W58RGZ-15-R-0045 APPENDIX E to SEMA PWS

APPENDIX E – COST AND SOFTWARE DATA REPORTING PLAN FORMAT

a. NAME:

Pre-A B C-FRP X

A C-LRIP X O&S

PROGRAM X

X

X

a. CWBS

DICTIONARY

d. DD 1921-2

(PCR)

f. SRDR

FORMATS

X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X

DD FORM 2794, MAY 2011 PREVIOUS EDITION IS OBSOLETE

X

a. CWBS

DICTIONARY

d. DD 1921-2

(PCR)

f. SRDR

FORMATS

X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X

DD FORM 2794, MAY 2011 PREVIOUS EDITION IS OBSOLETE

1.4.3.3 SUPPLY ANALYSIS EFFORTS X

1.4.3.4 SAFETY/HUMAN SYSTEMS INTEGRATION ENGINEERING X

1.4.3.5 AFFORDABILITY ENGINEERING X

1.4.3.6 OBSOLESCENCE ENGINEERING X

1.4.3.7 AVAILABILITY MANAGEMENT X

1.4.3.8 PRODUCT ENGINEERING SUPPORT X

1.4.3.9 INFORMATION ASSURANCE X

1.4.3.10 CONFIGURATION MANAGEMENT X

1.4.3.11 SYSTEM PERFORMANCE ANALYSIS X

1.4.3.12 SUPPLY X

1.4.3.13 DATA ANALYSIS X

1.4.3.14 PHYSICAL SECURITY X

1.4.4 PROGRAM MANAGEMENT X

1.4.4.1 CONTRACTOR LOGISTICS SUPPORT (CLS) MANAGEMENT X

1.4.4.2 CLS SUPPLY MANAGEMENT X

1.4.4.3 FINANCIAL/SCHEDULE PLANNING AND REPORTING X

1.4.4.4 TRANSITION TO LEAD SERVICE X

1.4.4.5 QUALITY ASSURANCE (Program Level) X

1.4.4.6 ADMINISTRATIVE SECURITY X

1.4.4.7 TRANSITION TO PERFORMANCE BASED LOGISTICS (PBL) X

1.4.4.8 RISK MITIGATION X

1.4.5 INFORMATION SYSTEMS X

1.4.5.1 TECH REFRESH X

1.4.5.2 LICENSE FEES X

1.4.5.3 MAINTENANCE X

1.4.6 DATA AND TECHNICAL PUBLICATIONS X

1.4.7 SIMULATOR OPERATIONS X

1.4.7.1 SIMULATOR OPERATIONS HARDWARE SUPPORT X

1.4.7.2 SIMULATOR OPERATIONS MANPOWER X

1.4.7.3 SIMULATOR TECH REFRESH X

1.4.8 OTHER SUSTAINING SUPPORT (Specify in Remarks) X

1.5 CONTINUING SYSTEM IMPROVEMENTS X

1.5.1 HARDWARE MODIFICATIONS OR MODERNIZATION X

1.5.1.1 MOD KIT DEVELOPMENT X

1.5.1.2 MOD KIT PROCUREMENT X

1.5.1.3 MOD KIT INITIAL SPARES X

1.5.1.4 MOD KIT INSTALLATION X

1.5.2 SOFTWARE MAINTENANCE OR MODIFICATION X

1.6 INSTALLATION AND PERSONNEL SUPPORT (System Level Only) X

Subtotal Cost X

Reporting Contractor G&A X Reporting Contractor Undistributed Budget X Reporting Contractor Management Reserve X Reporting Contractor FCCM X Total Cost X

Reporting Contractor Profit/Loss or Fee X

Total Price X

1.4.3.2 LOGISTICS ENGINEERING (LSA updates, logistics analysis) X

11. WBS ELEMENT CODE

12.

WBS REPORTING ELEMENTS

13. REPORTS REQUIRED

(X if applicable)

DD 1921-3 (CBDR):

a. PROGRAM/

CONTRACT/

SUBCONTRACT

b. CONTRACT/

SUBCONTRACT

b. DD 1921

(CDSR)

c. DD 1921-5

(FCHR)

e. DD 1921-4

(CSR)

1.4.3.1 RELIABILITY AND MAINTAINABILITY ENGINEERING X

1.4.3 SUSTAINING/SYSTEMS ENGINEERING X

1.1 UNIT-LEVEL MANPOWER (SYSTEM LEVEL COST ONLY) X

1.1.1 OPERATIONS MANPOWER X

1.1.2 UNIT-LEVEL MAINTENANCE MANPOWER X

1.1.3 OTHER UNIT-LEVEL MANPOWER (Specify in Remarks) X

1.2 UNIT OPERATIONS (SYSTEM LEVEL COST ONLY) X

1.2.1 OPERATING MATERIAL X

1.2.1.1 ENERGY (Fuel; Petroleum, Oil, and Lubricants (POL); Electricity) X

1.2.1.2 TRAINING MUNITIONS/EXPENDABLE STORES X

1.2.1.3 OTHER OPERATING MATERIAL (Specify in Remarks) X

1.2.2 SUPPORT SERVICES (INCLUDING NON-MAINTENANCE FSRs) X

1.2.3 TEMPORARY DUTY X

1.3 MAINTENANCE X

1.3.1 OVERHAUL OF END ITEMS X

1.3.1.1 SCHEDULED OVERHAUL X

1.3.1.1.1 VEHICLE OVERHAUL X

1.3.1.1.2 PROPULSION OVERHAUL X

1.3.1.1.3 OTHER OVERHAUL X

1.3.1.2 UNSCHEDULED OVERHAUL X

1.3.1.2.1 VEHICLE OVERHAUL X

1.3.1.2.2 PROPULSION OVERHAUL X

1.3.1.2.3 OTHER OVERHAUL X

1.3.2 DEPOT LEVEL REPARABLES (DLR) / REPAIR OF REPARABLES (ROR) X

1.3.3 CONSUMABLES AND REPAIR PARTS X

1.3.4 OTHER MAINTENANCE SERVICES (INCLUDING FSRs) (Explain in Remarks) X

1.3.4.1 O-LEVEL MAINTENANCE SERVICES X

1.3.4.2 I-LEVEL MAINTENANCE SERVICES X

1.3.4.3 DEPOT LEVEL MAINTENANCE SERVICES X

1.3.5 PACKING, HANDLING, SHIPPING AND TRANSPORTATION X

1.4 SUSTAINING SUPPORT (SYSTEM LEVEL COST ONLY) X

1.4.1 SYSTEM SPECIFIC TRAINING X

1.4.1.1 OPERATOR TRAINING X

1.4.1.2 MAINTENANCE TRAINING X

256-876-5495

6c. FAX NUMBER (Include Area Code)

256-876-2700

Aircraft SystemSustainment

5. LAST APPROVED PLAN DATE

(YYYYMMDD)

20140910

INITIAL

CHANGE

COST AND SOFTWARE DATA REPORTING PLAN Form Approved OMB No. 0704-0188

b. PHASE/MILESTONE c. PRIME MISSION PRODUCT

The public reporting burden for this collection of information is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information.

Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION.

2. WBS SYSTEM TYPE

1. MAJOR PROGRAM Army Fixed Wing Aircraft Sustainment - SEMA

3. SUBMISSION TYPE 4. CURRENT SUBMISSION

DATE (YYYYMMDD)

7. PLAN TYPE

CONTRACT (PRIME)

CONTRACT (SUB)

TBD

ii. DIVISION

9a. CONTRACTOR NAME/ADDRESS

i. PERFORMING ORGANIZATION

6d. E-MAIL ADDRESS brooke.n.chandler.civ@mail.mil

TBD

6a. POINT OF CONTACT (POC) NAME AND ADDRESS (Include ZIP Code)

Brooke Chandler 650 Discovery Drive Huntsville, AL

RDT&E

PROCUREMENT

O&M

9c. APPROPRIATION

6b. TELEPHONE NUMBER (Include Area Code)

A-14-G-C1

10. APPROVED PLAN NUMBER

c. DD 1921-5

(FCHR)

e. DD 1921-4

(CSR)

DD 1921-3 (CBDR):

9b. CONTRACT NUMBER

TBD

b. CONTRACT/

SUBCONTRACT

12.

WBS REPORTING ELEMENTS

11. WBS ELEMENT CODE 13. REPORTS REQUIRED

(X if applicable)

a. PROGRAM/

CONTRACT/

SUBCONTRACT

8. PREPARING

ORGANIZATION

Fixed Wing PO

1.0

1.4.2 1.4.1.3

b. DD 1921

(CDSR)

XSUSTAINMENT EFFORT

SUPPORT EQUIPMENT REPLACEMENT X

OTHER TRAINING X

X

d. AS OF DATE e. DUE DATE

(YYYYMMDD) (YYYYMMDD)

1 CWBS Dictionary Dictionary submitted with first cost report 20161130 20170130 2 1921, 1921-1 Interim #1 - RC 12 20161130 20170130 3 1921, 1921-1 Interim #1 - EO-5/ARL 20161130 20170130 4 1921, 1921-1 Interim #1 - ARL-E 20161130 20170130 5 1921, 1921-1 Interim #1 - EMARSS 20161130 20170130 6 1921, 1921-1 Interim #1 - EMARSS-MAMI 20161130 20170130 7 1921, 1921-1 Interim #2 - RC 12 20171130 20180130 8 1921, 1921-1 Interim #2 - EO-5/ARL 20171130 20180130 9 1921, 1921-1 Interim #2 - ARL-E 20171130 20180130

10 1921, 1921-1 Interim #2 - EMARSS 20171130 20180130 11 1921, 1921-1 Interim #2 - EMARSS-MAMI 20171130 20180130 12 1921, 1921-1 Interim #3 - RC 12 20181130 20190130 13 1921, 1921-1 Interim #3 - EO-5/ARL 20181130 20190130 14 1921, 1921-1 Interim #3 - ARL-E 20181130 20190130 15 1921, 1921-1 Interim #3 - EMARSS 20181130 20190130 16 1921, 1921-1 Interim #3 - EMARSS-MAMI 20181130 20190130 17 1921, 1921-1 Interim #4 - RC 12 20191130 20200130 18 1921, 1921-1 Interim #4 - EO-5/ARL 20191130 20200130 19 1921, 1921-1 Interim #4 - ARL-E 20191130 20200130 20 1921, 1921-1 Interim #4 - EMARSS 20191130 20200130 21 1921, 1921-1 Interim #4 - EMARSS-MAMI 20191130 20200130 22 1921, 1921-1 Interim #5 - RC 12 20201130 20210130 23 1921, 1921-1 Interim #5 - EO-5/ARL 20201130 20210130 24 1921, 1921-1 Interim #5 - ARL-E 20201130 20210130 25 1921, 1921-1 Interim #5 - EMARSS 20201130 20210130 26 1921, 1921-1 Interim #5 - EMARSS-MAMI 20201130 20210130 27 1921, 1921-1 Interim #6 - RC 12 20211130 20220130 28 1921, 1921-1 Interim #6 - EO-5/ARL 20211130 20220130 29 1921, 1921-1 Interim #6 - ARL-E 20211130 20220130 30 1921, 1921-1 Interim #6 - EMARSS 20211130 20220130 31 1921, 1921-1 Interim #6 - EMARSS-MAMI 20211130 20220130 32 1921, 1921-1 Interim #7 - RC 12 20221130 20230130 33 1921, 1921-1 Interim #7 - EO-5/ARL 20221130 20230130 34 1921, 1921-1 Interim #7 - ARL-E 20221130 20230130 35 1921, 1921-1 Interim #7 - EMARSS 20221130 20230130 36 1921, 1921-1 Interim #7 - EMARSS-MAMI 20221130 20230130 37 1921, 1921-1 Interim #8 - RC 12 20231130 20240130 38 1921, 1921-1 Interim #8 - EO-5/ARL 20231130 20240130 39 1921, 1921-1 Interim #8 - ARL-E 20231130 20240130 40 1921, 1921-1 Interim #8 - EMARSS 20231130 20240130 41 1921, 1921-1 Interim #8 - EMARSS-MAMI 20231130 20240130 42 1921, 1921-1 Interim #9 - RC 12 20241130 20250130 43 1921, 1921-1 Interim #9 - EO-5/ARL 20241130 20250130 44 1921, 1921-1 Interim #9 - ARL-E 20241130 20250130 45 1921, 1921-1 Interim #9 - EMARSS 20241130 20250130 46 1921, 1921-1 Interim #9 - EMARSS-MAMI 20241130 20250130 47 1921, 1921-1 Final Report - RC 12 20251130 20260130

DD FORM 2794 (PAGE 2), MAY 2011 PREVIOUS EDITION IS OBSOLETE

d. AS OF DATE e. DUE DATE

(YYYYMMDD) (YYYYMMDD)

48 1921, 1921-1 Final Report - EO-5/ARL 20251130 20260130 49 1921, 1921-1 Final Report - ARL-E 20251130 20260130 50 1921, 1921-1 Final Report EMARSS 20251130 20260130 51 1921, 1921-1 Final Report - EMARSS-MAMI 20251130 20260130 52 Assumes Contract award is 11/25/15

DD FORM 2794 (PAGE 2), MAY 2011 PREVIOUS EDITION IS OBSOLETE

c. Data for Future Years should be reflective of the number of years contained in the most current document, i.e., the FPRP or the FPRA. If the document applies to more than three future years, attach additional future year sheets as required. In the absence of these documents, estimates should be provided for three future years.

SEMA aircraft include c.

EVENT

1. Describe significant accounting changes from previous accounting period in the Remarks section of the reports, if applicable.

2. DD Form 1921-3 Contractor Business Data Report:

a. The Contractor Business Data Report is prepared by and for the business entity (e,g., business unit, segment, or site) responsible for submitting the Forward Pricing Rate Proposal (FPRP) representing the basis for Forward Pricing Rate Agreement (FPRA) negotiations with the government

b. Reports are submitted annually at the end of the contractor's fiscal year.

14. CSDR SUBMISSION DATES

15. REMARKS

c.

EVENT

a.

SUBMISSION

b.

FORM(S)

14. CSDR SUBMISSION DATES

a.

SUBMISSION

b.

FORM(S)

Addenda for CSDR Plans. The contractor shall provide the following additional information on a separate page(s) attached to the program or contract plan.

a. Resource Distribution Table (RDT) (formerly referred to as the Resource Assignment Matrix (RAM)). The RDT is designed to provide an overview of the program’s total or contract acquisition funding and to help ensure that all contracts meeting the reporting thresholds contain CSDR requirements. Provide the name and address of any prime contractors, subcontractors, lower-tier subcontractors, and government-furnished equipment (GFE) providers that may meet the CSDR thresholds along with the specific WBS elements for which they are responsible.

Include support contracts, government testing facilities, training facilities, and all other acquisition costs.

1. Program Plan RDT. Contract/subcontract information provided in the RDT section must be consistent with the current contract and cost information provided in other official program acquisition documents such as the Selected Acquisition Report (SAR) and the Acquisition Plan (required by the Federal Acquisition Regulation (FAR)) and is required to be updated every year. Note that including a particular contract or subcontract in the RDT does not automatically result in CSDR being required. This decision is made by the CWIPT in coordination with the DoD PM. An example of a properly completed RDT can be found at the DCARC Web site. T he information supplied is not intended in any way to preempt the prime contractor’s selection process for subcontractors. Instead, its purpose is to establish an early tracking mechanism to ensure all appropriate reporting requirements are implemented. The information contained in the RDT is required to be updated as RFPs are issued and contracts are awarded.

i. Enter the total program cost for the milestone/phase identified in Item 1c.

ii. The following information is mandatory for each prime contract:

(a) Identify the contractor if known; otherwise enter ”TBD” (for “to be determined”) and include the estimated total contract value and the estimated total software development effort which, for CSDR purposes, represents the expected price at contract completion (i.e., initial contract award plus all expected contract changes). This value must also be based upon the assumption that all contract options will be exercised.

(b) Identify each subcontractor if known; otherwise enter “TBD” (for “to be determined”) and its expected value and software development effort which, for CSDR purposes, represents the expected price at contract completion (i.e., initial contract award plus all expected contract changes).

This value must also be based upon the assumption that all contract options will be exercised.

(c) Using the WBS contained in Item 11 of the CSDR Plan, annotate with “X” the WBS elements for which the Prime contractor and each subcontractor have or will have effort.

iii. For government-furnished equipment (GFE):

(a) Identify each source of GFE and its estimated total value and estimated total software development effort which, for CSDR purposes, represents the expected price at completion (i.e., initial funding plus all expected changes). This value must also be based upon the assumption that all funding options will be exercised. If the GFE is already on contract, provide the assigned prime contract number the Government has with the prime contractor along with the contractor name.

(b) Using the WBS contained in Item 11 of the CSDR Plan, annotate with “X” the WBS elements for which the source of GFE has or will have effort.

2. Contract/Subcontract Plan RDT. Subcontract information provided in the RDT section must be consistent with current contract/subcontract information provided in the program plan RDT, that is, it must reflect the most current contract or subcontract value (including all mods and CLINs), and must conform to the applicable rules established above for the program plan RDT. In addition, include the assigned subcontract number for each subcontract between the prime and the subcontractor.

Rev Date Changes 0 4/26/2007 N/A 1 10/5/2007 • Item 1a: Changed example MDAP from AESA to UH-60M. •

Item 2: Removed ―Appendix A‖ from example entry. • Item 5:

Changed direction for initial plan submissions from entering ―initial‖ to leaving item blank. • Item 10b: Reiterated preference for numeric decimal WBS codes. • Item 13a: Changed direction from providing ―N/A‖ for non-applicable elements, to providing

―X‖ for every non-summary element. Removed direction for CWBS column to match DD 1921 column. • Item 13b: Changed direction from providing ―N/A‖ for all non-applicable elements, to providing ―X‖ for all MIL-HDBK881A common elements.

Removed direction for DD 1921 column to match CWBS column.

• RDT Description: Provided additional language on purpose of RDT, costs which must be included, and requirement for a total funding line for all providers not meeting thresholds. • Contract/Subcontract Plan RDT: Clarified contract/subcontract values are required according to same definition provided in Program RDT section.

2 3/7/2008 • Item 2 & 9: Edited item names for consistency with DD 2794 field names. • Item 11: Added instructions for usage of ―Non-MIL-HDBK 881 Attributable Costs‖ WBS element. • Item 15b: Revised language from ―these entries are mandatory‖ to―these topics are mandatory‖.

3 6/2/2008 • Added revisions history table.

4 8/6/2008 • Item 15b: Added additional standard language for recurring/nonrecurring definitions.

5 6/3/2009 • Item 15b: Added mandatory language describing the requirement for the DD Form 1921-3.

6 5/18/2011 • Item 1a renamed Major Program / Name. • Item 1b Phase/Milestone and Item 1c Prime Mission Product renumbered. • Item 2 renamed WBS System Type. • Items 9a Contractor Name, 9b Contract Number moved (were 12a/b); Item 9c Appropriation added. • Items 11a Program/Contract/Subcontract and 11b Contract/Subcontract modified. • Item 13 Reports Required: expanded for clarification and to fit current uses. • Item 14 CSDR Submission Dates: modified for Final Reports. • Item 15 Remarks: added section about technical metrics. • Updated references to match current DoD organizational structure and documents.

DD 2794 Form Instructions Revisions History

Example Resource Distribution Table (RDT) Sustainment - Contract Plan

Prime Contractor or Sub-Contractor Contract 1 In House Subcontract 1 In House Subcontract 2 In House Cumulative Contract Total

Description Contractor/Organization Name Company A Company B Company C

Contractor/Organization Location

Contract Number Total Program Office or Contract/Effort Value (Estimated), TY$M $0.0

Subtotal Software Contract Value (Estimated), TY$M Government Organization or PARM

CSDR Direct Reporting per CWIPT (Yes/No) SRDR Direct Reporting per CWIPT (Yes/No)

1.0 Unit Level Manpower

1.1 Operations Manpower

1.2 Unit-Level Maintenance Manpower

1.3 Other Unit-Level Manpower

2.0 Unit Operations

2.1 Operating Material

2.2 Support Services (including non-maint FSRs)

2.3 Temporary Duty

3.0 Maintenance

3.1 Overhaul of End Items

3.2 DLRs/RoRs

3.3 Consumables and Repair Parts

3.4 Other Maintenance Services

4.0 Sustaining Support

4.1 System Specific Training

4.2 Support Equipment Replacement

4.3 Sustainment/Systems Engineering

4.4 Program Management

4.5 Information Systems

4.6 Data and Publications

4.7 Simulator Operations

4.8 Other Sustaining Support

5.0 Continuing System Improvements

5.1 Modifications or Modernization

5.2 Software Maintenance or Modification

6.0 Installation and Personnel Support

Total

3. For government-furnished equipment (GFE):

b.) Identify each subcontractor if known: otherwise enter "TBD" and its expected value and software development effort which, for CSDR purposes, Prime Contractor represents the expected price at contract completion (i.e., initial contract award plus all expected contract changes). This value must also be based upon the assumption that all contract options will be exercised.

c.) Using the WBS contained in block 10 of the CSDR Plan, annotate with "X" the elements for which the Prime contractor and each subcontractor have or

Prime(s) a.) Identify the contractor if known, otherwise enter "TBD" and include the estimated total contract value and the estimated total software development effort which, for CSDR purposes, represents the expected price at contract completion (i.e., initial contract award plus all expected contract changes). This value must be based upon the assumption that all contract options will be exercised.

1. The following information is mandatory for each prime contract:

WBS

NUMBERS

WBS Element Name with the contractor's name.

b.) Using the WBS contained in block 10 of the CSDR Plan, annotate with "X" the elements for which the source of GFE has or will have effort.

or willl have effort.

a.) Identify each source of GFE and its estimated total value and estimated total software development effort which, for CSDR purposes, represents the expected price at completion (i.e., initial funding plus all expected changes). This value must be based upon the assumption that all funding options will be exercised. If the GFE is already on contract, provide the assigned contract number between the government and the prime contractor, along

Example Resource Distribution Table (RDT) Aircraft System - Contract Plan

Prime Contractor or Sub-Contractor Total In-House Total Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Description

Contractor/Organization Name Contractor/Organization Location

Contract Number Total Program Office or Contract/Effort Value (Estimated), TY$M

Subtotal Software Contract Value (Estimated), TY$M Program Office

CSDR Direct Reporting per CWIPT (Yes/No) SRDR Direct Reporting per CWIPT (Yes/No)

L1 L2 L3 L4

1.0 Aircraft System

1.1 Air Vehicle

1.1.1 Airframe

1.1.1.1 Fuselage

1.1.1.2 Wing

1.1.1.3 Mechanical Subsystem

1.1.1.4 Hyraulic Subsystem

1.1.1.5 Electrical Subsystem

1.1.1.6 Integ., Assembly & C/O

1.1.2 Propulsion

1.1.3 AV Applications Software

1.1.4 AV System Software

1.1.5 Communications/Identification

1.1.6 Navigation/Guidance

1.1.7 Central Computer

1.1.8 Fire Control

1.1.9 Data Display and Controls

1.1.10 Survivability

1.1.11 Reconnaissaince

1.1.12 Automatic Flight Control

1.1.13 Central Integrated Checkout

1.1.14 Antisubmarine Warfare

1.1.15 Armament

1.1.16 Weapons Delivery

1.1.17 Auxiliary Equipment

1.1.18 Crew Station

1.2 Systems Engineering / Program Management

1.3 System Test and Evaluation

1.4 Training

1.5 Data

1.6 Peculiar Support Equipment

1.7 Common Support Equipment

1.8 Operational / Site Activation

1.9 Industrial Facilities

1.10 Initial Spares and Repair Parts

2. If known, the assigned contract number for each subcontract between the prime and a subcontractor must be included.

to the applicable rules established for the Program Plan RDT

WBS

NUMBER

Prime Contractor Subcontractors

WBS Element Name

1. Contract/subcontract information provided in the Contract Plan RDT must be consistent with the information provided in the Program Plan RDT. It must reflect the most current contract or subcontract value (including all mods or CLINs) and must conform

Other files

File Type Posted
W58RGZ-15-R-0045_Conformed_Contract_April_4,_2017.pdf PDF
W58RGZ15R0045-0006.pdf PDF
W58RGZ-15-R-0045_Conformed_Contract_March_27,_2017.pdf PDF
W58RGZ-15-R-0045_Conformed_Copy.pdf PDF
W58RGZ-15-R-0045_Amendment_0005.pdf PDF
W58RGZ-15-R-0045_0004_and_attachments.pdf PDF
SEMA_Conformed_Contract_22_June.pdf PDF
W58RGZ15R0045-0003.pdf PDF
W58RGZ-15-R-0045_Conformed_Solicitation_with_ALL_Attachments.pdf PDF
W58RGZ15R0045-0002_(PADDS).pdf PDF
W58RGZ15R0045-0001.pdf PDF
3rd_Set_of_SEMA_Questions_25_May_2016.pdf PDF
2ND_SET_OF_SEMA_QUESTIONS_11_MAY_2016.pdf PDF
SEMA_Questions_5_May_2016.pdf PDF
Attachment_0035_SEMA_B1_Matrix.xlsx XLSX spreadsheet
W58RGZ-15-R-0045.pdf PDF
Attachment_002_SEMA_CDRL —
Attachment_004_SEMA_DSL —
Attachment_023_SEMA_Appendix_S_PWS —
Attachment_035_FW_IUID_Plan_2014 —
Attachment_012_SEMA_Appendix_H_PWS —
Attachment_025_SEMA_Solicitation_Section_M —
Attachment_017_SEMA_Appendix_M_PWS —
Attachment_030_SEMA_GFP_Listing —
Attachment_019_SEMA_Appendix_O_PWS —
Attachment_027_SEMA_Sys_Eng_Process_Guide —
Attachment_018_SEMA_Appendix_N_PWS —
Attachment_010_SEMA_Appendix_F_PWS —
Attachment_013_Appendix_I_PWS —
Attachment_033_SEMA_Historical_Parts_Usage_Data —
Attachment_022_SEMA_Appendix_R_PWS —
Attachment_028_SEMA_DD254 —
Attachment_016_SEMA_Appendix_L_PWS —
Attachment_026_SEMA_Performance_Incentive_Plan —
Attachment_015_SEMA_Appendix_K_PWS —
Attachment_011_SEMA_Appendix_G_Reserved_PWS —
Attachment_024_SEMA_Solicitation_Section_L —
Attachment_001_SEMA_PWS —
Attachment_032_SEMA_Historical_FH_Rates —
Attachment_029_SEMA_QASP —
SEMA_Section_H —
Attachment_006_SEMA_Appendix_B_PWS —
Attachment_020_SEMA_Appendix_P_PWS —
Attachment_007_SEMA_Appendix_C_PWS —
Attachment_034_SEMA_Aircraft_B1_Matrix_Notional —
Attachment_003_SEMA_CDRL_Enclosure —
Attachment_005_SEMA_Appendix_A —
Attachment_031_SEMA_CR_Parts_for_CLIN_1004 —
Attachment_014_SEMA_Appendix_J_PWS —
Attachment_021_SEMA_Appendix_Q_PWS —
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .