DRAFT RFP W9124J-17-R-0006
ATTACHMENT #6
CLIN Structure
White Sands Missile Range, NM
11 APRIL 2016
CLIN* Description Completion Date** Planned Award Schedule Contractor Proposed Price
CLIN 0001
Development of PMP and other General Project Plans. *
Conduct groundwater monitoring program at site WSMR-70 (sampling for calendar year 2018)
This is ER,A-funded
Completion of Required Project Plans
Completion of groundwater monitoring report.
30 Days from task order award for Draft PMP, 30 days of receipt of comments for Final Initial PMP.
Completion of other general project plans driven by requirements for site specific CLINs and shall not impact performance of those CLINs.
Groundwater monitoring report – 30 June 2019.
Upon award of the task order
Optional CLIN 1001
Annual revision of
PMP*
Conduct groundwater monitoring program at site WSMR-70 (sampling for calendar year 2019)
Completion of revised PMP
Completion of groundwater monitoring report.
30 Days from task order award for Draft PMP, 30 days of receipt of comments for Final Initial PMP.
Groundwater monitoring report – 30 June 2020.
NLT 30 November 2018
This is ER,A-funded
Optional CLIN 2001
Annual revision of
PMP*
Conduct groundwater monitoring program at site WSMR-70 (sampling for calendar year 2020)
This is ER,A-funded
Completion of revised PMP
Completion of groundwater monitoring report.
30 Days from task order award for Draft PMP, 30 days of receipt of comments for Final Initial PMP.
Groundwater monitoring report – 30 June 2021.
NLT 30 November 2019
Optional CLIN 3001
Annual revision of
PMP*
Conduct groundwater monitoring program at site WSMR-70 (sampling for calendar year 2021)
This is ER,A-funded
Completion of revised PMP
Completion of groundwater monitoring report.
30 Days from task order award for Draft PMP, 30 days of receipt of comments for Final Initial PMP.
Groundwater monitoring report – 30 June 2022.
NLT 30 November 2020
CLIN 0002
RCRA Facility Investigation at
Completion of RFI report
Within 36 months of Task Order Award
Upon award of the task order
WSMR-33, WSMR-
60, WSMR-79
This is ER,A-funded
Optional CLIN 0003
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-33
This is ER,A-funded
Administrative complete determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of RFI Report for WSMR-33 under CLIN
Optional CLIN 0004
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-60
This is ER,A-funded
Administrative complete determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of RFI Report for WSMR-60 under CLIN
Optional CLIN 0005
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-79
This is ER,A-funded
Administrative complete determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of RFI Report for WSMR-79 under CLIN
CLIN 0006
Accelerated Corrective Action at
WSMR-67
This is ER,A-funded
Completion of Final Report
Within 36 months of task order award
Upon task order award
Optional CLIN 0007
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR-67
This is ER,A-funded
Administrative complete determination
Within 24 months from award of the CLIN
May be exercised no later than 60 days of COR approval of Final Report for WSMR-67 under CLIN
CLIN 0008
Corrective Action Complete (CAC) Petition per RCRA permit through administrative complete determination for
WSMR- 30,
WSMR-32, WSMR-
56, WSMR-58,
WSMR-73, WSMR-
81, WSMR-82,
CCWS-04
This is ER,A-funded
Administrative complete determination
Within 24 months from award of the task order
Upon task order award.
CLIN 0009
Implementation of approved Corrective Action Complete Petition with Controls for 12 months for WSMR-
30, WSMR-32,
WSMR-56, WSMR-
58, WSMR-73,
WSMR-81, WSMR-
82, CCWS-04
This is ER,A-funded
Final report on the implementation.
Within 12 months of approval of the Petition in CLIN 0008
NLT 60 days following COR approval of the Final CAC Petition.
CLIN 0010
Closure Report for
CCWS-71
This is CC-funded
Completion of LTM and Reporting
Within 48 months from award of the CLIN
Upon task order award
TOTAL $
*Note 1: The PMP shall be updated within 30 calendar days of anniversary of the award of the contract or more frequently if circumstances warrant an update.