W56HZV16R0024-0002.pdf

PDF 164 KB Posted

Attached to
FMTV A2 Production Effort Federal contract opportunity
Solicitation number
W56HZV16R0024
Issued by
Department of the Army Materiel Command Contracting Command Detroit Arsenal

About this file

Amendment 0002 - W56HZV16R0024

View the file

Other files for this federal contract opportunity

Other files attached to FMTV A2 Production Effort, newest first.
File Type Posted
Conformed_RFP_through_Amd_0008.pdf PDF
W56HZV16R0024-0008.pdf PDF
Attachment_0052_-_Vehicle_Dynamics_Data_Sheet_(30_Mar_2016).xlsx XLSX spreadsheet
W56HZV16R0024-0007.pdf PDF
Questions_and_Answers_Reference_Number_65.pdf PDF
W56HZV-16-R-0024_Conformed_Copy_through_Amendment_6.pdf PDF
Questions_and_Answers_Reference_Numbers_63-64.pdf PDF
W56HZV16R0024-0006.pdf PDF
Attachment_0067_-_Test_Summary_Report__(24_Jan_2017).pptx PPTX presentation
Questions_and_Answers_Reference_Numbers_61-62.pdf PDF
Questions_and_Answers_Reference_Numbers_56-60.pdf PDF
Questions_and_Answers_Reference_Numbers_49-55.pdf PDF
Questions_and_Answers_Reference_Numbers_34-46.pdf PDF
Attachment_0046_-_Performance_Requirements_Matrix_(20_Dec_2016).xlsx XLSX spreadsheet
W56HZV16R0024-0004.pdf PDF
W56HZV16R0024-0003.pdf PDF
Attachment_0046_-_Performance_Requirements_Matrix_(16_Nov_2016).xlsx XLSX spreadsheet
Attachment_0052_-_Vehicle_Dynamics_Data_Sheet_(16_Nov_2016).xlsx XLSX spreadsheet
W56HZV16R0024-0001.pdf PDF
Attachment 0026 - Draft FMTV Trailer De-Processing Checksheet.xls XLS spreadsheet
Attachment 0057 - Certification of Small Business Size and Socioeconomic Status for Subcontractors Not Registered In SAM.docx DOCX document
Attachment 0012 - Logistics Integrated Master Schedule.xlsx XLSX spreadsheet
Attachment 0005 - Windchill User Guide.pdf PDF
Attachment 0027 - Government Furnished Property and Equipment.xlsx XLSX spreadsheet
Attachment 0004 - PdM MTV Drawing and Modeling Standards and Best Practices.pdf PDF
Attachment 0028 - Lateral Transfer Request Form Template.xls XLS spreadsheet
Attachment 0055 - Vehicle Configuration Tables.xlsx XLSX spreadsheet
Attachment 0016 - Logistics Product Data - Packaging Data Products.doc DOC document
Attachment 0007 - Instructions for Preparing RFV Forms.pdf PDF
Attachment 0044 - Small Business Participation Factor Workbook Instructions.docx DOCX document
Attachment 0008 - Instructions for Preparing ERR Forms.pdf PDF
Attachment 0018- ATPD 2232 - Engines Preparation for Shipment and Storage Of.pdf PDF
Attachment 0029 - Fielding Schedule Template.xlsx XLSX spreadsheet
Attachment 0033 - Application of CPC.doc DOC document
Attachment 0032 - Overpaint Criteria.doc DOC document
Attachment 0017 - Incoming Transaction Format.doc DOC document
Attachment 0045 - TIR and FACAR Report Data.pdf PDF
Attachment 0049 - TDP BOM.xlsx XLSX spreadsheet
Attachment 0003 - TDP Option Selection Worksheet.docx DOCX document
Attachment 0053 - Failure Definition - Scoring Criteria.doc DOC document
Attachment 0061 - Hardware and Software List.xls XLS spreadsheet
Attachment 0067 - Test Summary Report.pptx PPTX presentation
Attachment 0013 - NMWR Candidate List.docx DOCX document
Attachment 0050 - Technical Maturity Rubric.docx DOCX document
Attachment 0020 - CDRS Search Request.pdf PDF
Attachment 0034 - CSDR Plan.pdf PDF
Attachment 0021 - Warranty SIC Parameter Requirements.docx DOCX document
Attachment 0014- Attribute Selection Worksheet.xlsx XLSX spreadsheet
Attachment 0035 - DD Form 254.pdf PDF
Attachment 0030 - Projected Net Classes.xlsx XLSX spreadsheet
Show all 50

FMTV A2 Production Effort has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

0002 2016DEC02

W56HZV

U.S. ARMY CONTRACTING COMMAND

WARREN, MICHIGAN 48397-5000

VICKI MISIAK

EMAIL: VICKI.L.MISIAK.CIV@MAIL.MIL

W56HZV-16-R-0024

2016OCT13

X

X

/SIGNED/

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 56

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: VICKI MISIAK

Buyer Office Symbol/Telephone Number: CCTA-HTA-A/(586)282-8394

Type of Contract 1: Firm Fixed Price

Type of Contract 2: Cost Plus Fixed Fee

Kind of Contract: System Acquisition Contracts

*** End of Narrative A0000 ***

Solicitation Number: W56HZV-16-R-0024

Amendment Number: 0002

1. Amendment 0002 to Solicitation Number W56HZV-16-R-0024 is being issued to incorporate the following revision:

A. Delete FAR clause 52.215-20, Alternate III.

B. Add FAR clause 52.215-20, Alternate IV.

C. Add FAR clause 52.215-21, Alternate III.

D. Revise Attachment 0001, Performance Specification FMTV.

E. Revise Attachment 0046, Performance Requirements Matrix.

F. Revise Attachment 0051, VCI Data.

G. Revise Attachment 0052, Vehicle Dynamics Data Sheets.

H. Revise Section C.6.11

I. Revise Section C.10.3.1

J. Revise Section C.10.4.1

K. Add Attachment 0069, "PEO CS&CSS OPSEC Plan"

L. Revise Attachment 0035, "DD Form 254"

M. Delete Attachment 0063, "TACOM LCMC OPSEC Plan"

N. Revise TACOM Clause 52.204-4022.

O. Revise the Volume Numbers in L.4.1, L.4.2, L.4.3, and L.4.4.

2. As a result of this Amendment, the following revisions are being made:

Section C_________

A. Section C.10.3.1 is changed from:

C.10.3.1 Unclassified information will be protected in accordance with Attachment 0062, "PEO CS&CSS Armoring Systems SCG" as well as Attachment 0063, "TACOM LCMCs OPSEC Plan", respective DOD and Army Regulations, and additional guidance provided above.

To:

C.10.3.1 Unclassified information will be protected in accordance with Attachment 0062, "PEO CS&CSS Armoring Systems SCG" as well as Attachment 0069, "PEO CS&CSS OPSEC Plan", respective DOD and Army Regulations, and additional guidance provided above.

B. Section C.10.4.1 is changed from:

C.10.4.1 When receiving, generating, and handling classified information, the Contractor shall adhere Attachment 0062, "PEO CS&CSS

Armoring Systems SCG", DoD 5220.22-M, Attachment 0063, "TACOM LCMCs OPSEC Plan" and Attachment 0035, "DD Form 254" and their respective continuation sheets.

2 56

W56HZV-16-R-0024 0002

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

To:

C.10.4.1 When receiving, generating, and handling classified information, the Contractor shall adhere Attachment 0062, "PEO CS&CSS

Armoring Systems SCG", DoD 5220.22-M, Attachment 0069, "PEO CS&CSS OPSEC Plan" and Attachment 0035, "DD Form 254" and their respective continuation sheets.

C. Section C.6.11 is changed from:

C.6.11 New Equipment Training: The Contractor shall develop and deliver Training Products that support operator, maintenance, and

IKPT Training. The Contractor shall develop and deliver the Training Products as part of the TSP to support operator and maintenance training conducted during NET. The Contractor shall provide a training program and shall brief status of the training program at the SOW conducted reflects the most current vehicle configuration. The Contractor shall develop, update, and document training and training materials in accordance with AR 350-1, AMC-R 350-6 and U.S. Army Training and Doctrine Command (TRADOC)

Regulation 350-70. The Contractor shall deliver training products in the Army Systems Approach to Training (ASAT) format. The

Contractor shall provide all necessary personnel, equipment and materials to conduct IKPT training in accordance with the

Government approved TSP.

To:

C.6.11 New Equipment Training: The Contractor shall develop and deliver Training Products that support operator, maintenance, and

IKPT Training. The Contractor shall develop and deliver the Training Products as part of the TSP to support operator and maintenance training conducted during NET. The Contractor shall provide a training program and shall brief status of the training program at the SOW meeting and subsequent MPP conferences. The Contractor shall ensure the training developed and conducted reflects the most current vehicle configuration. The Contractor shall develop, update, and document training and training materials in accordance with AR 350-1, and U.S. Army Training and Doctrine Command (TRADOC) Regulation 350-70. The process for developing Army learning products is analysis, design, development implementation, and evaluation (ADDIE). The Contractor shall provide all necessary personnel, equipment and materials to conduct IKPT training in accordance with the Government approved TSP.

D. Paragraph a. of TACOM Clause 52.204-4022, "Requirements for an OPESC Standing Operation Procedure/Plan" is revised from:

a. The contractor is subject to provisions of the TACOM LCMC OPSEC Standing Operating Procedures (SOP/Plan), or other U.S.

Government

OPSEC plan, per AR 530-1, Operations Security. This SOP/Plan specifies the governments critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.

To:

a. The contractor is subject to provisions of Attachment 0069, "PEO CS&CSS OPSEC Plan". This SOP/Plan specifies the governments critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.

Section I_________

A. FAR clause 52.215-21, Alternate III is added.

Section J_________

A. Attachment 0001, "Performance Specification FMTV" is revised from the document dated 01 Aug 2016 to the document dated 16 Nov

2016. Updates were made to requirements FMTV-PS-R-177 and FMTV-PS-R-178 to exclude the M1088A2 tractor variant, FMTV-PS-R-4617 to include the calculated combat gear weight for the 50th percentile soldier, and FMTV-PS-R-5540 is added to define the standard in which cab crew weight shall be calculated.

B. Attachment 0046, "Performance Requirements Matrix" is revised from the document dated 01 Aug 2016 to the document dated 16 Nov

2016. Revisions were made to exclude the M1088A2 from the Subfactor 4, Mobility requirement and move the M1087A2 to its own proposed level of performance under Subfactor 1, Payload.

C. Attachment 0051, "VCI Data" is revised from the document dated 01 Aug 2016 to the document dated 16 Nov 2016. Revisions were made to remove the M1088 tractor worksheet and provide clarification that all data is to be provided for vehicle at GVW in Armor

Configuration at CTIS tire inflation pressure for snow/mud/sand

D. Attachment 0052, "Vehicle Dynamics Data Sheets" is revised from the document dated 01 Aug 2016 to the document dated 16 Nov 2016.

Revisions were made to include which vehicle configurations require data inputs and to remove unnecessary data fields.

E. Attachment 0035, "DD Form 254" is revised from the document dated 01 Aug 2016 to the document dated 16 Nov 2016. Revisions were made to remove references to Attachment 0063, "TACOM LCMCs OPSEC Plan".

3 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

F. Attachment 0069, "PEO CS&CSS OPSEC Plan" is added.

G. Attachment 0063, "TACOM LCMCs OPSEC Plan" is deleted.

Section L_________

A. FAR clause 52.215-20 Alternate III is deleted.

B. FAR clause 52.215, Alternate IV is added.

C. Revise L.4.1 from "Volume I - Technical Factor" to "Volume 2 - Technical Factor".

D. Revise L.4.2 from "Volume II - Technical Maturity Factor" to "Volume 3 - Technical Maturity Factor"

E. Revise L.4.3 from "Volume III: Total Evaluated Cost/Price (TEC/P)" to "Volume 4 - Total Evaluated Cost/Price (TEC/P)"

F. Revise L.4.4 from "Volume IV - Small Business Participation (SBP) Factor" to "Volume 5 - "Small Business Participation (SBP)

Factor".

3. Except as specifically stated above, all other terms and conditions of the RFP remain unchanged.

*** END OF NARRATIVE A0003 ***

4 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

C-1 CHANGED 52.204-4022 REQUIREMENT FOR AN OPSEC STANDING OPERATION PROCEDURE/PLAN JAN/2014

(TACOM)

a. The contractor is subject to provisions of Attachment 0069, PEO CS&CSS OPSEC Plan". This SOP/Plan specifies the governments critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.

b. The contractor will receive a copy of the SOP/Plan at time of award. Local form STA Form 7114 (or similar) will be used to document and record security OPSEC reviews which are conducted by G2, TACOM LCMC or individual organizations supporting OPSEC Officers.

c. The contractor shall identify an individual who will be an OPSEC Coordinator. The contractor will ensure that this individual is

OPSEC Level I.

(End of Clause)

C.6 LOGISTICS: _________

The Contractor shall plan, develop, and complete the Logistics Product development necessary in order for the Government to complete TM

Authentication, Type Classification Standard, Full Materiel Release for materiel handoff to the First Unit Equipped (FUE) in accordance with the Logistic Integrated Master Schedule (LIMS) (Attachment 0012). To complete the logistic product development, the Contractor shall consider utilizing the current Interactive Electronic Technical Manuals (IETM); however, it is solely the Contractor's responsibility to validated the existing data in its entirety, ensure the existing data is accurate, usable, and represents the FMTV A2 production configuration. The Contractor shall validate all data utilized for this FMTV A2 effort.

If trailer configuration changes are necessary as a result of changes to the truck, the Contractor shall develop the same logistic products for both FMTV trucks and trailers as detailed in the Contract and Logistic Integrated Master Schedule.

During the course of program and logistic development, the Contractors Logistic Leadership shall attend CCB meetings to include the PDR, CDR, Test Readiness Review (TRR), and ECP reviews. During these reviews, the Contractor shall provide their comments, recommendations and impacts to TM Authentication, Type Classification Standard and Full Materiel Release.

The Contractor shall complete logistic development and logistics validation for assemblies common with the legacy configuration during the production of test assets and the testing phase.

C.6.1 Logistics Management and Administration: The Contractor shall designate a Product Support Manager (PSM) to ensure the achievement _______________________________________ of logistic program objectives within program cost and schedule. Additionally, the PSM shall possess the authority to manage, direct, and control the execution of all Product Support Elements (PSE) under this contract. The PSM shall conduct all Logistic meetings. The

Contractor shall conduct weekly IPT meetings through FRP decision to discuss IPS elements with the Government. In support of weekly IPT meetings, the Contractor shall present metrics in graphic form to the Government for development of logistics products that include the

Technical Publication work packages, provisioning data, training data, and packaging data with supporting data. The Government and the

Contractor will conduct weekly IPTs discussing Government and Contractor approved metrics. The Contractor shall deliver the metrics in a read ahead package IAW CDRL A001, "Agenda, Read Ahead, and Minutes".

C.6.1.1 Reserved

C.6.1.2 Product Support Management Review (PSMR): The Contractor shall host and conduct quarterly PSMR IAW SAE TA-STD-0017TM Activity ________________________________________

3.4.1. The Contractor shall discuss and review all CDRL deliveries, current logistic status updates, and the LIMS within SAE TA-STD-

0017TM Activity 2.1. The purpose of the PSMR is for the Contractor to provide a detailed presentation covering schedule, program status, upcoming meetings, identification of any problem areas, and mitigation plans for any schedule slippage. The Contractor may present any additional information at the PSMR pertinent to this effort; the agenda shall identify such information. The Contractor shall be responsible for taking minutes to capture status, key concerns, issues, and information exchanged. The Contractor shall deliver the agenda and meeting minutes in writing IAW CDRL A001, "Agenda, Read Ahead, and Minutes".

C.6.1.3 Reserved.

C.6.1.4 Contractor Responsibility for Timely Delivery of Logistics Products:______________________________________________________________________________

Acceptance of hardware end items will not proceed until the Contractor fully complies with all logistics products requirements under contract necessary to complete a full AR 700-142, Type Classification and Material Release. The Contracting Officer has the unilateral right to extend the FMTV delivery schedule of the FMTV's at no cost to the Government by the period of time equal to any delay on delivery and Government acceptance of logistic products required for Type Classification and Material Release. During this delay, the

Contractor shall store all MTVs and conduct Care of Supplies in Storage (COSIS) at no additional cost to the Government.

5 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

C.6.1.5 Errors: ______

C.6.1.5.1 Identification of Errors: Errors are defined as: items that do not meet the applicable standards specified within this scope _________________________ of work and as identified in the associated CDRL; tasks that cannot be performed as written, or identified within the Logistic Quality

Plan (LQP). During TM verification, the Government IPT will determine if the task is a Pass or a Fail based on the ability of the soldier to complete the task as written. Validator or maintainer preference cannot be considered an error that would be corrected at the Contractors cost. The Government will consider a preferential change as additional scope.

C.6.1.5.2 Rework: The Government defines rework as any deliverable rejected by the Government and returned to the Contractor for _______ correction. The Contractor shall deliver contract deliverables in accordance with the applicable CDRL, which are subject to Government acceptance or rejection. The Government COR will be the sole focal point for official CDRL rejection. The Contractor shall rework rejected Contract deliverables at no cost to the Government, before re-delivery to the Government for acceptance. The Contractor shall correct all errors found in the IETM, TMs, Training Support Package (TSP), Electronic Technical Manuals (ETM), logistics documents, and electronic data files resulting from Government reviews, tests, verification, demonstrations, or assessments at no additional cost to the Government. The Contractor shall deliver corrected data to the Government within CDRL prescribed timeframes.

C.6.1.6 CDRL Receipt and Acceptance: Contractor submission of a data item does not constitute receipt nor acceptance by the Government. _______________________

The COR will confirm data item receipt in writing. The Government bases acceptance of documentation on the completeness, accuracy, compatibility to applicable military standards and regulations of delivered documentation, and the adherence to applicable military specifications and standards and requirements of the applicable CDRL. The COR or PCO will provide written notice to the Contractor as to the status of its submission. The PCO will provide explanation of any rejection. The Government reserves the right to withhold final payment if data deliverables are delinquent. The Contractor shall be responsible for ensuring all data deliverables required by this

Contract are completed and accepted in order to meet the requirements specified.

C.6.1.7 TM Authority: Product Support Integration Directorate for FMTV (AMSTA-LCC-HM) is the designated Government TM, RPSTL, _____________ provisioning, and maintenance acceptance activity for this effort. AMSTA-LCC-HM will provide notification of comments through the COR.

If the Contractor receives comments or corrections from any Government activity, the Contractor shall forward these comments and corrections to the COR for direction.

C.6.1.8 Source Data: The Contractor shall deliver source data as an electronic editable file to the Government IAW CDRL C001, "Source ____________

Data". Source data includes illustrations, photos and MS Office Products. The Government reserves the right to record logistic efforts photographically or electronically, for instructional use or review. If the Contractor decides to claim a copyright to the presentation recorded by the Government, the Contractor shall grant to the Government a license to that copyrighted work for any and all uses the

Government will make of that recording.

C.6.1.9 Reserved.

C.6.1.10 Technical Publications, Provisioning and Related IPS Cost Report: The Contractor shall develop a Cost Report that provides the _________________________________________________________________

Government with the actual costs of IPS development. The Contractor shall deliver the report IAW CDRL C002, "ILS Cost Report".

C.6.1.11 Field Service Representative (FSR) Support __________________________________________

C.6.1.11.1 The Contractor shall provide FSR support for logistic and test events. The Contractor shall provide FSR support for inventories, hand off, and setup of the PSP. The Contractor shall be responsible for necessary repairs and the setup/tear down prior to and after each logistic event.

C.6.1.11.2 The Contractor shall provide an itemized list of repairs, repair parts, and the total cost of repairs including FSR labor IAW

CDRL C002, "IPS Cost Report".

C.6.2 Logistics Reports, Plans, and Data __________________________________

C.6.2.1 LIMS: The Contractors shall develop a plan to support full materiel release, type classification and the authentication of all _____

TMs and Technical Bulletins (TB) IAW the Governments LIMS (Attachment 0012, "LIM Schedule"). The Government will maintain the LIMS for the lifetime of the contract. The Contractor shall immediately notify the Government if they foresee a change to scheduled CDRL deliveries. Contractor notification shall include the reason for the change and a get-well plan. The Government reserves the right to review and approve or disapprove Contractor proposed LIMS updates.

C.6.2.2 Logistics Quality Plan (LQP): The Contractor shall implement and maintain a LQP to ensure logistic services are performed IAW _____________________________ this contract. The Contractor shall deliver the Logistics Quality Plan for Government review and approval IAW CDRL C004, "Logistic

Quality Plan". The Contractors LQP shall outline procedures to be implemented to identify and either prevent or ensure non-recurrence of defective services; it is the means of assuring the work complies with regulatory requirements. The LQP shall include a description of the inspection system to address logistic services listed in this contract.

C.6.2.2.1 The Contractor shall develop the LQP in accordance with the overall Contractor Quality Management System with the same procedures, methodologies and tools used in production. The Contractor shall audit, approve, or write Corrective Action Reports (CAR)

6 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

IAW E.2 Quality Program. The Contractor shall report the audit results of the their work or Subcontractors work to the Government IAW

E.2 and deliver the results IAW CDRL E006, "Error-Proofing Audit Results and Corrective Actions". The description shall include methods for identifying and preventing defects in the quality of services performed. The LQP shall include standard check sheets for common past error. If the Government Logistic Product Support Manager, Integrated Process Team (PSMIPT) discovers errors, the PSMIPT will ramp up a sampling program.

C.6.2.2.2 The Contractor shall provide a chapter in the LQP titled Technical Manual Quality Plan (TMQP) outlining the Contractors process leading to the delivery of TMs and NMWR for authentication while ensuring the quality of the TMs and the NMWRs produced under this contract. The Contractors execution of the TMQP shall consist of Quality Assurance (QA) personnel who are not the writers or editors of the publications being prepared. As part of the TMQP, the Contractor shall detail plans to maintain validation records showing publication corrections, deletions and additions identified during the publication validation and QA processes.

C.6.2.3 Technical Manual Plan: The Contractor shall prepare and deliver a TM Plan in accordance with Military Standard (MIL-STD)-40051 ______________________ and CDRL C005 "Technical Manual Plan". The purpose of this plan is to describe the development process the Contractor shall use to plan, gather data, author, illustrate, produce, review, and deliver the required publications that ensure Technical Manual authentication when required by the Government Logistic Integrated Master Schedule.

C.6.2.4 Logistic Configuration Summary: The Contractor shall develop and deliver an Executive Summary detailing updates to operation or _______________________________ maintenance impacting the FMTV trucks and trailers, including the legacy fleet, resulting from configuration changes. The Contractor shall deliver the Logistic Configuration Summary IAW CDRL C006, "Logistic Configuration Summary Report".

C.6.3. Program Events: For program events defined below, Contractor provided amenities may be required consisting of: facilities, ______________ mechanic support, office space, standard tools and shop equipment, printing support, internet connectivity and standard office support.

C.6.3.1 Logistic Start of Work Meeting ______________________________

C.6.3.1.1 The Contractor shall conduct a Logistic Start of Work Meeting (SOWM), at the Contractor's facility within 30 days after

Contract Award. This meeting shall introduce and align the Government and Contractor Logistic teams. The Logistic SOWM shall consist of a SOW review and an LIMS review. For planning purposes, this meeting is anticipated to be a three consecutive day event.

C.6.3.1.2 The Contractor shall present their organizational key roles at the Logistic SOWM and discuss the plan for communicating and transitioning personnel changes. The LIMS review shall verify the Contractor's use of a reliable performance baseline that includes the pertinent contract SOW, consistent with contract schedule requirements. Discussions at the meeting shall include contract requirements, the establishment of lines of communications, required plans and reports, and document delivery. For the SOWM, the Contractor shall deliver an agenda and read-ahead IAW CDRL A001, "Agenda, Read Ahead, and Minutes".

The Contractor shall present:

- The list of Contract Personnel and functional area

- The LIMS including staffing plan and Critical Path Analysis

- Tailoring Logistic Product Data Attribute Selection Worksheet

At the SOWM, the Government will:

-Review the SOW

-Identify Contractor support requirements for testing

-Review Support Equipment (SE) and Test Measurement and Diagnostic Equipment (TMDE)

-Discuss Packaging, Handling, Storage, and Transportation (PHS&T) requirements

-Discuss New Equipment Training (NET) requirements

-Provide an overview and conduct the initial Maintenance, Provisioning, and Publications Guidance Conference

-Discuss GFE and GFI

-Collaborate with the Contractor to Tailor Logistic Product Data Attribute Selection Worksheet

-Discuss the LQP and quality control process for product support development

- Discuss the Logistic Demonstration

C.6.3.2 Maintenance, Publications, and Provisioning (MPP) Guidance Conferences: The Contractor shall hold a MPP Guidance Conference _______________________________________________________________________ quarterly, starting in conjunction with the Logistic Start of Work Meeting. During the meeting, the Contractor shall present a detailed path and a graphic milestone presentation that defines Contractor performance to meet contract delivery requirements. The Contractor shall be prepared to discuss the following topics and relevant matters to ensure mutual understanding:

- Technical Manual Plan

- LQP

- Maintenance

- Special Tools and Test Equipment (STTE)

7 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

- Provisioning Guidance

- Publications Guidance

- New Equipment Training

C.6.3.2.1 MPP Reviews Overview: MPP Reviews are collaborative reviews between the Government and the Contractor to assess and discuss _____________________ logistic documentation development. The Government Maintenance Manager leads the MPP to address technical issues and concerns. The purpose of these events is to maintain consistent oversight and review of products in development to help ensure successful validation and verification. MPP Reviews will be the forum to facilitate Government review and acceptance of new or updated FMTV Technical Data.

The Contractor shall deliver a written agenda, take minutes to capture key concerns, issues, and information exchanged. The Contractor shall deliver the agenda and minutes in writing IAW CDRL A001, "Agenda, Read Ahead, and Minutes".

C.6.3.2.2 MPP Requirements: The Contractor shall have the logistic products listed below available for each MPP Review: _________________

- Maintenance Task Analysis (MTA)

- Maintenance Allocation Chart (MAC)

- Level of Repair Analysis (LORA)

- Expendable Durable Items List (EDIL)

- Mandatory Replacement Parts (MRP) List

- STTE List

- Critical Task List

- Sample Work Packages (maintenance, troubleshooting, Preventive Maintenance Checks and Services (PMCS), RPSTLs, and schematics)

- Sample Training Material (agendas, Program of Instruction (POIs))

- Electronic Maintenance System (EMS) Next Generation (NG) Software Report

C.6.3.3 Training Review Conference (TRC): The Contractor shall conduct a TRC to identify and resolve potential problems and discuss ________________________________ areas of mutual interest concerning training. The Contractor shall conduct the TRC concurrently with the MPP Reviews. The Contractor shall conduct the TRC to meet tester, trainer, maintainer, and user training requirements. The Contractor shall deliver TRC agenda and minutes as part of the MPP Review agenda and minutes IAW CDRL A001, "Agenda, Read Ahead, and Minutes".

C.6.3.4 Technical Publications Logistics Demonstration (LD): The Contractor shall participate in, facilitate and support LD efforts. ____________________________________________________

C.6.3.5 TM/NMWR Verification Events: The Contractor shall host and support verification events to ensure the technical publications are ____________________________ accurate and complete.

C.6.3.6 Training Events: _______________

C.6.3.6.1 Operator and Field Level Maintenance IKPT: The Contractor shall provide NET, Operator New Equipment Training (OPNET) and _________________________________________

Field Level Maintenance New Equipment Training (FLMNET) during Instructor Key Personnel Training (IKPT). The Contractor shall provide each participant a complete TSP, Student Guide, and Instructor Guide for both Operator and Field Level Maintenance training for 12 15 students.

C.6.3.6.2 The Contractor shall provide Operator and Field Level Maintenance familiarization training prior to the PVT, LD, OT (Operator

Familiarization Training Only) and Verification to validate the Contractors TSP.

C.6.4 Production Progress, Vehicle Tracking and Shipping Report: The Contractor shall deliver Production Progress reports as required by _________________________________________________________

FAR 52.242-2, entitled, "Production Progress Report". The Contractor shall prepare and deliver a Production Progress, Vehicle Tracking and Shipping Report spreadsheet IAW CDRL C008, "Vehicle Tracking and Shipping Report". Reporting is required for all truck and trailer

CLINs under this contract. This shall include all vehicle loans and vehicles returned to the Contractors site.

C.6.5 Maintenance Support Planning: The Contractor shall develop logistics documentation IAW AR 750-1, "Army Materiel Maintenance ____________________________

Management Policy", to ensure that the end item can be serviced, maintained, repaired, and overhauled at the lowest levels of support possible. The Contractor shall develop a Maintenance Support Plan that determines maintainability characteristics. The Contractor shall develop and document the Maintenance Support Plan using the results from the FMECA (C.6.5.2), Reliability Centered Maintenance (RCM) analysis (C.6.5.3) and LORA (C.6.5.6). The Contractor shall also find and incorporate commercially available reliability information in the development of this Maintenance Support Plan. The Maintenance Support Plan shall also include a summary consisting of supporting information from the RAM testing that justifies the need for maintenance actions (e.g., failure modes). Other reliability and maintainability data shall consist of task frequency, failure rate of an item or mean time between failure, mean time to repair an item, mean time between maintenance actions, mean time between removals, operational availability, Maximum Time to Repair and Mean Time to

Repair (MTTR) Percentile. The summary shall be broken down within the hierarchy of the end item by major components and delivered IAW

CDRL C009, "Maintenance Support Plan" and AR 700-127, "Integrated Product Support". The Contractor shall use the Government approved

Maintenance Support Plan for TM development. The Contractor shall develop and deliver a Maintenance Support Plan as part of activity

12, within the SAE TA-STD-0017TM.

C.6.5.1 Product support analysis and logistics product data ___________________________________________________

C.6.5.1.1 Product Support Analysis Plan: The Contractor shall develop and implement a Product Support Analysis Plan (PSAP) during SAE TA- ______________________________

8 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

STD-0017TM Activity 1, 2.1, and 2.2. The Contractor shall deliver the PSAP IAW CDRL C010, "Product Supportability Analysis Plan".

C.6.5.1.1.1 The Contractor shall develop a PSAP that will provide the detailed outline for the Product Support Analysis (PSA). The PSA shall form the basis for logistic product development. The PSAP shall address the end item in terms of operator and maintenance tasks and the associated support resources required for system supportability and readiness. Within the PSAP, the Contractor shall include separate chapters detailing PSMR, MPP, TM Development and Authentication, Provisioning, Training and Logistic events including LD, OT, TM and NMWR Verification, and TSP development to support IKPT and NET.

C.6.5.1.2 LPD: The Contractor shall develop Logistics Product Data (LPD) IAW the current SAE TA-STD-0007TM, SAE TA-HB-0007-1TM and ___

Attachment 0014, "Attribute Selection Worksheet" based on the different Product Support Analysis activity numbers and headings (e.g., Maintenance Support Planning, Activity # 2, Logistics Support Analysis (LSA)-004, LSA-019 and LSA-030).

The Contractor shall input, maintain and update LPD in the PowerLOG-J application. The Contractor shall deliver source data and file formats that allow the Government to directly upload into PowerLOG-J without corrections or modifications. When encountering errors with

PowerLOG-J, the Contractor shall work with the Logistics Support Activity (LOGSA) POC below to resolve issues.

PowerLOG-J HOTLINE: 256-955-9847

DSN: 645-9847

COMM: 256-955-9847

EMAIL: mailto:logsa.powerlog.help@conus.army.mil

LOGSA provides this service at no cost to the Contractor.

C.6.5.1.2.1 The Contractor shall produce and deliver IPS products for FMTV as an integral part of the design, development and integration process. The Contractor shall address all applicable and related elements of logistics that will focus on the highest possible system availability at the lowest life cycle cost.

C.6.5.1.2.2 The Contractor shall appoint Logistics Support Analysis (LSA) and LPD focal points to coordinate design interface activities supporting LSA and LPD tasks and subtasks required to develop and produce the required logistics products used by the Government.

C.6.5.1.2.3 LPD Summaries: The Contractor shall deliver all LPD reports in LSA format with the product data summaries. The format for ______________ each LPD summary is contained in the "Report Format" section of SAE-TA-HB-0007-1, per the corresponding activity name and number.

C.6.5.1.2.4 Logistic Product Data Source Files: The Contractor shall deliver Government approved Logistics Product Data (LPD) source _____________________________________ files in an Extensible Markup Language (XML) format, along with a written executive summary and the associated Logistics Product Summary activities as defined within SAE TA-STD-0017TM.

C.6.5.1.2.5 Logistic Product Data Repository: The Contractor shall establish a supportability analysis database and Logistics Product _________________________________

Data Repository, to store logistics product data. The Contractor shall ensure the data is cybersecurity protected with built in redundancy that ensures data integrity and no physical loss. The Contractor shall deliver final updated logistics product data to the

Government, in its entirety (deliver a full exchange file), before the end of the period of performance of the contract.

C.6.5.2 FMECA (LSA-056) _______________

C.6.5.2.1 The Contractor shall conduct a FMECA analysis, IAW the SAE TA-STD-0017TM Activities 9.3-9.5, and American National Standards

Institute (ANSI)/ Automotive Aftermarket Industry Association (AAIA) Standard S-102.2.4-2009. The Contractor shall deliver the Logistic

Product source data files and the associated Logistics Product Summary IAW CDRL C011, "Failure Mode, Effects and Criticality Analysis

(FMECA)".

C.6.5.2.2 The Contractor shall develop a tailored FMECA that addresses the critically analysis through failure probability levels including frequency, reasonability, probability, occasional, remote or extremely unlikely. The Contractor shall complete a FMECA for major assemblies and items with a high failure effect probability and an assigned severity classification in Categories 1-3. The FMECA results shall identify failure predictability, detection means, maintenance actions that identify the maintainability critical tasks needed for the Logistic Demonstration Readiness Review (LDRR) and successful completion of the logistic demonstration phase.

The Contractor shall use the FMECA to determine probability of failure modes at the functional and piece-part level. The Contractor shall use this analysis as the foundation for the Operator Critical Task List and the Maintenance Critical Task List. The Contractor shall generate FMECA reports for all FMTV variants. The Contractor shall ensure the FMECA reports are updated and available for

Preliminary Technical Manual (PTM) reviews, LD events and Verifications.

C.6.5.3 RCM ANALYSIS (LSA-050): The Contractor shall conduct a RCM analysis for the FMTV, within SAE TA-STD-0017TM Activity 9.7. The ______________________

Contractor shall deliver the Logistic Product source data files and the associated Logistics Product Summary IAW CDRL C012, "Reliability

Centered Maintenance (RCM)".

C.6.5.3.1 The Contractor shall conduct the RCM analysis process activity concentrating on critical failures that result in catastrophic

9 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

mission, safety or environmental failures. The Contractor shall conduct the RCM analysis as a systematic approach for identifying preventative scheduled maintenance tasks for the end item, and establishing preventative maintenance scheduled task intervals. The

Contractor shall ensure the RCM analysis develops a maintenance schedule to enhance that reliability of the end item by implementation of maintenance tasks prior to the failure occurrence of the component in question. The consolidated results from the RCM analysis process shall form the basis of a Preventive Maintenance Checks and Services (PMCS) program for the system. The Contractor shall conduct the RCM analysis to determine PMCS tasks to improve equipment reliability for the life cycle. The Contractor shall use the information generated by FMECA that identifies probable failure modes and hardware components that have the greatest effect on the equipment reliability and availability for the RCM analysis. Using the decision tree process of RCM analysis, the Contractor shall complete an analysis of each functionally significant item and their assigned failure modes. The intent of the analysis is to determine which preventive maintenance tasks are necessary to support the system.

C.6.5.3.2 As a result of the RCM analysis, the Contractor shall prepare, host and conduct a PMCS review meeting NLT 60 days prior to the start of RAM testing and again 120 days after the start of RAM testing. The purpose of the meeting is to review the Contractors

Operators and Maintenance PMCS schedule for the FMTV to determine if the task(s) are:

- arranged for efficiency

- assigned the appropriate maintenance level

- a candidate for interval change or elimination

The Contractor shall ensure representatives from Engineering, Test, and Logistics are involved in this effort. The first meeting is anticipated to be a two (2) day event and the second meeting a 1 day event. The results of the first meeting will establish a baseline

PMCS that will be evaluated in test. The second meeting is intended to identify and incorporate recommended changes coming from test that will be used to re-baseline the PMCS and allow further evaluation in the test program. The Contractor shall provide a read ahead package, agenda and minutes of the meeting, IAW CDRL A001, "Agenda, Read Ahead, and Minutes".

C.6.5.3.3 The Contractor shall conduct and deliver IAW CDRL C013, "PMCS and Scheduled Services Analysis" a PMCS and Scheduled Services analysis with recommendations to support a reduction in the overall maintenance burden with no decrement to safety, readiness, serviceability or availability. The Governments goal of the analysis and recommendations is to reduce time, frequency, resources and cost associated with PMCS, Scheduled Service and unscheduled maintenance requirements.

C.6.5.3.4 PMCS Report (LSA-033): The Contractor shall conduct a PMCS analysis for the FMTV, within SAE TA-STD-0017TM Activity 9.7. ______________________

The Contractor shall deliver the Logistic Product source data files and the associated Logistics Product Summary IAW CDRL C013, "PMCS

Report".

C.6.5.4 Critical Maintenance Task List (LSA-006): The Contractor shall conduct a Logistic Analysis to develop a Critical Maintenance ________________________________________

Task List (LSA-006) Summary during SAE TA-STD-0017TM Activity 12. The Contractor shall populate data attributes in the logistics product data file to generate an LSA-006. The Contractor shall deliver the Logistic Product source data files and the associated

Logistics Product Summary IAW CDRL C014, "Critical Maintenance Task Summary".

C.6.5.5 Task Inventory: The Contractor shall analyze the results of the FMECA to identify and document corrective maintenance task ______________ requirements. The Contractor shall develop a task inventory within SAE TA-STD-0017TM Activity 9.8, 12, 12.1 and 12.2 and deliver IAW

CDRL C015, "Task Inventory".

C.6.5.6 LORA: The Contractor shall conduct a LORA as prescribed within SAE TA-STD-0017TM Activity 11.7 IAW SAE AS1390TM, utilizing the ____

Computerized Optimization Model for Predicting and Analyzing Support Structure (COMPASS) available at https://www.logsa.army.mil/lec/compass/. The Contractor shall utilize the current version of COMPASS at time of CDRL delivery. The

Contractor shall deliver the LORA IAW CDRL C016, "Level of Repair Analysis". The Contractor shall input, maintain and update all associated LORA LPD in the COMPASS application.

C.6.5.6.1 The LORA shall determine the maintenance level at which the items should be repaired or replaced. The Contractor shall include economic and non-economic criteria in this analysis. Non-economic criteria that could impact the level of maintenance decision include manpower and personnel implications, support equipment, and facilities availability in accordance with the Army two level maintenance concept. The Contractor shall address factors such as availability of replacements and the effect on operational readiness. The

Contractor shall incorporate results of this analysis in the MAC and in the TMs.

C.6.5.6.2 The Contractor shall develop a NMWR Candidate List IAW CDRL C016, "Level of Repair Analysis". The NMWR candidate list shall consist of repairable assemblies. The Government will review the NMWR Candidate list to identify which items are to have NMWRs developed.

C.6.5.7 MTA: The Contractor shall conduct a MTA within SAE TA-STD-0017TM Activity 12. The Contractor shall populate data attributes in ____ the logistics product data file to generate an LSA-019. The Contractor shall deliver the Logistic Product source data files and the associated Logistics Product Summary IAW CDRL C017, "Maintenance Task Analysis".

C.6.5.7.1 The Contractor shall develop a MTA to encompass all operator, maintainer, and support personnel tasks as identified by LORA, RCM Analysis, FMECA, utilizing the Operational Mode Summary (OMS)/Mission Profile (MP). The Contractor shall perform the MTA on the approved Product Baseline including the results of the latest RAM, safety, health hazards, and human factors engineering analyses. The

10 56

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Contractor shall update the MTA to reflect changes to the Product Baseline and the results from testing, training, quality, manufacturing, LD, and other FMTV evaluations.

C.6.5.7.2 The Contractor shall analyze the operational, maintenance and support function of the system in the identification of required operator and maintenance tasks. AR 750-1 Army Materiel Maintenance Management Policy will drive the maintenance of the end item. The analysis shall be reliability-centric and identify maintenance functions, levels of maintenance, manpower, spare parts, support equipment, and the time required to perform tasks. Analysis shall determine maintenance requirements and functions based on:

- Identification of components that are critical in terms of mission

- Components whose functional failure will not be evident to the operator

- Economical and operational consequences of failure

- Where scheduled maintenance can prevent failure.

C.6.5.8 Manpower Requirements Criteria (MARC) (LSA-065): The Contractor shall conduct a Logistic Analysis within SAE TA-STD-0017TM ________________________________________________

Activity 12 to determine Manpower Requirements Criteria. The Contractor shall populate data attributes in the logistics product data file to generate an LSA-065. The Contractor shall deliver the Logistic Product source data files and the associated Logistics Product

Summary IAW CDRL C018, "Manpower Requirements Criteria (MARC)".

C.6.5.9 Annual Man-Hour by Skill Specialty Code and Level of Maintenance (LSA-001): The Contractor shall conduct a Logistic Analysis to ___________________________________________________________________________ determine the annual Man-Hour by Skill Specialty Code and Level of Maintenance within SAE TA-STD-0017TM Activity 12. The Contractor shall populate data attributes in the logistics product data file to generate an LSA-001. The Contractor shall deliver the Logistic

Product source data files and the associated Logistics Product Summary IAW CDRL C019, "Annual Man-Hour by Skill Specialty Code and Level of Maintenance".

C.6.5.10 MAC (LSA-004): The Contractor shall conduct a Logistic Analysis to develop a MAC within SAE TA-STD-0017TM Activity 12. The _____________

Contractor shall populate data attributes in the logistics product data file to generate an LSA-004. The Contractor shall deliver the

Logistic Product source data files and the associated Logistics Product Summary IAW CDRL C020, "Maintenance Allocation Chart".

C.6.5.11 Transportability Report (LSA-085): The Contractor shall conduct a Logistic Analysis within SAE TA-STD-0017TM Activity 4, 9, ________________________________

11.12, 12.7 to develop the Transportability Report. The Contractor shall populate data attributes in the logistics product data file to generate an LSA-085. The Contractor shall deliver the Logistic Product source data files and the associated Logistics Product Summary

IAW CDRL C021, "Transportability Report".

C.6.5.12 Demilitarization (DEMIL) & Disposal Plan: The Contractor shall develop a DEMIL and Disposal Plan for the FMTVs, as prescribed _________________________________________ within SAE TA-STD-0017TM Activity 16-16.2 and DODI 4160.28, DOD 4160.21-M, and AR 700-144, "Demilitarization and Trade Security

Controls". The Contractor shall deliver the plan and executive summary IAW CDRL C022, "Demilitarization (DEMIL) & Disposal Plan".

C.6.5.13. Hazardous Materials Summary Report (LSA-078): The Contractor shall conduct a Logistic Analysis within SAE TA-STD-0017TM _______________________________________________

Activity 11, 12.8, 14 and 16 to develop the Hazardous Materials Summary Report. The Contractor shall populate data attributes in the logistics product data file to generate an LSA-078. The Contractor shall deliver the Logistic Product source data files and the associated Logistics Product Summary IAW CDRL C023, "Hazardous Material Summary Report".

C.6.5.14. Long Lead Time Items (LLTI): LLTIs are parts identified that require advance ordering to meet delivery schedules. LLTI may be ____________________________ items that; are complex in design, involve a complicated manufacturing process, have limited production capacities or cause extended production procurement cycles beyond six (6) months. The Contractor shall identify and document LLTIs as referenced in AR 700-18, "Provisioning of US Army Equipment". The Contractor shall screen the entire Bill of Material (BOM) including MRP, EDIL, STTE, Initial

Support Package (ISP) list and Authorized Stocking List (ASL) for LLTIs. The Contractor shall deliver the LLTI list IAW CDRL C024 "Long

Lead Time Item List".

The Contractor shall pre-screen the LLTI list with Defense Logistic Information System (DLIS) prior to delivery. Upon Government approval of the LLTI list, the Contractor shall ensure that all LLTIs that are part of the PSP required for logistic or test events are available 30 days prior to the designated effort.

C.6.5.15. Authorization List Items Report (LSA-040): The Contractor shall conduct a Logistic Analysis within SAE TA-STD-0017TM Activity __________________________________________

11, 12.8 and 14 to determine and document required…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .