technical Competence - Assess the knowledge of, and skill in the exercise of, practices required for successful completion of the contract (understanding of laws, regulations, and procedures):

EX FORMCHECKBOX

VG FORMCHECKBOX

S FORMCHECKBOX

M FORMCHECKBOX

Describe any significant strong points:

Describe any significant weak points:

If you had a choice, would you use this company again? Yes No

Explain:

Other contacts that may be able to furnish past performance information:

(TO BE COMPLETED AND RETURNED BY THE REFERENCE.)

***YOUR NAME WILL NOT BE RELEASED OUTSIDE OF THE GOVERNMENT***

A. Name of Evaluator:

B. Title:

C. Telephone Number:

D. Company/Organization:

E. Position held in reference to the contract (Technical Inspector, Contract Administrator, etc.):

F. Length of involvement in contract:

G. Was the contractor given the opportunity to respond to all adverse past performance information?

Yes No Not Applicable Unknown

Explain:

H. Date questionnaire completed/information provided:

I. If the information was submitted in writing, the signature of the respondent:

J. If the information was obtained telephonically, the signature(s) of the government representative(s) documenting the phone call: