ARMOR_OSUT_1_-_5_Pre_Award_Addendum_1.pdf
PDF 4 MB Posted
- Attached to
- Armor OSUT 2 Federal contract opportunity
- Solicitation number
- W911SF-19-R-0020
About this file
Pre Award Addendum
View the file
Other files for this federal contract opportunity
Show all 50
Armor OSUT 2 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1of [3]
PRE AWARD AMENDMENTS
for ARMOR OSUT PROJECTS
SCOPE OF WORK
17 JULY 2019
ARMOR OSUT, FORT BENNNING, GA
Date of Issue: 17 July 2019
The information provided in these pre award amendments come in the form of a requirement by the User (Range Division) to the Government regarding the work described below.
This pre award addendum is issued as a requirement by PEO-STRI who performed a site visit to access the project. It was their observation and recommendation to incorporate these additional items for the long term sustainability. This proposal should be accepted by the Government, as an addition to current infrastructure, and serves as a notice to proceed with the change in design and scope of work. The contractor shall provide all labor, supervision, material and equipment to perform the following items of work. The Contractor will provide 100% design work for the additional scope of work associated with Armor OUST projects 1 thru 5.
Part I Drawings:
Item 1) The overall architectural style and design features (dimensions, construction details, building elevations and floor plans) will match the design intent of the original drawings and scope of work as issued and as described in the bid documents.
Item 2) Drawings include two ammo points (single) with fencing, 20 amp re-established electrical services at the firing lines and barrow pits locations.
Part II Scope of Work:
Item 1) The amendments shall incorporate and provide the following specifics in addition to the original design intent:
a) Armor OSUT Projects #1 thru #5 - The firing position must be constructed in accordance with Huntsville Range Design Guide and minimum target exposure along line of sight in accordance with U.S. Army Training Circular 25-8.
b) Armor OSUT Projects #1, #2, and #3 - Onsite borrow is available for Armor OSUTs 1, 2, and 3. For Armor OSUT 1 the borrow will be available from Oscar 15. For Armor OSUT 2 the borrow will be available from Oscar 5. For Armor OSUT 3 the borrow will be available from Oscar
11. See attached drawings for intended areas on each site. The
Page 2of [3] for ARMOR OSUT PROJECTS contractor will have to provide a separate NOI for a borrow area and provide final stabilization for NOT for that borrow area. The end state of the borrow area must be graded to drain. The contractor must provide a survey for the area once complete.
c) Armor OSUT Project #1 - Oscar range 15 (Lafayette Pool): Contractor shall construct a new ammo point (single) next to the existing ammo point building so that both buildings are within +/-8’-0” between the two. See attached drawing for details and a new fence layout.
d) Armor OSUT Project #1 - Oscar range 14 (Stevon Booker): Contractor shall construct a new ammo point (single) next to the existing ammo point building so that both buildings are within +/-8’-0” between the two. See attached drawing for details and a new fence layout.
e) Armor OSUT Project #3 - Omit all Electrical SOW from Oscar 3 range.
f) Armor OSUT Project #3 – Oscar ranges 12, 9, 7, 6, and Simpson receiving an updated electrical SOW. The attached weatherproof enclosure is an example or Contractor can provide something equal. See attached SOW and data sheet.
g) Armor OSUT Project #5 - The server and rack shall be removed from the existing tower and relocated fully in the new tower upon completion. The existing tower will remain fully operational until the new tower is finished.
For Electrical:
1. Upon completion of the new tower, contractor shall relocate all the existing downrange power cables from the existing tower to the new tower.
2. Contractor shall provide and install the same amount of the power service and panelboards to the new tower as the existing tower.
For Communications:
1. Upon completion of the new tower, contractor shall relocate all the existing downrange fiber optic cables from the existing tower to the new tower.
a) If possible to remove all of the Outside Plant Fiber out of the two and tag how everything is connected.
b) If you cannot remove all of the outside Plant Fiber you will need a minimum of 60 feet of the original OSP fiber to splice on to the new fiber. Provide and install a manhole and run new ducts from the manhole to the new tower.
c) Remember it is important to document as much as possible how the fiber is connected/ran so that someone will not
Page 3of [3] for ARMOR OSUT PROJECTS have to shoot a laser out each strand to trace everything out.
2. Contractor shall coordinate with the government to relocate the existing NEC network fiber optic device (if present) from the existing control tower to the new control tower. Contractor to provide backboard for NEC to mount equipment. Note: NEC does not support fiber connections from targets to tower server.
3. Contractor shall relocate all telecommunications equipment from the existing control tower to the new control tower.
4. Reference: Fort Benning
a. NEC Telecommunications & network Installation
Specifications dated 07/15/2016 (see attached document)
b. UFC 3-501-01
c. UFC 3-580-01
Item 2) Attachments:
1. 44026 Morris Oscar 5 Nad 83 Site Plan Model Amended 12 July 2019
2. 44026 Steindam Oscar 11 Nad 83 Grading Plan Model Amended 12 July
3. Lafayette Pool Oscar 15 Nad 83 Grading Plan Sheet 1 Amended 12 July
4. Ammo Point + Fence Layout
5. Statement of Work - Oscar 6 Electrical_Amended 12 July 2019
6. Statement of Work - Oscar 7 Electrical_Amended 12 July 2019
7. Statement of Work - Oscar 9 Electrical_Amended 12 July 2019
8. Statement of Work - Oscar 12 Electrical_Amended 12 July 2019
9. Statement of Work - Simpson Electrical_Amended 12 July 2019
10. Example NEMA box at each firing position: Weatherproof Enclosure Date
Sheet
11. Fort Benning’s NEC Telecommunications and Network Installation
Specifications dated 07/15/2016
End of Pre Award Amendment
Project: AR OSUT – Add receptacles in Oscar 6 (McBryar) Range
26 Electrical
i) Electrical Guidelines (New Work):
The electrical new work shall comply with the design criteria specified in Technical Instructions TI 800- 01 Design Criteria, TI 800-03 Technical Requirements for Design-Build, TI 811-16 Lighting Design;
Technical Manual TM 5-811-1 Electric Power Supply and Distribution, TM 5-811-2 Electrical Design - Interior Electrical System, UFC 3-501-01, UFC 3-550-03FA, NFPA 70, IEEE C2, ANSI/ICEA S-94-649, TIA/EIA 568-B, and National Electrical Codes (NEC) and all referenced documents.
1. Existing electrical power system and/or existing transformer in the Oscar 6 Range shall remain in place. Contractor must verify and/or determine that the existing power distribution system and/or existing transformer has sufficient current capacity for the additional loads. Upgrade the existing power distribution system and/or existing transformer if needed.
2. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 1 and 2. Install the new panelboard in the new mounting rack at the center between firing lanes 1 and 2, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
3. Provide and install surge protection device(s) on each panelboard.
4. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 1 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 1 platform.
5. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 2 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 2 platform.
6. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 3 and 4. Install the new panelboard in the new mounting rack at the center between firing lanes 3 and 4, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
7. Provide and install surge protection device(s) on each panelboard.
8. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 3 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 3 platform.
9. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 4 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 4 platform.
10. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 5 and 6. Install the new panelboard in the new mounting rack at the center between firing lanes 5 and 6, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
11. Provide and install surge protection device(s) on each panelboard.
12. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 5 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 5 platform.
13. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 6 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 6 platform.
14. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 7 and 8. Install the new panelboard in the new mounting rack at the center between firing lanes 7 and 8, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
15. Provide and install surge protection device(s) on each panelboard.
16. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 7 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 7 platform.
17. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 8 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 8 platform.
18. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 9 and 10. Install the new panelboard in the new mounting rack at the center between firing lanes 9 and 10, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
19. Provide and install surge protection device(s) on each panelboard.
20. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 9 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 9 platform.
21. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 10 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 10 platform.
22. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 11 and 12. Install the new panelboard in the new mounting rack at the center between firing lanes 11 and 12, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
23. Provide and install surge protection device(s) on each panelboard.
24. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 11 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 11 platform.
25. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 12 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 12 platform.
26. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 13 and 14. Install the new panelboard in the new mounting rack at the center between firing lanes 13 and 14, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
27. Provide and install surge protection device(s) on each panelboard.
28. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 13 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 13 platform.
29. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 14 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 14 platform.
30. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 15 and 16. Install the new panelboard in the new mounting rack at the center between firing lanes 15 and 16, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
31. Provide and install surge protection device(s) on each panelboard.
32. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 15 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 15 platform.
33. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 16 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from
16 platform.
Project: AR OSUT – Add receptacles in Oscar 7 (FOWLER) Range
The electrical new work shall comply with the design criteria specified in Technical Instructions TI 800- 01 Design Criteria, TI 800-03 Technical Requirements for Design-Build, TI 811-16 Lighting Design;
Technical Manual TM 5-811-1 Electric Power Supply and Distribution, TM 5-811-2 Electrical Design - Interior Electrical System, UFC 3-501-01, UFC 3-550-03FA, NFPA 70, IEEE C2, ANSI/ICEA S-94-649, TIA/EIA 568-B, and National Electrical Codes (NEC) and all referenced documents.
1. Existing electrical power system and/or existing transformer in the Oscar 7 Range shall remain in place. Contractor must verify and/or determine that the existing power distribution system and/or existing transformer has sufficient current capacity for the additional loads. Upgrade the existing power distribution system and/or existing transformer if needed.
2. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 1 and 2. Install the new panelboard in the new mounting rack at the center between firing lanes 1 and 2, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
3. Provide and install surge protection device(s) on each panelboard.
4. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 1 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 1 platform.
5. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 2 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 2 platform.
6. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 3 and 4. Install the new panelboard in the new mounting rack at the center between firing lanes 3 and 4, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
7. Provide and install surge protection device(s) on each panelboard.
8. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 3 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from
NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 4 platform.
10. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 5 and 6. Install the new panelboard in the new mounting rack at the center between firing lanes 5 and 6, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
11. Provide and install surge protection device(s) on each panelboard.
12. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 5 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 5 platform.
13. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 6 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 6 platform.
14. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 7 and 8. Install the new panelboard in the new mounting rack at the center between firing lanes 7 and 8, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
15. Provide and install surge protection device(s) on each panelboard.
16. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 7 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 7 platform.
17. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 8 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 8 platform.
18. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 9 and 10. Install the new panelboard in the new mounting rack at the center between firing lanes 9 and 10, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the
NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 9 platform.
21. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 10 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 10 platform.
22. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 11 and 12. Install the new panelboard in the new mounting rack at the center between firing lanes 11 and 12, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
23. Provide and install surge protection device(s) on each panelboard.
24. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 11 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 11 platform.
25. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 12 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 12 platform.
26. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 13 and 14. Install the new panelboard in the new mounting rack at the center between firing lanes 13 and 14, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
27. Provide and install surge protection device(s) on each panelboard.
28. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 13 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 13 platform.
29. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 14 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 14 platform.
existing transformer and/or from the main distribution panelboard inside the tower.
31. Provide and install surge protection device(s) on each panelboard.
32. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 15 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 15 platform.
33. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 16 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from
Project: AR OSUT – Add receptacles in Oscar 9 (PULASKI) Range
The electrical new work shall comply with the design criteria specified in Technical Instructions TI 800- 01 Design Criteria, TI 800-03 Technical Requirements for Design-Build, TI 811-16 Lighting Design;
Technical Manual TM 5-811-1 Electric Power Supply and Distribution, TM 5-811-2 Electrical Design - Interior Electrical System, UFC 3-501-01, UFC 3-550-03FA, NFPA 70, IEEE C2, ANSI/ICEA S-94-649, TIA/EIA 568-B, and National Electrical Codes (NEC) and all referenced documents.
1. Existing electrical power system and/or existing transformer in the Oscar 9 Range shall remain in place. Contractor must verify and/or determine that the existing power distribution system and/or existing transformer has sufficient current capacity for the additional loads. Upgrade the existing power distribution system and/or existing transformer if needed.
2. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 1 and 2. Install the new panelboard in the new mounting rack at the center between firing lanes 1 and 2, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
3. Provide and install surge protection device(s) on each panelboard.
4. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 1 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 1 platform.
5. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 2 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 2 platform.
6. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 3 and 4. Install the new panelboard in the new mounting rack at the center between firing lanes 3 and 4, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
7. Provide and install surge protection device(s) on each panelboard.
8. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 3 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from
NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 4 platform.
10. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 5 and 6. Install the new panelboard in the new mounting rack at the center between firing lanes 5 and 6, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
11. Provide and install surge protection device(s) on each panelboard.
12. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 5 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 5 platform.
13. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 6 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 6 platform.
14. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 7 and 8. Install the new panelboard in the new mounting rack at the center between firing lanes 7 and 8, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
15. Provide and install surge protection device(s) on each panelboard.
16. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 7 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 7 platform.
17. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 8 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 8 platform.
18. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 9 and 10. Install the new panelboard in the new mounting rack at the center between firing lanes 9 and 10, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the
NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 9 platform.
21. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 10 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 10 platform.
22. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 11 and 12. Install the new panelboard in the new mounting rack at the center between firing lanes 11 and 12, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
23. Provide and install surge protection device(s) on each panelboard.
24. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 11 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 11 platform.
25. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 12 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 12 platform.
26. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 13 and 14. Install the new panelboard in the new mounting rack at the center between firing lanes 13 and 14, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
27. Provide and install surge protection device(s) on each panelboard.
28. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 13 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 13 platform.
29. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 14 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 14 platform.
existing transformer and/or from the main distribution panelboard inside the tower.
31. Provide and install surge protection device(s) on each panelboard.
32. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 15 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 15 platform.
33. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 16 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from
Project: AR OSUT – Add receptacles in Oscar 12 (BAUM) Range
The electrical new work shall comply with the design criteria specified in Technical Instructions TI 800- 01 Design Criteria, TI 800-03 Technical Requirements for Design-Build, TI 811-16 Lighting Design;
Technical Manual TM 5-811-1 Electric Power Supply and Distribution, TM 5-811-2 Electrical Design - Interior Electrical System, UFC 3-501-01, UFC 3-550-03FA, NFPA 70, IEEE C2, ANSI/ICEA S-94-649, TIA/EIA 568-B, and National Electrical Codes (NEC) and all referenced documents.
1. Existing electrical power system and/or existing transformer in the Oscar 12 Range shall remain in place. Contractor must verify and/or determine that the existing power distribution system and/or existing transformer has sufficient current capacity for the additional loads. Upgrade the existing power distribution system and/or existing transformer if needed.
2. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 1 and 2. Install the new panelboard in the new mounting rack at the center between firing lanes 1 and 2, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
3. Provide and install surge protection device(s) on each panelboard.
4. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 1 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 1 platform.
5. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 2 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 2 platform.
6. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 3 and 4. Install the new panelboard in the new mounting rack at the center between firing lanes 3 and 4, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
7. Provide and install surge protection device(s) on each panelboard.
8. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 3 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from
NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 4 platform.
10. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 5 and 6. Install the new panelboard in the new mounting rack at the center between firing lanes 5 and 6, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
11. Provide and install surge protection device(s) on each panelboard.
12. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 5 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 5 platform.
13. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 6 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 6 platform.
14. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 7 and 8. Install the new panelboard in the new mounting rack at the center between firing lanes 7 and 8, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
15. Provide and install surge protection device(s) on each panelboard.
16. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 7 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 7 platform.
17. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 8 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 8 platform.
18. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 9 and 10. Install the new panelboard in the new mounting rack at the center between firing lanes 9 and 10, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the
NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 9 platform.
21. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 10 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 10 platform.
22. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 11 and 12. Install the new panelboard in the new mounting rack at the center between firing lanes 11 and 12, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
23. Provide and install surge protection device(s) on each panelboard.
24. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 11 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 11 platform.
25. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 12 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 12 platform.
26. Provide and install a new 120/240V, 100A, single-phase panelboard with 18 circuit spaces between firing lanes 13 and 14. Install the new panelboard in the new mounting rack at the center between firing lanes 13 and 14, and ten (10) feet behind the firing point. Obtain the underground secondary power service in PVC conduit(s) to the new panelboard from the existing transformer and/or from the main distribution panelboard inside the tower.
27. Provide and install surge protection device(s) on each panelboard.
28. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 13 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 13 platform.
29. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 14 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 14 platform.
existing transformer and/or from the main distribution panelboard inside the tower.
31. Provide and install surge protection device(s) on each panelboard.
32. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 15 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from the new 100A panelboard to the four (4) receptacles inside the NEMA 4X enclosure in firing lane 15 platform.
33. Provide and install NEMA 4X, weatherproof enclosure with the new mounting rack next to the firing lane 16 platform. Provide and install four (4) 120V, 20A GFCI duplex receptacles inside the NEMA 4X enclosure. Provide the underground secondary power cables in PVC conduits from
Type 3, 3R, 4, 4X BoXes and enclosuRes Hinge-Cover Type 3r enClosures nVent.com/HOFFMANSUBJECT TO CHANGE WITHOUT NOTICEcommeRcial1 Spec-00266 H
Spec-00266
Hinge-coveR, medium, Type 3R indusTRy sTandaRds UL 50, 50E Listed; Type 3R; File No. E27567 cUL Listed per CSA C22.2 No 94; Type 3R File No. E27567
NEMA/EEMAC Type 3R
IEC 60529, IP32
applicaTion These enclosures have a size range of 16 x 12 x 6-in. to 48 x 36 x 16-
in. and meet basic functionality requirements for applications that require protection from rain, sleet, snow or dripping water.
FeaTuRes
• Drip shield top and seam-free sides, front, and back protect from rain, snow, or sleet
| • | 16 gauge plated steel continuous hinge has stainless steel pin |
| • | Cover fastened securely with captive plated steel screws |
| • | Collar studs provided for mounting optional panels |
| • | Hasp and staple provided for padlocking |
| • | No gasketing or knockouts |
speciFicaTions
• 16 or 14 gauge galvanized steel
FinisH ANSI 61 gray polyester powder paint finish inside and out over galvanized steel. Optional solid panels are white.
accessoRies See also Accessories.
Industrial Corrosion Inhibitors Electric Heater Grounding Device Panels for Type 3R, 4, 4X, 12 and 13 Enclosures Rack Mounting Angles - U Style (Type RA) Touch-Up Paint Steel and Stainless Steel Window Kits Bulletin: A3M
Standard Product Catalog Number AxBxC in. AxBxC mm Panel Perforated Panel Panel Size D x E (in.) Panel Size D x E (mm) Mounting G x H (in.) Mounting G x H (mm) Overall L (in.) Overall L (mm) A16R126HCR 16.00 x 12.00 x 6.00 406 x 305 x 152 A16P12 A16P12PP 13.00 x 9.00 330 x 229 17.00 x 3.00 432 x 76 18.00 457 A16R166HCR 16.00 x 16.00 x 6.00 406 x 406 x 152 A16P16 A16P16PP 13.00 x 13.00 330 x 330 17.00 x 13.00 432 x 330 18.00 457 A18R186HCR 18.00 x 18.00 x 6.00 457 x 457 x 152 A18P18 A18P18PP 15.00 x 15.00 381 x 381 19.00 x 13.00 483 x 330 20.00 508 A20R166HCR 20.00 x 16.00 x 6.00 508 x 406 x 152 A20P16 A20P16PP 17.00 x 13.00 432 x 330 21.00 x 13.00 533 x 330 22.00 559 A20R208HCR 20.00 x 20.00 x 8.00 508 x 508 x 203 A20P20 A20P20PP 17.00 x 17.00 432 x 432 21.00 x 13.00 533 x 330 22.00 559 A24R208HCR 24.00 x 20.00 x 8.00 610 x 508 x 203 A24P20 A24P20PP 21.00 x 17.00 533 x 432 25.00 x 13.00 635 x 330 26.00 660 A24R248HCR 24.00 x 24.00 x 8.00 610 x 610 x 203 A24P24 A24P24PP 21.00 x 21.00 533 x 533 25.00 x 13.00 635 x 330 26.00 660 A30R248HCR 30.00 x 24.00 x 8.00 762 x 610 x 203 A30P24 A30P24PP 27.00 x 21.00 686 x 533 31.00 x 13.00 787 x 330 32.00 813 A18R1810HCR 18.00 x 18.00 x 10.00 457 x 457 x 254 A18P18 A18P18PP 15.00 x 15.00 381 x 381 19.00 x 13.00 483 x 330 20.00 508 A30R308HCR 30.00 x 30.00 x 8.00 762 x 762 x 203 A30P30 A30P30PP 27.00 x 27.00 686 x 686 31.00 x 27.00 787 x 686 32.00 813 A24R2410HCR 24.00 x 24.00 x 10.00 610 x 610 x 254 A24P24 A24P24PP 21.00 x 21.00 533 x 533 25.00 x 13.00…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.