This amendment modifies an existing federal contract solicitation to alter an F-35 aircraft hangar at Dane County Regional Airport - Truax Field in Madison, Wisconsin. The scope of work includes demolishing approximately 20,000 square feet of existing hangar shop space and reconfiguring the area for F-35 aircraft maintenance operations. An additional 20,000 square feet of hangar space will be modified to accommodate F-35 aircraft, including fire suppression and electrical systems upgrades. The contract will award on a single fixed-price basis for both demolition and new construction work. Two optional line items are included for a fire protection runoff storage trench and infill slab. The pre-bid conference is scheduled for February 16, 2021 with bids due by March 8, 2021. The North American Industry Classification Code is 236220 and the contract value is estimated between $10-25 million. The solicitation and plans are available through the SAM.gov website.
View the file
Other files for this federal contract opportunity
Show all 50
F-35 Alter Hangar 406 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XGFG182008
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to replace Specification Table of Contents (TOC) w ith revised Specification TOC, replace Section 07 24 00 w ith revised Section 07 24 00, replace Section 07 27 26 w ith revised Section 07 27 26, replace Section 09 67 23.13 w ith completely new Section 09 67 23.13, delete Section 10 22 26.13 and replace w ith new Section 10 22 39, replace Section 32 92 19 w ith revised Section 32 92 19, replace Sheet A-131 w ith revised Sheet A-131 w ith colored markings, replace Sheet A-201 w ith revised Sheet A-201 that has added Keyed Note 4.221, replace C-101 w ith revised C-101, replace C-121 w ith revised C-121, and attached Geotechnical Exploration and Analyses report.
The bid due date of 15 March 2021 remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Mar-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S9F21B0001
X 9B. DATED (SEE ITEM 11)
04-Feb-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Mar-2021
CODE
USPFO WI 115 MISSION SUPPORT CONTRACTING
3110 MITCHELL ST BLDG 500
MADISON WI 53704-2591
W50S9F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W50S9F21B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003 CHANGES
Amendment 0003 consists of changes to the specifications and drawings listed below. Revised specifications and drawings are also provided with this amendment.
Changes to specifications:
A. Specification TOC
1. Replace Specification Table of Contents (TOC) with Revised Specification TOC.
B. Section 07 24 00
1. Replace Section 07 24 00 with revised Section 07 24 00 that includes changes below:
a. Deleted Parts 2.4 and 3.3.2.1 that referenced mechanical attachments of insulation in original Section 07 24 00.
b. In revised Section 07 24 00, Part 2.4.2.c is changed to state, " Drainage: Vertical troweled on adhesive providing channels for moisture drainage, or other drainage medium as required by manufacturer for their system."
C. Section 07 27 26
1. Replace Section 07 27 26 with revised Section 07 27 26 that includes change below:
a. Change Part 2.1.1.c “Vapor Impermeable Membrane” to “Vapor Permeable Membrane” meeting revised requirements as specified.
D. Section 09 67 23.13
1. Replace Section 09 67 23.13 with completely new Section 09 67 23.13.
E. Section 10 22 26.13
1. Delete Section 10 22 26.13 and replace with new Section 10 22 39.
F. Section 32 92 19:
1. Replace Section 32 92 19 with revised Section 32 92 19 that includes change below:
a. Deleted both Part 2.4 Mulch & Part 2.4.1 Straw from original Section 32 92 19.
Changes to plans:
A. Drawing A-131:
1. Replace Sheet A-131 with revised Sheet A-131 with colored markings.
B. Drawing A-201:
1. Replace Sheet A-201 with revised Sheet A-201 that has added Keyed Note 4.221 "PROVIDE HIGH
IMPACT RESISTANT EIFS WHERE EXPOSED TO PEDESTRIAN AND VEHICULAR TRAFFIC
AND NOT PROTECTED BY MASONRY VENEER, UP TO FIRST REVEAL, APPROX. 7'-8"
W50S9F21B0001
ABOVE GRADE”.
C. Drawing C-101:
1. Replace C-101 with revised C-101. Changed text that states, “RESTORATION AREA TOPSOIL, SEED & MULCH” to just say “RESTORATION AREA”. Added “NOTES” number 1 to define RESTORATION AREA requirements.
D. Drawing C-121:
1. Replace C-121 with revised C-121. Changed all labels that say, “LANDSCAPE RESTORATION” to “RESTORATION AREA”. Changed the label that says “SOD” to “RESTORATION AREA”. Added an additional “RESTORATION AREA” on east side of B406. Added “NOTES” number 1 to define RESTORATION AREA requirements.
Reports
A. Geotechnical Exploration and Analyses Report, dated Oct. 18, 2019:
1. Attached.