This document outlines a solicitation for construction services to alter and add to an F-35 Squadron Operations facility. The solicitation will result in a single firm fixed-price construction contract valued between $1-5 million to reconfigure approximately 4,300 square feet of existing space at Dane County Regional Airport in Madison, Wisconsin for F-35 operations. Work includes demolishing interior walls, constructing new spaces, and modifying mechanical, plumbing, electrical and technology systems. Strict adherence to provided plans and specifications is required. The solicitation includes base and optional work, and offers a HubZone preference. The contract duration is 365 days from notice to proceed. Interested parties must attend a pre-proposal site visit on December 28, 2020. Proposals are due January 20, 2021 and will be evaluated for technical merit, past performance and price. Award will be made without discussions to the best value offer.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F-35 Add/Alter B404 Q&A 6
Q44. There have been several questions and answers posted to the solicitation, including changes to the bid form on beta.sam. Will the solicitation be amended per FAR 15.206 to address these changes so that the Offerors can acknowledge these changes?
Yes, it has been posted with this posting. Please note that there is not a modification 0001. There was a system glitch that pushed the mod to 0002. You should only be acknowledging the one modification.
Q45. What type of carpet is currently installed in the building? Plans state to remove and salvage carpet for reinstallation. If it is glued down, it cannot be salvaged and reinstalled. Please advise. Carpet product data is outlined on Sheet A-601 of the Drawings.
Q46. Are there any existing secure area computers or servers with critical power needs that will require a generator during power switch over?
The facility will be completely cleared of all classified materials.
Q47. Keynote 4.134 on page A-121 states that All walls (existing and new) above the ceiling up to roof deck, provide a level 5 gyp finish and paint to match color below. Previous work at existing walls were left with a painted, level 1 finish. Remediate deficiencies at penetrations, gyp bd joints, and screws, and may require a complete skim coat. Please provide photos of these conditions in these areas so offerors can provide accurate pricing.
See attached photos. Simply put; the level of finish you expect to see at eye-level must be extended from true-floor (concrete) to true-ceiling (roof decking). There should be no noticeable finish distinction along the wall.
NOTE: This is the last set of questions that were asked. NO further questions will be accepted.
File details come from the government source that posted it. Updated .