Specification Date 15 February 2019
ONE UNIT STATION TRAINING – ARMOUR
(OUST-AR)
RANGE PROJECT #2 OSCAR 5
Fort Benning, Georgia
Prepared by:
Engineering Division, DPW 6650 Meloy Drive, Building 6 Fort Benning, GA 31905
Specifications Prepared by:
| Architectural | C. Craig Davis R.A. |
| DIRECTORATE OF PUBLIC WORKS |
ENGINEERING DIVISION
FORT BENNING, GEORGIA
Project #: AROO2
PROJECT TABLE OF CONTENTS DIVISION 01 - GEN ERAL REQUIREMENTS
SUMMARY OF WORK
PROJECT SCHEDULE
| 01 |
| 33 |
| 00 |
SUBMITTAL PROCEDURE
| 01 |
| 35 |
| 29 |
SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
| 01 |
| 42 |
| 00 |
SOURCES FOR REFERENCE PUBLICATIONS
| 01 |
| 45 |
| 01 |
QUALITY CONTROL
| 01 |
| 50 |
| 00 |
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
| 01 |
| 50 |
| 61 |
DUST CONTROL
| 01 |
| 57 |
| 20.00 |
| 10 |
| ENVIRONMENTAL PROTECTION |
| 01 |
| 57 |
| 23.00 |
| 10 |
| STORM WATER POLLUTION PREVENTION MEASURES |
| 01 |
| 62 |
| 35 |
RECYCLED/ RECOVERED MATERIALS
| 01 |
| 74 |
| 19 |
CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
| 01 |
| 78 |
| 02.00 |
| 10 |
| CLOSEOUT SUBMITTALS |
| 01 |
| 78 |
| 23 |
OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
| 02 41 |
| 00 |
DEMOLITION
| 02 84 |
| 16 |
PCB BALLASTS, TRANSFORMERS AND HAZARDOUS WASTE LAMP REMOVAL AND RECYLING
DIVISION 03 - CONCRETE
| 03 |
| 11 |
| 13.00 |
| 10 |
| STRUCTURAL CONCRETE FORMWORK |
| 03 |
| 15 |
| 13.00 |
| 10 |
| EXPANSION JOINTS, CONTRACTION JOINTS, AND WATERSTOPS |
| 03 |
| 20 |
| 01.00 |
| 10 |
| CONCRETE REINFORCEMENT |
| 03 |
| 31 |
| 00.00 |
| 10 |
| CAST - IN -PLA CE STRUCTURAL CONCRETE |
DIVISION 04 – MASONRY
04 20 00 MASONRY
04 21 13.13 NONBEARING MASONRY VENEER/STEEL STUD WALLS
DIVISION 05 - METALS
| 05 05 |
| 23 |
WELDING, STRUCTURAL
| 05 12 |
| 00 |
STRUCTURAL STEEL
| 05 21 |
| 19 |
OPEN WEB STEEL JOIST FRAMING
| 05 30 |
| 00 |
STEEL DECKS
| 05 50 |
| 13 |
MISCELLANEOUS METAL FABRICATIONS
| 05 51 |
| 00 |
METAL STAIRS
| 05 52 |
| 00 |
METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
| 06 20 00 FINISH CARPENTRY |
| 06 41 16.00 10 LAMINATE CLAD ARCHITECTURAL CASEWORK |
06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS
15 FEBUARY 2018
OUST-IN RANGE PROJECTS
Fort Benning, Georgia
PROJECT TABLE OF CONTENTS Page 5
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
| 07 21 13 | BOARD AND BLOCK INSULATION |
| 07 21 16 | MINERAL FIBER BLANKET INSULATION |
| 07 25 00.00 06 | BUILDING AIR BARRIER SYSTEM |
| 07 27 26 | FLUID APPLIED AIR AND MOISTURE BARRIER |
07 42 13 METAL WALL PANELS
| 07 60 00 | FLASHING AND SHEET METAL |
| 07 61 14.00 20 | STEEL STANDING SEAM ROOFING |
| 07 84 00 | FIRESTOPPING |
| 07 92 00 | JOINT SEALANTS |
DIVISION 08 - OPENINGS
| 08 11 13 | STEEL DOORS AND FRAMES |
| 08 33 13 | METAL ROLLING COUNTER DOORS |
| 08 14 00 | WOOD DOORS |
| 08 51 13 | ALUMINUM WINDOWS |
| 08 71 00 | DOOR HARDWARE |
| 08 81 00 | GLAZING |
| 08 91 00 | METAL WALL LOUVERS |
DIVISION 09 - FINISHES
| 09 22 00 | METAL SUPPORT ASSEMELIES |
| 09 29 00 | GYPSUM BOARD |
| 09 51 00 | ACOUSTICAL CEILINGS |
| 09 65 00 | RESILIENT FLOORING |
| 09 68 00 | CARPET |
| 09 90 00 | PAINTS AND COATINGS |
DIVISION 10 - SPECIALTIES
| 10 10 00 | VISUAL COMMUNICATIOKS SPECIALTIES |
| 10 14 02 | INTERIOR SIGNAGE |
10 22 13 WIRE MESH PARTITIONS
10 44 16 FIRE EXTINGUISHER CABINETS
DIVISION 11 – REFURBISHED EQUIPMENT
11 42 13 FOOD SERVING TABLES
DIVISION 12 - FURNISHINGS
| 12 24 13 |
| 12 48 13.13 |
ROLLER WINDOW SHADES
ENTRANCE FLOOR MATS
DIVISION 13 – SPECIAL CONSTRUCTION
| 13 12 05 | METAL ANGLE FRAMED BLEACHERS |
| 13 34 19 | METAL BUILDING SYSTEMS |
DIVISION 14 - Not Used
DIVISION 21 – Not Used
DIVISION 22 – Not Used
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
| 23 |
| 00 |
| 00.00 |
| 40 |
| GENERAL MECHANICAL PROVISIONS |
| 23 |
| 00 |
| 00 |
AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
| 23 |
| 05 |
| 93 |
TESTING, ADJUSTING, AND BALANCING FOR HVAC
| 23 |
| 07 |
| 00 |
THERMAL INSULATION FOR MECHANICAL SYSTEMS
| 23 |
| 08 |
| 00 |
COMMISSIONING OF HVAC SYSTEMS
| 23 |
| 23 |
| 00 |
REFRIGERANT PIPING
| 23 |
| 34 |
| 23 |
POWER VENTILATORS
| 23 |
| 36 |
| 00 |
AIR TERMINAL UNITS
| 23 |
| 37 |
| 13 |
DIFFUSERS, REGISTERS, AND GRILLS
| 23 |
| 82 |
| 02.00 |
| 10 |
| UNITARY HEATING AND COOLING EQUIPMENT |
DIVISION 25 - Not Used DIVISION 26 - ELECTRICAL
| 26 |
| 00 |
| 00 |
BASIC ELECTRICAL MATERIALS AND METHODS
| 26 |
| 20 |
| 00 |
INTERIOR DISTRIBUTION SYSTEM
| 26 |
| 28 |
| 01.00 |
| 10 |
| COORDINATED POWER SYSTEM PROTECTION |
| 26 |
| 41 |
| 01.00 |
| 10 |
| LIGHTNING PROTECTION SYSTEM |
| 26 |
| 51 |
| 00 |
INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00
BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
| 31 00 00 |
| EARTHWORK |
| 31 11 00 |
| CLEARING AND GRUBBING |
| 31 23 00 |
| ECAVATION AND FILL |
| 31 31 16 |
| SOIL TREATMENT FOR SUBTERRANEAN TERMITE CONTROL |
| 31 32 11 |
| SOIL SURFACE EROSION CONTROL |
DIVISION 32 - EXTERIOR IMPROVEMENTS
| 32 0119 | FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIDGID PAVEMENTS | |
| 32 05 33 | LANDSCAPE ESTABLISHMENT | |
| 32 11 23 | AGGREGATE BASE COURSE | |
| 32 13 13.06 | PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE FACILITIES | |
| 32 15 00 | AGGREGATE SURFACE COURSE | |
| 32 17 24.00 10 | PAVEMENT MARKINGS | |
| 32 31 13.53 | HIGH -S ECURITY CHAIN LINK FENCES AND GATES | |
| 32 92 19 | SEEDING |
33 40 00 STORM DRAINAGE UTILITIES
- - End of Project Table of Contents - -