About this file

This document contains a pre-solicitation notice for the eXportable Combat Training Capability program. The U.S. Army Contracting Command - Orlando plans to award a full and open contract to provide the Army National Guard with a capstone training event for Brigade Combat Teams to achieve T-Level 3 readiness. The twofold mission is to develop adaptive leaders and enable platoons to achieve trained proficiency in core functions. The draft solicitation is intended to facilitate an exchange with industry to receive questions, comments and recommendations on the requirements before the final RFP is issued. Potential offerors are encouraged to submit feedback to the identified Contract Specialist by March 4, 2019 to improve the final solicitation.

TDP Item 40 - Field Support Center Manual

View the file

Other files

File Type Posted
XCTC_IDIQ_RFP_Amendment_0002_conformed_track_changes.docx DOCX document
XCTC_IDIQ_RFP_Amendment_0002.docx DOCX document
Attachment_33_Camp_Guernsey_WD_15-5414_Rev_07.pdf PDF
Attachment_14_XCTC_Pricing_Workbook_2019-04-30.xlsx XLSX spreadsheet
Attachment_32_Sample_Task_Order_PWS_2019-04-30_track_changes.docx DOCX document
XCTC_IDIQ_RFP_Amendment_0001.docx DOCX document
Attachment_31_Sample_Task_Order_2019-04-30_track_changes.docx DOCX document
Attachment_07_Potential_XCTC_training_locations_2019-04-30.xlsx XLSX spreadsheet
Attachment_34_RFP_Q_and_A_2019-04-30.xlsx XLSX spreadsheet
XCTC_IDIQ_RFP_Amendment_0001_conformed_track_changes.docx DOCX document
Attachment_01_IDIQ_PWS_2019-04-30_track_changes.docx DOCX document
Attachment_31_Sample_Task_Order_2019-04-30.docx DOCX document
Attachment_02_GFP_List_2019-04-30.xlsx XLSX spreadsheet
Exhibit_11_XCTC_CDRL_(SB_Sub_Report)_A010.pdf PDF
Exhibit_10_XCTC_CDRL_(SBU_Use_Report)_A009.pdf PDF
Exhibit_12__XCTC_CDRL_(QCP)_A011.pdf PDF
Exhibit_02_XCTC_CDRL_(Mo_Rpt)_A001.pdf PDF
Exhibit_07_XCTC_CDRL_(DAL)_A006.pdf PDF
Exhibit_09_XCTC_CDRL_(OPSEC_Pln)_A008.pdf PDF
Exhibit_04_XCTC_CDRL_(STIG_Rpt)_A003.pdf PDF
Exhibit_06_XCTC_CDRL_(RMF)_A005.pdf PDF
Exhibit_08_XCTC_CDRL_(GFE_INV_RPT)_A007.pdf PDF
Exhibit_03_XCTC_CDRL_(Meet_min)_A002.pdf PDF
Exhibit_01_XCTC_DD254.pdf PDF
Exhibit_05_XCTC_CDRL_(RISK_Man_Pln)_A004.pdf PDF
Example_04_Planning_Conferences.pptx PPTX presentation
Example_01_RD_Monthly_Telecon_Slides.pptx PPTX presentation
Example_03_Five-year_Rotation_Tracker.xlsx XLSX spreadsheet
Example_06_Concept_Brief.pptx PPTX presentation
Example_08_Trng_Res_Req_Matrix.xlsx XLSX spreadsheet
Example_13_Academy_Trng_Schedule.pptx PPTX presentation
Example_07_XCTC_Leader_Book_.pdf PDF
Example_10_EXROE.pptx PPTX presentation
Example_05_Rotation_Brief.pptx PPTX presentation
Example_12_XCTC_Mission_Book.pdf PDF
Example_02_Six-Month_event_calendar.xlsx XLSX spreadsheet
Example_09_Exercise_Directive.pdf PDF
Example_11_Horse_Blanket_20190318.xlsx XLSX spreadsheet
Example_14_MILES_Request.pdf PDF
RTS-comms-shelter_B3.pdf PDF
100-300_Manual_Rev_B3.pdf PDF
Masthead_Assembly_Design_Documents.zip ZIP file
5100_ES_Model_I_Operating_Manual_B3.pdf PDF
Network_Operations_Center_Design_Documents.zip ZIP file
Base-X_Dome_manual_Rev_B3.pdf PDF
Video_Take_Home_Package_BoM.zip ZIP file
FREDI-2_Basic_Transit_Case_Design_Documents.zip ZIP file
Administrative_Communications_Center.zip ZIP file
IC-OUM-08002_2.3_B3.pdf PDF
IC-OUM-07010_1.4_v2_(002)_B3.pdf PDF
Show 40 more

Latest 50 of 233 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IC-OUM-09000 Rev 1.2 11/7/2017

Operator User Manual for the Field Support Center

Date: 7 November 2017

Prepared by: Taylor Lynard

Operator User Manual for the Field Support Center

CHANGE LOG

CHANGE / REVISION RECORD

Revision Page(s) Description of Change Made By Date Approved By

1.0 All Initial Release

1.1 All Edited formatting

Taylor Lynard

11/7/17 James DePersis

1.2 2 Revised date James

DePersis 2/9/18 James

DePersis

Operator User Manual for the Field Support Center

Table of Contents

1. Introduction

1.1 General Information

1.1.1 Scope

1.1.2 Safety

1.1.3 Security

1.1.4 List of Abbreviations/Acronyms

1.2 Equipment Description

1.2.1 Equipment Characteristics, Capabilities, and Features

1.2.2 Equipment Data

1.3 Principles of Operation

2. Operating Instructions

2.1 Description and Use of Operator’s Controls and Indicators

2.2 Operation under Usual Conditions

2.2.1 Preparation for Operation

2.2.2 Operation

2.2.3 Termination

2.2.4 Removal

2.2.5 Preparation for Storage

2.2.6 Preparation for Shipment

2.3 Operation under Unusual Conditions

2.3.1 Unusual Environment

2.3.2 Emergency Procedures

3. Operator Maintenance Instructions

3.1 Troubleshooting

3.2 Maintenance Procedures

4. Special Tools/Installation Equipment

5. Appendix

Operator User Manual for the Field Support Center

Table of Figures Figure 1: FSC right side door view……………………………………………………………………………………………………………6

Figure 2: FSC Workbench…………………………………………………………………………………………………………………………7

Figure 3: Power Service Selector Switch………………………………………………………………………………………………….8

Figure 4: Electrical Breaker Panel…………………………………………………………………………………………………………….8

Operator User Manual for the Field Support Center

1. Introduction

1.1 General Information

1.1.1 Scope

The operator’s manual for the Field Support Center focuses on the functionality of the Field Support Center within the FlexTrainTM program.

1.1.2 Safety

The Field Support Center requires all regularly scheduled semi-trailer services. Use caution when deploying the Field Support Center during adverse conditions. The Field Support Center should be deployed on stable, level ground whenever possible.

1.1.3 Security

Not Applicable

1.1.4 List of Abbreviations/Acronyms

FSC Field Support Center

HVAC Heating, Ventilation Air Conditioning

POL Petroleum, Oils and Lubricants

1.2 Equipment Description

The FSC is a 53 ft. semi-trailer used to support field operations.

1.2.1 Equipment Characteristics, Capabilities, and Features

The Field Support Center serves as the primary operations center for Range Operations generator/HVAC service and tool/equipment storage in support of a FlexTrain exercise. The FSC provides workspace and equipment vital to the operation and sustainment of the FlexTrainTM infrastructure.

The FSC may be accessed via the rear roll up door or a side staircase leading to a personnel door.

The personnel door staircase is secured in a compartment underneath the side access door during transport. After the FSC is deployed, the staircase and associated hand rails shall be properly secured to the attachment points on the exterior of the trailer prior to any personnel utilizing this entry point.

1.2.1.1 Functions of the Field Support Center

The FSC is used to transport all the tools and equipment that support the deployment and sustainment of generators, HVAC’s and mobile relay towers. The FSC is used as a storage location for any necessary spare components required for repair or service of generators, HVAC’s and mobile relay towers. Located inside the FSC is a Hazmat Storage Locker where all

Operator User Manual for the Field Support Center

POL is stored to support FlexTrainTM operations. The FSC has a small office space that can be utilized when other options are not available.

1.2.2 Equipment Data

Not Applicable

1.3 Principles of Operation

The Field Support Trailer is a rapidly deployable semi-trailer that houses equipment and workspace for FlexTrainTM missions. The FSC should be delivered and placed onto stable, level ground to provide safe access for removing equipment. The FSC should be placed so that the rear opening of the trailer is accessible by forklift for removing equipment. Location of the FSC should be placed within proximity to the Instrumentation Warehouse.

The FSC contains network ready workspace for initial configuration and setup tasks for a

FlexTrainTM exercise. The FSC may be powered via an external IEC 60309 (color code Orange) 120/240 power source. Power may be provided by an onsite generator or other direct wire power source. The outlets are located along workbenches in the interior of the trailer. Lighting is provided from overhead light fixtures. The interior of the trailer is maintained with a heating, ventilation, and air conditioning unit for warm and cold weather operating conditions.

Figure 1. FSC

Operator User Manual for the Field Support Center

Figure 2. FSC Workbench

2. Operating Instructions

2.1 Description and Use of Operator’s Controls and Indicators The rear electric lift gate is powered by a pair of 12V automotive batteries located underneath the trailer.

The lift gate control panel is located adjacent to the rear lift gate. After the lift gate has been lowered, the rear roll up door may be unlatched and opened to grant access to the rear cargo hold of the FSC. Keep clear of the lift gate while it is in operation. The lift gate should remain in the down position and marked with road cones when not in use.

Main electrical power should be connected to the FSC by a certified electrical technician. A power service switch and an electrical breaker panel are located on the interior of the FSC near the personnel entrance door. HVAC operation is automatic when connected to a power source and may be controlled by its corresponding electrical breaker.

The FSC is outfitted with 20-Amp 120v electrical outlets near all workbenches. An electrical breaker controls the power to each 4-outlet electric panel. Light fixtures are attached along the length of the ceiling of the FSC. A light switch located near the personnel entrance door will toggle lighting inside the trailer.

Operator User Manual for the Field Support Center

Figure 3. Power Service Selector Switch Figure 4. Electrical Breaker Panel

2.2 Operation under Usual Conditions

2.2.1 Preparation for Operation

2.2.1.1 Installation of the Field Support Center

The FSC should be delivered and placed on level, firm ground near the Instrumentation Warehouse unless the mission requirements dictate otherwise. All entrance stairways and handrails should be securely setup before extended operations inside the FSC.

2.2.1.2 Power-up and Initialize

Main electrical power should be connected to the FSC by a certified electrical technician.

2.2.2 Operation

The FSC is used as needed for the storage of tools and equipment and a workspace.

2.2.3 Termination

Turn off all electrical items inside the FSC. Turn off the overhead lights and place all breakers into the off position. Place the Power Service Selector Switch to the OFF position.

2.2.4 Removal

The FSC is removed by a contracted trucking company.

Operator User Manual for the Field Support Center

2.2.5 Preparation for Storage

Ensure all latches are secure and locked on the rear doors. Secure the rear lift gate and ensure it is in the fully closed position. Properly remove and store the personnel entrance staircase and handrail into the underneath storage compartment. Secure the staircase and handrail with the appropriate locking mechanisms to ensure it does not become loose during transport.

2.2.6 Preparation for Shipment

Ensure that all components of the FSC are road and travel ready. Ensure all items are secured within the trailer prior to transport. Place cargo netting and/or rubber tarp straps to secure loose items on tables and workbenches. Place all POL in the HazMat locker. Check that all external entrances are properly latched and secured. Check that any external items are properly secured.

Check condition of tires and ensure that the semi-trailer suspension provides enough clearance for the tires, so they will not contact the semi-trailer during travel. Check the semi-trailer lights to ensure road safety during transport.

2.3 Operation under Unusual Conditions

2.3.1 Unusual Environment

When entering or exiting the FSC via the side personnel entrance or rear roll up door, take caution that any debris or weather may cause slippery footing both inside and outside the FSC.

During severe electrical or lightning storms, operations inside the FSC should be conducted only if necessary.

2.3.1.1 Lightning

The FSC and any connected electrical generators should be properly grounded during setup. Avoid working inside the FSC during severe lightning storms unless necessary. If lightning damage is suspected, immediately power down the FSC and any connected generators and thoroughly check for lightning damage.

2.3.1.2 Strong Winds

The FSC is used at ground level and should not be affected by strong wind conditions.

2.3.1.3 Cold

Not Applicable

2.3.2 Emergency Procedures

Not Applicable

Operator User Manual for the Field Support Center

3. Operator Maintenance Instructions

3.1 Troubleshooting

a. Observation: Electrical outlets are non-functioning. Lights do not work with electricity connected.

b. Solutions: Open circuit breaker panel and check for any breakers in the off or disconnected position. Ensure the power service selector switch is in the proper position, either Generator or Land Power. Contact a licensed electrician if problems persist

a. Observation: HVAC unit does not activate with power connected.

b. Solutions: Open circuit breaker panel and check for any breakers in the off or disconnected position. Contact a licensed HVAC technician if problems persist.

a. Observation: Toggling the control panel for the rear lift gate does not produce any motion in the lift gate.

b. Solutions: The battery for the rear lift gate has likely run out of charge. Attach an appropriate 12v or car battery charger to the battery and let sit until fully charged. Ensure all electrical connections between the batteries and the lift gate are functioning properly. Check the lift gate fuse.

3.2 Maintenance Procedures

Not Applicable

4. Special Tools/Installation Equipment Not Applicable

5. Appendix Not Applicable

1. Introduction
1.1 General Information
1.1.1 Scope
1.1.2 Safety
1.1.3 Security
1.1.4 List of Abbreviations/Acronyms
1.2 Equipment Description
The FSC is a 53 ft. semi-trailer used to support field operations.
1.2.1 Equipment Characteristics, Capabilities, and Features
1.2.1.1 Functions of the Field Support Center

1.2.2 Equipment Data

1.3 Principles of Operation

2. Operating Instructions
1.1 Description and Use of Operator’s Controls and Indicators
2.1
Figure 3. Power Service Selector Switch Figure 4. Electrical Breaker Panel
1.1 Operation under Usual Conditions
2.2
2.2.1 Preparation for Operation
1.1.1.1
2.2.1.1 Installation of the Field Support Center
The FSC should be delivered and placed on level, firm ground near the Instrumentation Warehouse unless the mission requirements dictate otherwise. All entrance stairways and handrails should be securely setup before extended operations inside the FSC.
2.2.1.2 Power-up and Initialize
2.2.2 Operation
2.2.3 Termination
Turn off all electrical items inside the FSC. Turn off the overhead lights and place all breakers into the off position. Place the Power Service Selector Switch to the OFF position.
1.1.1
2.2.4 Removal
2.2.5 Preparation for Storage
2.2.6 Preparation for Shipment
1.1 Operation under Unusual Conditions
2.3
2.3.1 Unusual Environment
2.3.1.1 Lightning
2.3.1.2 Strong Winds
2.3.1.3 Cold

2.3.2 Emergency Procedures

1. Operator Maintenance Instructions
3.
1.1 Troubleshooting
3.1
3.2 Maintenance Procedures
4. Special Tools/Installation Equipment
5. Appendix