This document summarizes a federal solicitation for construction services to alter an F-35 aircraft hangar. The solicitation will result in a single fixed-price construction contract to demolish approximately 20,000 square feet of hangar shop space and modify an additional 20,000 square feet of hangar space at Truax Field in Madison, Wisconsin. Work includes mechanical, plumbing, electrical, and communications systems installation; fire suppression system modifications; aircraft power and air systems; and security upgrades. The solicitation includes two options and requires several brand-specific products. The response due date is March 8, 2021, with an award to the responsive and responsible lowest bidder. The project value is between $10-25 million and is designated for the North American Industry Classification code 236220 with a $39.5 million size standard. The pre-bid conference is February 16, 2021 and the solicitation is available on beta.SAM.gov.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 Alter Hangar 406, newest first.
File Type Posted
SF1419 Abstract of Offers - No Hubzone Preference.pdf PDF
W50S9F21B00010007.pdf PDF
406 Questions and Answers_142-143.pdf PDF
23 07 00_Add04.pdf PDF
W50S9F21B00010005.pdf PDF
C-121_Add03.pdf PDF
C-504_Add03.pdf PDF
34 71 13.19_Add03.pdf PDF
01 45 00.00 10_Add03.pdf PDF
22 31 00_Add03.pdf PDF
T-121 Add03.pdf PDF
F-001_Add03.pdf PDF
Asbestos and Lead Inspection.pdf PDF
Repair Roofs 406 Warranty Cert.pdf PDF
A-401_Add02.pdf PDF
04 20 00_Add02.pdf PDF
A-501_Add02.pdf PDF
A-601_Add02.pdf PDF
02 83 00_Add02.pdf PDF
01 14 00_Add02.pdf PDF
01 11 00_Add02.pdf PDF
406 Questions and Answers_26-112.pdf PDF
G-001_Add02.pdf PDF
E-101_Add02.pdf PDF
01 50 00_Add02.pdf PDF
12 21 00_Add02.pdf PDF
10 14 00.20_Add02.pdf PDF
05 40 00_Add02.pdf PDF
01 78 00_Add02.pdf PDF
W50S9F21B00010004.pdf PDF
C-141_Add02.pdf PDF
G-011_Add02.pdf PDF
07 27 26_Add01.R1.pdf PDF
A-131_Add01.R1.pdf PDF
C-121_Add01.R1.pdf PDF
W50S9F21B00010003.pdf PDF
10 22 39_Add01.R1.pdf PDF
W50S9F21B00010002.pdf PDF
B.07.406 Site Visit Sign In 19Feb21.pdf PDF
B.07.406 Site Visit Sign In 22Feb21.pdf PDF
Pre-Bid Slides - F-35 406.pptx PPTX presentation
W50S9F21B00010001.pdf PDF
ATTACHMENT 4-Justification and Approval Advantor.pdf PDF
ATTACHMENT 1-Truax F-35 B406 XGFG182008 Specs Vol 1 of 2 Dated 31 July 2020.pdf PDF
ATTACHMENT 5-Justification and Approval Andover.pdf PDF
W50S9F-21-B-0001.pdf PDF
ATTACHMENT 6-Justification and Approval Monaco.pdf PDF
ATTACHMENT 8-406 Submittal Log.xlsx XLSX spreadsheet
ATTACHMENT 9-SFS Form 12.xls XLS spreadsheet
ATTACHMENT 10-PRE-BID CONFERENCE AND SITE VISIT INSTRUCTIONS.pdf PDF
Show all 50

F-35 Alter Hangar 406 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRUAX FIELD ANGB - F-35: ALTER BLDG 406 Addendum 1

XGFG182008 24 FEB 2021

SECTION 32 92 19

SEEDING

08/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. DEPARTMENT OF AGRICULTURE (USDA)

AMS Seed Act (1940; R 1988; R 1998) Federal Seed Act

1.2 DEFINITIONS

1.2.1 Stand of Turf

95 percent ground cover of the established species.

1.3 RELATED REQUIREMENTS

Section 31 00 00 EARTHWORK, applies to this section with additions and modifications herein.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Fertilizer

Include physical characteristics, and recommendations.

SD-06 Test Reports

SD-07 Certificates

State Certification and Approval for Seed

SD-08 Manufacturer's Instructions

Erosion Control Materials

SECTION 32 92 19 Page 1

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery

1.5.1.1 Seed Protection

Protect from drying out and from contamination during delivery, on-site storage, and handling.

1.5.1.2 Fertilizer Delivery

Deliver to the site in original, unopened containers bearing manufacturer's chemical analysis, name, trade name, trademark, and indication of conformance to state and federal laws.

1.5.2 Storage

1.5.2.1 Seed, Fertilizer Storage

Store in cool, dry locations away from contaminants.

1.5.2.2 Topsoil

Stockpile topsoil to be salvaged and protect the pile from sediment transport with silt fence, sediment logs, tarps, or temporary seed.

1.5.2.3 Handling

Do not drop or dump materials from vehicles.

1.6 TIME RESTRICTIONS AND PLANTING CONDITIONS

1.6.1 Restrictions

Do not plant when the ground is frozen, snow covered, muddy, or when air temperature exceeds 90 degrees Fahrenheit.

1.7 TIME LIMITATIONS

1.7.1 Seed

Apply seed within twenty four hours after seed bed preparation.

PART 2 PRODUCTS

2.1 SEED

2.1.1 Classification

Provide State-approved seed of the latest season's crop delivered in original sealed packages, bearing producer's guaranteed analysis for percentages of mixtures, purity, germination, weedseed content, and inert material. Label in conformance with AMS Seed Act and applicable state seed laws. Wet, moldy, or otherwise damaged seed will be rejected. Field mixes will be acceptable when field mix is performed on site in the presence of the Contracting Officer.

SECTION 32 92 19 Page 2

2.1.2 Seed Mixtures

Seed shall meet the requirement of WisDOT standard specification section 630.

WisDOT Mix No. Use

40 Lawn Areas

Oats Temporary

Proportion seed mixtures by weight. Temporary seeding must later be replaced by seed mix No. 40 for a permanent stand of grass.

2.2 TOPSOIL

2.2.1 On-Site Topsoil

Surface soil stripped and stockpiled. When available topsoil must be existing surface soil stripped and stockpiled on-site in accordance with Section 31 00 00 EARTHWORK.

2.2.2 Off-Site Topsoil

Conform to requirements specified in paragraph COMPOSITION. If required, additional topsoil must be furnished by the Contractor. Imported topsoil shall be organic soil, free of stones larger than a 1/2 inch, roots, vegetation or other contaminents. Imported topsoil shall be observed and approved by the Contracting Officer prior to placement.

2.3 FERTILIZER

2.3.1 Granular Fertilizer

Use Type A fertilizer, meeting the requirements of WisDOT standard specification section 629.

2.4 WATER

Source of water must be approved by Contracting Officer and of suitable quality for irrigation, containing no elements toxic to plant life.

2.5 EROSION CONTROL MATERIALS

Erosion control material must conform to the following:

2.5.1 Erosion Control Tackifier

Hydrophilic colloids must be physiologically harmless to plant and animal life without phytotoxic agents. Colloids must be naturally occurring, silicate powder based, and must form a water insoluble membrane after curing. Colloids must resist mold growth.

2.5.2 Erosion Control Fence (Silt Fence)

Silt Fence shall meet the requirements of WisDOT standard specification section 628.

SECTION 32 92 19 Page 3

2.5.3 Inlet Protection Fabric

Fabric shall meet the requirements of WisDOT standard specification section 628.

2.5.4 Sediment Logs (Temporary Ditch Checks)

Sediment logs shall be 12" diameter and shall be listed on the WisDOT Product Acceptability List (PAL).

2.5.5 Erosion Control Material Anchors

Erosion control anchors must be as recommended by the manufacturer.

PART 3 EXECUTION

3.1 PREPARATION

3.1.1 EXTENT OF WORK

Provide soil preparation prior to planting, fertilizing, seeding, and surface topdressing of all newly graded finished earth surfaces, unless indicated otherwise, and at all areas inside or outside the limits of construction that are disturbed by the Contractor's operations.

3.1.1.1 Topsoil

Provide 4 inches of on-site or imported topsoil to meet indicated finish grade. After areas have been brought to indicated finish grade, incorporate fertilizer into soil a minimum depth of 2 inches by disking, harrowing, tilling or other method approved by the Contracting Officer.

Remove debris and stones larger than 3/4 inch in any dimension remaining on the surface after finish grading. Correct irregularities in finish surfaces to eliminate depressions. Protect finished topsoil areas from damage by vehicular or pedestrian traffic.

3.1.1.2 Fertilizer Application Rates

Apply fertilizer at a rate of 7 pounds per 1000 sq. ft.

3.2 SEEDING

3.2.1 Seed Application Seasons and Conditions

Immediately before seeding, restore soil to proper grade. Do not seed when ground is muddy, frozen, snow covered, or in an unsatisfactory condition for seeding. Apply seed within twenty four hours after seedbed preparation.

Sow seed by approved sowing equipment. Sow one-half the seed in one direction, and sow remainder at right angles to the first sowing.

3.2.2 Seed Application Method

Seeding method must be broadcasted and drop seeding.

3.2.2.1 Broadcast and Drop Seeding

Seed must be uniformly broadcast at the rate of 2 pounds per 1000 square feet. Use broadcast or drop seeders. Sow one-half the seed in one direction, and sow remainder at right angles to the first sowing. Cover

SECTION 32 92 19 Page 4 seed uniformly to a maximum depth of 1/4 inch in clay soils and 1/2 inch in sandy soils by means of spike-tooth harrow, cultipacker, raking or other approved devices.

3.2.3 Mulching

3.2.3.1 Non-Asphaltic Tackifier

Hydrophilic colloid must be applied at the rate recommended by the manufacturer, using hydraulic equipment suitable for thoroughly mixing with water. A uniform mixture must be applied over the area.

3.2.4 Erosion Control Material

Install in accordance with manufacturer's instructions, where indicated or as directed by the Contracting Officer.

3.2.5 Watering

Start watering areas seeded as required by temperature and wind conditions. Apply water at a rate sufficient to insure thorough wetting of soil to a depth of 2 inches without run off. During the germination process, seed is to be kept actively growing and not allowed to dry out.

3.3 PROTECTION OF SEEDED AREAS

Immediately after seeding, protect area against traffic and other use.

3.4 RESTORATION

Restore to original condition existing seeded areas which have been damaged during seed installation operations at the Contractor's expense. Keep clean at all times at least one paved pedestrian access route and one paved vehicular access route to each building. Clean other paving when work in adjacent areas is complete.

-- End of Section --

SECTION 32 92 19 Page 5

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 32 92 19 Page 6

File details come from the government source that posted it. Updated .