This document appears to be a set of questions and answers (Q&A) related to a federal solicitation for Repair Maintenance (MTX) Hangar Building 1001 (B1001) at the 125th Fighter Wing (FW) Jacksonville International Airport (JIA) in Jacksonville, Florida. The solicitation number is W50S6Y24B0002 and the project title is F-35 Repair Maintenance Hangar B1001, Project Number LSGA212001.

The Q&A provides responses from the Architect-Engineer (A-E) and Government to various technical and logistical questions submitted by the potential contractor, Advantor. Key details include requirements for new conduits, camera locations, door hardware, phasing plan challenges, utility cutovers, nitrogen gas piping, and fire alarm system modifications. The contract has a 540 calendar day Period of Performance and is set aside for small businesses under NAICS code 236220 with a $45M size standard. The project magnitude is estimated between $10M to $20M.

View the file

Other files

File Type Posted
Repair Hanger Abstract OF_1419-4.25.24-KO.pdf PDF
Bid Submission Day Sign-In Sheet-25APR24.pdf PDF
W50S6Y24B0002_00004 Repair MTX_19Apr24.pdf PDF
Rev 3 Attach-2 Adend 3- Electrical E-ED.pdf PDF
Set 06_Q-A_W50S6Y24B0002 Hanger.pdf PDF
QA Set 05 W50S6Y24B0002 Hanger.docx DOCX document
Rev 2 Attach-2 U. P-110B Adend 2.pdf PDF
Rev 2 Attach-2 E-M. STRC Adend 2.pdf PDF
Rev 2 Attach-2 C. CS402 ADEND2 signed.pdf PDF
Set 05_Q-A_W50S6Y24B0002 Hanger.pdf PDF
Rev 2 Attach-2 A. CD100 Adend 2 signed.pdf PDF
Rev 2 Attach-2 B. CU100 Adend 2 signed.pdf PDF
Rev 2 Attach-2 N-T. ARCH & Interiors Adend 2.pdf PDF
Rev 2 Attach-1_22 00 00 Specs.pdf PDF
Rev 2 Attach-2 D. CS403 Adend 2 signed.pdf PDF
W50S6Y24B0002_00003 Repair MTX_3Apr24.pdf PDF
Rev 2 Attach-2 II. TY-101 ADEND #2.pdf PDF
Notifier Panel Pics.pdf PDF
Rev 2 Attach-2 V-HH. ELEC Adend 2.pdf PDF
Set 03_Q-A_W50S6Y24B0002 Hanger.pdf PDF
W50S6Y24B0002_00002 Repair MTX_28Mar24.pdf PDF
Site Visit Sign-In Sheet-20MAR24.pdf PDF
Hanger Pre-Proposal minutes.pdf PDF
MTX Pre-Bid slides B1001.pptx PPTX presentation
Set 02_Q-A_W50S6Y24B0002 Hanger.pdf PDF
Addendum 01_Q-A_W50S6Y24B0002 Hanger.pdf PDF
Attach-7-125FW Form 2 Fillable (Aug 2023) - CAO 01MAR2024.pdf PDF
Rev 1 Attach-2-LSGA212001_B1001 Hangar Combined Drawings B-3_3.4.24.pdf PDF
Rev 1 Attach-1-LSGA212001_B1001 Hangar Combined Specifications B-3_3.4.24.pdf PDF
W50S6Y24B0002_00001 Repair MTX_5Mar24.pdf PDF
Attach-1-LSGA 212001_B1001 Hangar Combined Specifications B-3.pdf PDF
Attach-7-125FW Form 2 Installation Access Request dated Sep 2022.pdf PDF
Attach-4-JA-SS-LSGA212001-B-Advantor_Redacted.pdf PDF
Attach-2-LSGA 212001_B1001 Hangar Combined Drawings B-3.pdf PDF
Attach-3-JA-BN-LSGA212001-A-Best Locks_Cores-Redact.pdf PDF
W50S6Y24B0002 Repair MTX_29FEB24.pdf PDF
Attach-5-JA-BN-LSGA212001-C-Monaco-Redact.pdf PDF
Attach-6-JA-BN-LSGA212001-D-JCI Metasys-Redact.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION W50S6Y-24-B-0002 Repair Hanger B1001 (MTX) Set 04 Q&A

03 April 2024 Advantor’s design RFIs:

1. Where else can Advantor put Panel Enclosures besides Rooms 117A & 168 (Com Rooms)?

Otherwise, there will be a large amount of wiring that will need conveyance to these Rooms and the exis�ng conduit may not be of adequate size. (Example, each Card Reader is a 22/6 cable, each HSS is a 22/6 cable, ML and ES are 18/2) A-E Response: All Conduits for security shall be new. No exis�ng conduit shall be used. Conduit sizing shall be done per NEC. Wiring from each door must be done using combo cable as indicated in drawings T-205, T-206, and T-393. Per informa�on provided by Advantor, each Access control panel should support four doors. The General Contractor may suggest a varia�on once under contract, and A-E will evaluate. Bid as shown in drawings and specifica�on.

2. Is there a requirement for IVA (Immediate visual assessment) for the LOD protec�ng the aircra�? If so, the exis�ng CCTV does not provide the required needs, cameras will have to be added.

A-E Response: The Government Security Force to confirm if IVA is required for the LOD. Also, refer to the new camera loca�ons in sheets TY-101, TY-102, and TY-104. The design does not rely on any exis�ng cameras in the Hangar Bay.

3. Will Push Bars (Door ACS) be preinstalled and have a �e-in provided for Advantor to connect?

A-E Response: Contractor means and methods. Advantor to coordinate with the General Contractor.

4. Area A Door 113B just has an ES and no CR on the design, yet it has a symbol C that specifies a CR entry. Is there a CR on this door or is it just an Emergency Exit Door?

A-E Response: Door 113B is an Emergency Exit Door only. A revision for TY-101 will be provided in a forthcoming Amendment.

5. Is IDS required in any of the other offices or entry ways besides the Hangar Bay Area?

A-E Response: IDS only required in Hangar Area as shown in drawings.

General Ques�ons

6. Please reference drawing G-103 phasing plan. I believe there will be a big issue with this plan as far ac demo, and comple�on of phase 1 areas.

Phase #1 Which is on both ends of the building has new panelboards, busways, panel feeders, cable tray and systems in each of these. The problem is these feeders, and busway start out of room 148 which is in phase 3. Also, the cable trays and systems start out of the main It room.

There is no way to complete phase 1 without disturbing phases 2 and 3 so please explain how we are to demo, and finish phase #1, when everything starts from the beginning in phase 2 and

3. I’m sure this is also affec�ng other trades as well

A-E Response: The three phases need to be completed in order. When work in other phase areas of the building must occur in order to complete the phase currently being worked on, the Contractor shall coordinate access with the Government. Specifica�on 01 14 00, para. 1.2.b details the requirements for detailing the Contractors ini�al plan for construc�on phasing by submi�ng a Construc�on Phasing Plan which shall also detail areas where temporary work access will be necessary to account for the access concerns men�oned in the ques�on above.

The Government will review and approve the plan and coordinate Contractor access when needed as construc�on progresses. Proposed varia�ons to the phasing plan shown on Sheet G- 103 and will be considered by the Government during the pre-construc�on submital phase.

Note. Paragraph 1.2.b also men�ons areas not currently turned over to the contractor shall remain in opera�on. “In opera�on” includes power, HVAC, water/sanitary and telecommunica�ons services. Provide temporary services if the main building systems service must be isolated from the affected area. U�lity cutovers and temporary access to other phase areas shall be requested from the Government for approval NET 15 days prior (Ref. para.1.2.c and 1.3.5). Off-regular hours work for certain tasks may be scheduled with the Government.

Addi�onal provisions for working around occupied areas are in paragraph 1.3.4.

7. One other major ques�on regarding drawing E-007 riser. It calls for us to add one new conduit and wire from each new 1500 KVA transformer to each of the exis�ng main switchboards. Since these exis�ng switchboards are located approximately 30’ inside the building and I assume fed underground, how are we to maintain equal consistency with wires? Do the floors need to be dug up and equipment removed, or can this be ran underground up to the building and then overhead through the exis�ng building to the switchboards?

A-E Response: During demoli�on protect exis�ng transformer secondary cables. Megger test exis�ng cables prior to re-termina�ng at new transformers. Report results to engineer.

Reterminate exis�ng cables at new transformers and adjust circuit breaker trip se�ngs to 1550 amps. Drawings will be revised to reflect in a forthcoming Amendment.

8. P-110A shows a new High Pressure Nitrogen Gas Drop being installed. However there doesn’t seem to be anything within plans or specifica�ons addressing what type of piping required, fi�ngs or how this line will need to terminate within the wheel & Tire Shop. Please provide this informa�on required for pricing.

A-E Response: Nitrogen Pressure Drop is for �res per the FRD. Refer to updated Specifica�on 22 00 00 for piping and fi�ngs in forthcoming Amendment.

9. Per sec�on 1.3.5.4 of spec sec�on 09 67 23.15 and .16 it required the prep and coa�ng applica�on must be cer�fied to SSPC QP8. Only 7 or 8 companies in the na�on have this cer�fica�on and 2-3 only do steel work. We can provide cer�fica�ons from the manufacturer for installa�on and knowledge/prac�ces of proper prep of substrate. With this being said, will this cer�fica�on be required?

A-E Response: Refer to prior RFI response Set 03 Q#9 & 10

10. In hangar 101, 102 on the RCP the structure states to be EXP. On the finish schedule shows no work to be done, but on the finish legend EXP shall receive Dryfall paint. Please advise?

A-E Response: Refer to revised sheet I-601, Finish schedule in a forthcoming Amendment. Areas noted with EXP for Ceiling in the schedule shall receive EXP finish as called out in the Finish Legend.

11. Page A-132-A, the RCP, shows a one-hour sha� wall ceiling, buted up to the mezzanine 10” joists. This is at +/- 8’AFF. In the past, a system such as this required smoke/fire dampers and special sleeves on conduits and pipes. Ques�on--- Will the sha� wall be the finished ceiling?

What type of access will the other trades have?

A-E Response: Fire dampers, and fire rated pipe sleeves and conduits are to be provided for any penetra�ons through sha� wall ceiling system. Refer to MEP drawings for these condi�ons.

The underside of the sha� wall ceiling type B2 is intended to serve as the finished ceiling for rooms 103, 108, 111, 112, and 113a.

12. As shown on drawings E-010, E-011, E-012, E-013, are the 400 Hz 150A receptacles needing to be Class 1 Division 2?

A-E Response: As currently shown these are not required to be Class 1 Division 2.

13. Will there be a FOD walk each day throughout the dura�on of the project?

Gov Response: Refer to Sec 01000, Item 20, Cleanup/Disposal of debris & Fill of SF1442, the Contractor shall keep the site clean.

14. As shown on drawing E-005, the class1 division 2 will be in the area up to 18” above the floor and within 5’ around each plane, but will the areas outside these be unclassified or be specified as something else?

A-E Response: Refer to sheet E-005 and applicable codes and standards including but not limited to the UFC’s and NEC. Sheet E-005 tags adjacent spaces with applicable hazardous classifica�on ra�ngs.

15. As far as li�s in the hangars, will there be any restric�ons on what type of li�s will be allowed? (type and fuel) Gov Response: Eco friendly preferred, Electric/Propane, No other restrictions.

16. The exis�ng bird ne�ng in the hangar areas, will this be removed prior to work be completed in the areas or will we be working around these?

A-E Response: Refer to keynote D38 on demo RCP’s: Temporarily remove exis�ng bird ne�ng for installa�on of new fan.

17. The conduits feeding the 800A buss ducts and the power converter associated with the 400 Hz system, will this be required to be ran in aluminum conduit or will steel conduit suffice?

A-E Response: U�lize rigid aluminum conduits for these applica�ons.

18. Is there any specific badging/training that will be needed and if so, what would be the cost/ hours needed to get the badging completed?

KO Response: Form 2 is required for Base access, follow those instructions. Follow Sec 00700 and 01000 for any training requirements. No cost to submit Form 2s

19. Will there be a specific onsite storage area/staging area where we will be able to park a storage Conex?

Gov Response: see response to Q2 of Q&A set 4 for response.

20. Is this project apart of the Buy American Act?

Gov Response: No, see Solicitation Clause in reference to Buy American, Restriction on Foreign purchase and Supply chain order (not all inclusive)

21. Will this project require city permits/inspec�ons, or will they be conducted and recorded in house?

Gov Response: NO on City permits, inspection.

Yes, on Government like Burn permits, dig, etc.

22. On sheet S-101A, S6 can you please provide the height off the new CMU par��on wall or an eleva�on.

A-E Response: See arch. for par��on type and height (Sheets A-110A and A-005)

23. Reference specifica�on sec�on 09672315 Fuel Resis�ve Resinous Flooring 3 Coat System, paragraph 1.3.5.4 Qualifica�ons of Coa�ng Contractors. Ques�on: May installer NACE cer�fica�on be acceptable in lieu of the installer SSPC QP8 and SSPC QS1 cer�fica�on?

24. Reference specifica�on sec�on 09672315 Fuel Resis�ve Resinous Flooring 3 Coat System, paragraph 1.3.5.3 Qualifica�ons of QC Specialist Coa�ng Inspector. Ques�on: May 3rd party NACE inspec�on be acceptable in lieu of SSPC QP5 inspector cer�fica�on.

25. Please provide location & pictures of the Notifier Fire Alarm Control Panel Gov Response: See atached pictures A-E Response: See FA101D and Specifica�ons for exis�ng panel manufacture and loca�ons.

26. Please provide location & pictures of the Voice Control Panel (similar to a Notifier DVC)

Gov Response: See atached pictures A-E Response: See above- Comment #25

27. Specifica�ons and scope of work calls for a phased replacement of exis�ng conven�onal fire alarm in 1st floor only to a new code compliant addressable system and connect exis�ng devises on 2nd floor to the new system. The exis�ng fire alarm is integrated in all phased areas and work will have to be done in 1 phase, covering all areas. With a new system, we recommend that all devices, including the 2nd floor, is replaced to ensure warranty and UL lis�ng combability.

MCS recommends a new No�fier panel with voice evacua�on no�fica�on and a base specified transceiver for bass wide communica�on to be installed using a “Hot swap” method to reduce any fire alarm down�me. The system will be installed in 1 phase only and cover all areas.

A-E Response: Bid as shown on drawings and specifica�ons.

28. Please clarify the quantities of 12 strand OM4 cables as noted on the riser drawing. 4X12F- Is this 4 OM4 fiber optic cables? Also there is a 5X12F. Should we assume there is 4 OM4 MM and 5 OM4 MM fiber routing from the 1st floor comm rooms to the 2nd floor comm room?

A-E Response: 4X12F = 4 OM4 cables. 12 Strand Mul�mode Fiber is equivalent to one OM4 Cable. (Each cable should have 12 strands)

29. Are all existing block wall penetrations at removed ductwork required to be infilled as per detail

A1/S-401 (note they can only be identified on drawing MD110a, MD110b, MD110c, and MD110d)?

A-E Response: Yes, all penetra�ons at removed ductwork (that isn’t being reused or modified) will need to be infilled. Refer to forthcoming Amendment structural sheets where this is addressed.

30. Please confirm if the Type E Curtain Wall Entrance within the is project, is required to be Impact?

A-E Response: Yes.

31. what specifically in Phase 1 in support of Phase 2 is required to be completed so aircra� can be effec�vely housed in the facility by the EOM March 2025 deadline?

A-E Response: All of Phase 1.

32. Will the hangar be opera�onal or occupied during any por�on of the Period of Performance?

Gov Response: Yes

33. Will the KTR have space available within the facility for an office? It is understood that this office may need to relocate based on the phasing.

Gov Response: Yes, See Q&A set 03 #2

34. Will the hangar be available to use as a staging area for various materials, etc.?

Gov Response: Refer to Q&A set 03 #2

35. Is/Are there par�cular areas for laydown, equipment storage etc. outside?

Gov Response: Refer to Q&A set 03 #2

36. Are internal areas required to be isolated for dust control?

Gov Response: Yes, occupied areas.

37. The hazardous materials report does not indicate the presence of cadmium and chromium;

however, plans are required to address these contamina�ons. Is addi�onal tes�ng during the PoP required?

A-E Response: See response to Set 1 Q3.

38. Pb based paint was noted as probable, but none specifically iden�fied within the provided environmental assessment report; are we required to perform a more detailed report upon mobiliza�on to ascertain specific loca�ons and thereby removal be interpreted as ‘unforeseen’ and be facilitated via contract modifica�on?

A-E Response: Refer to Hazardous Materials report for what area(s) were determined to be posi�ve for lead. Comply with requirements in Specifica�on 02 83 00 and refer to sheet notes in Sheet AD-101A thru AD-101D.