Construction & Demo

View the file

Other files

File Type Posted
W911SF19R00200004.pdf PDF
ARMOR_OSUT_1_-_5_Pre_Award_Addendum_1.pdf PDF
W911SF19R00200003.pdf PDF
Attachment_4_Performance_Assessment_Questionnaire.pdf PDF
ARMOR_OSUT_Site_Visit_Attendees.pdf PDF
44026_Morris_Oscar_5_Nad_83_Site_Plan_Model_Amended_12_July_2019.pdf PDF
Blank_Bid_Breakdown_Form.xlsx XLSX spreadsheet
Armor_OSUT_2_Questions.pdf PDF
ARMOR_OSUT_1_-_5_General_Questions.pdf PDF
OSUT_01_57_20_Environmental_Protection.pdf PDF
W911SF-19-R-0020-0002,_ARMOR_OSUT_2,_wdr,_5Jul19.pdf PDF
OSUT_33_40_00_Storm_Drainage_Utilities.pdf PDF
Stationary_Infantry_Target_(SIT).pdf PDF
OSUT_01_11_0_Summary_of_Work.pdf PDF
OSUT_01_45_01_Quality_Control.pdf PDF
SIT_ED-01.pdf PDF
OSUT_32_05_33_Landscape_Establishment.pdf PDF
OSUT_26_41_01_Lightning_Protection_System.pdf PDF
OSUT_01_32_01_Project_Schedule.pdf PDF
DSIT_ED-01A.pdf PDF
OSUT_32_01_19_Field_Molded_Sealants_for_Sealing_Jts_In_Rigid_Pavg.pdf PDF
OSUT_01_50_00_Temporary_Construction_Faclities_and_Controls.pdf PDF
44026-E5.pdf PDF
SIT_Clusters_ED-05.pdf PDF
26_00_00.00_20.pdf PDF
26_24_16.00_40.pdf PDF
OSUT_01_62_35_Recycled_Recovered_Materails.pdf PDF
OSUT_31_11_00_Clearing_and_Grubbing.pdf PDF
44026-E12.pdf PDF
OSUT_26_00_00_Basic_Electrical_Materials_and_Methods.pdf PDF
OSUT_01_35_29_Safety_and_Occupational_Health_Requirements.pdf PDF
OSUT_32_92_19_Seeding.pdf PDF
44026_Elec.pdf PDF
44026-E6.pdf PDF
OSUT_01_42_00_Sources_for_Referencece_Publications.pdf PDF
44026-E3.pdf PDF
OSUT_01_50_61_Dust_Control.pdf PDF
44026-E7.pdf PDF
OSUT_26_28_01_Coordinated_Power_System_Protection.pdf PDF
44026-E11.pdf PDF
44026-E13.pdf PDF
44026-E14.pdf PDF
OSUT_32_15_00_Aggregate_Surface_Course.pdf PDF
44026-E2.pdf PDF
OSUT_26_20_00_Interior_Distribution_System.pdf PDF
Downrange_Power_&_Data_Distribution_-_Over_300M.pdf PDF
OSUT_31_32_11_Soil_Surface_Erosion_Control.pdf PDF
OSUT_01_78_02_00_10_Closeout_Submittals.pdf PDF
44026-E9.pdf PDF
44026-E8.pdf PDF
Show 40 more

Latest 50 of 73 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OUST-AR RANGE PROJECTS FY19

SECTION 01 74 19

CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01/07

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM E 1609 (1994; R 2001) Development and Implementation of a Pollution Prevention Program

1.2 GOVERNMENT POLICY

Government policy is to apply sound environmental principles in the design, construction and use of facilities. As part of the implementation of that policy the Contractor shall: (1) practice efficient waste management when sizing, cutting, and installing products and materials and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse. A minimum of 75 percent by weight of total project solid waste shall be diverted from the landfill.

1.3 MANAGEMENT

Develop and implement a waste management program in accordance with ASTM E 1609 and as specified. Take a pro-active, responsible role in the management of construction and demolition waste and require all subcontractors, vendors, and suppliers to participate in the effort.

Construction and demolition waste includes products of demolition or removal, excess or unusable construction materials, packaging materials for construction products, and other materials generated during the construction process but not incorporated into the work. In the management of waste consideration shall be given to the availability of viable markets, the condition of the material, the ability to provide the material in suitable condition and in a quantity acceptable to available markets, and time constraints imposed by internal project completion mandates. The Contractor is responsible for implementation of any special programs involving rebates or similar incentives related to recycling of waste.

Revenues or other savings obtained for salvage, or recycling accrue to the Contractor. Appropriately permit firms and facilities used for recycling, reuse, and disposal for the intended use to the extent required by federal, state, and local regulations. Also, provide on-site instruction of appropriate separation, handling, recycling, salvage, reuse, and return methods to be used by all parties at the appropriate stages of the project.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Waste Management Plan; G;

SD-11 Closeout Submittals

Records

1.5 MEETINGS

Conduct Construction Waste Management meetings. After award of the Contract and prior to commencement of work, schedule and conduct a meeting with the Contracting Officer to discuss the proposed Waste Management Plan and to develop a mutual understanding relative to the details of waste management. The requirements for this meeting may be fulfilled during the coordination and mutual understanding meeting outlined in Section 01 45 01.10 USACE QUALITY CONTROL SYSTEM, and 01 45 01 USACE QUALITY CONTROL.

At a minimum, environmental and waste management goals and issues shall be discussed at the following additional meetings:

a. Pre-bid meeting.

b. Preconstruction meeting.

c. Regular site meetings.

d. Work safety meetings.

1.6 WASTE MANAGEMENT PLAN

A waste management plan shall be submitted within 30 days after notice to proceed and not less than 10 days before the preconstruction meeting. The plan shall demonstrate how the project waste diversion goal shall be met and shall include the following:

a. Name of individuals on the Contractor's staff responsible for waste prevention and management.

b. Actions that will be taken to reduce solid waste generation, including coordination with subcontractors to ensure awareness and participation.

c. Description of the regular meetings to be held to address waste management.

d. Description of the specific approaches to be used in recycling/reuse of the various materials generated, including the areas on site and equipment to be used for processing, sorting, and temporary storage of wastes.

e. Characterization, including estimated types and quantities, of the waste to be generated.

f. Name of landfill and/or incinerator to be used and the estimated costs for use, assuming that there would be no salvage or recycling on the project.

g. Identification of local and regional reuse programs, including non-profit organizations such as schools, local housing agencies, and organizations that accept used materials such as materials exchange networks and Habitat for Humanity. Include the name, location, and phone number for each reuse facility to be used, and provide a copy of the permit or license for each facility.

h. List of specific waste materials that will be salvaged for resale, salvaged and reused on the current project, salvaged and stored for reuse on a future project, or recycled. Recycling facilities that will be used shall be identified by name, location, and phone number, including a copy of the permit or license for each facility.

i. Identification of materials that cannot be recycled/reused with an explanation or justification, to be approved by the Contracting Officer.

j. Description of the means by which any waste materials identified in item (h) above will be protected from contamination.

k. Description of the means of transportation of the recyclable materials (whether materials will be site-separated and self-hauled to designated centers, or whether mixed materials will be collected by a waste hauler and removed from the site).

l. Anticipated net cost savings determined by subtracting Contractor program management costs and the cost of disposal from the revenue generated by sale of the materials and the incineration and/or landfill cost avoidance.

Revise and resubmit Plan as required by the Contracting Officer. Approval of Contractor's Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. Distribute copies of the Waste Management Plan to each subcontractor, the Quality Control Manager, and the Contracting Officer.

1.7 RECORDS

Records shall be maintained to document the quantity of waste generated;

the quantity of waste diverted through sale, reuse, or recycling; and the quantity of waste disposed by landfill or incineration. Records shall be kept in accordance with the MICC Reference Guide and using the Government provided Letter Template. The records shall be made available to the Contracting Officer during construction, and a copy of the records shall be delivered to the Contracting Officer upon completion of the construction.

1.9 COLLECTION

Separate, store, protect, and handle at the site identified recyclable and salvageable waste products in a manner that maximizes recyclability and salvagability of identified materials. Provide the necessary containers, bins and storage areas to facilitate effective waste management and clearly and appropriately identify them. Provide materials for barriers and enclosures around recyclable material storage areas which are nonhazardous and recyclable or reusable. Locate out of the way of construction traffic.

Provide adequate space for pick-up and delivery and convenience to subcontractors. Recycling and waste bin areas are to be kept neat and clean, and recyclable materials shall be handled to prevent contamination of materials from incompatible products and materials. Clean contaminated materials prior to placing in collection containers. Use cleaning materials that are nonhazardous and biodegradable. Handle hazardous waste and hazardous materials in accordance with applicable regulations and coordinate with Section 01 57 20.00 10 ENVIRONMENTAL PROTECTION. Separate materials by one of the following methods:

1.9.1 Source Separated Method.

Waste products and materials that are recyclable shall be separated from trash and sorted as described below into appropriately marked separate containers and then transported to the respective recycling facility for further processing. Deliver materials in accordance with recycling or reuse facility requirements (e.g., free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process). Separate materials into the following category types as appropriate to the project waste and to the available recycling and reuse programs in the project area:

a. Land clearing debris.

b. Asphalt.

c. Concrete and masonry.

d. Metal (e.g. banding, stud trim, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized, stainless steel, aluminum, copper, zinc, lead brass, bronze).

(1) Ferrous.

(2) Non-ferrous.

e. Wood (nails and staples allowed).

f. Debris.

g. Glass (colored glass allowed).

h. Paper.

(1) Bond.

(2) Newsprint.

(3) Cardboard and paper packaging materials.

i. Plastic.

(1) Type 1: Polyethylene Terephthalate (PET, PETE).

(2) Type 2: High Density Polyethylene (HDPE).

(3) Type 3: Vinyl (Polyvinyl Chloride or PVC).

(4) Type 4: Low Density Polyethylene (LDPE).

(5) Type 5: Polypropylene (PP).

(6) Type 6: Polystyrene (PS).

(7) Type 7: Other. Use of this code indicates that the package in question is made with a resin other than the six listed above, or is made of more than one resin listed above, and used in a multi-layer combination.

j. Gypsum.

k. Non-hazardous paint and paint cans.

l. Carpet.

m. Ceiling tiles.

n. Insulation.

o. Beverage containers.

1.9.2 Co-Mingled Method.

Waste products and recyclable materials shall be placed into a single container and then transported to a recycling facility where the recyclable materials are sorted and processed.

1.9.3 Other Methods.

Other methods proposed by the Contractor may be used when approved by the Contracting Officer.

1.10 DISPOSAL

Control accumulation of waste materials and trash. Recycle or dispose of collected materials off-site at intervals approved by the Contracting Officer and in compliance with waste management procedures. Except as otherwise specified in other sections of the specifications, disposal shall be in accordance with the following:

1.10.1 Reuse.

First consideration shall be given to salvage for reuse since little or no re-processing is necessary for this method, and less pollution is created when items are reused in their original form. Coordinate reuse with the Contracting Officer. Sale or donation of waste suitable for reuse shall be considered.

1.10.2 Recycle.

Waste materials not suitable for reuse, but having value as being recyclable, shall be made available for recycling. All fluorescent lamps, HID lamps, and mercury-containing thermostats removed from the site shall be recycled. Arrange for timely pickups from the site or deliveries to recycling facilities in order to prevent contamination of recyclable materials.

1.10.3 Compost

Consider composting on site if a reasonable amount of compostable material will be available. Compostable materials include plant material, sawdust, and certain food scraps.

1.10.4 Waste.

Materials with no practical use or economic benefit shall be disposed at a landfill or incinerator.

1.10.5 Return

Set aside and protect misdelivered and substandard products and materials and return to supplier for credit.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used. -- End of Section --