This document provides acceptance criteria for the MK 706 Mod 0 Shipping Container to be used for the Hydra-70 Rocket System production contract. The criteria outline visual inspections and specific accept/reject guidelines for the shipping containers, including allowances for minor paint damage and dents but rejecting containers with major paint damage, body tube damage impeding motor insertion, or illegible stencil markings. The document also includes figures illustrating examples of acceptable and rejectable conditions.

A related special notice announces an industry day on March 27, 2018 to provide insight into and obtain feedback on the draft RFP for the Hydra-70 FY 19-23 Production and Engineering Services requirement for the Joint Attack Munition Systems Project Office. Interested parties are requested to pre-register by March 13 and submit any questions on the requirement or draft RFP by the same date. The technical data package will be provided to registered attendees. Questions and responses from the industry day will be posted to FEDBIZOPS within 15 business days.

Attachment 0020 MK 706 Mod 0 Shipping Container Acceptance Criteria

View the file

Other files

File Type Posted
Final_Vendor_Question_65_25_Apr_18.pdf PDF
Hydra-70_Final_Questions_and_Answers.pdf PDF
Hydra-70_Draft_RFP_and_Industry_Day_Questions_and_Answers_5_April_2018.pdf PDF
W31P4Q-17-R-0046_Hydra-70_Draft_RFP_as_of_26Mar2018.pdf PDF
Attach0006-_FFP_Hydra_Pricing_Tables.xlsm XLSM spreadsheet
Attach0010_MK2_Accept.pdf PDF
Attach0027__Delivery_Scenario.xls XLS spreadsheet
Attach0023_PMP.pdf PDF
Attach0017_SysRiskMgmtPlan.pdf PDF
Attach0002__IPT_Charter.pdf PDF
Attach0006-_FFP_Tables.xlsm XLSM spreadsheet
Attach0019_QASP.pdf PDF
ExB_CDRL.pdf PDF
Attach0016_Grain_TDPL.pdf PDF
Attach0007_ES_Pricing.xlsx XLSX spreadsheet
ExA_CDRL.pdf PDF
Attach0001_DSL.pdf PDF
Attach0025_Price_Template.xlsm XLSM spreadsheet
Attach0005_HazClass.pdf PDF
Attach0021__Refurb_Accept.pdf PDF
Attach0012_Changes.pdf PDF
Attach0011__OPSEC_DD254.pdf PDF
Attach0022_M643_Accept.pdf PDF
Attach_0003_SOW.pdf PDF
Attach0009_HazMtl.pdf PDF
Attach0004_TDPList.pdf PDF
Attach0008-GFP.pdf PDF
Attach0024__Skill_Crosswalk.xlsx XLSX spreadsheet
Attach0013_WBS.pdf PDF
Attach0026_Preaward_Survey.pdf PDF
https://einvitations.afit.edu/inv/anim.cfm?i=374163&k=016646087D54 —
W31P4Q-17-R-0046_DRAFT_for_Hydra-70_FY19-23_Production_and_Engineering_Services.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MK 706 MOD 0 SHIPPING CONTAINER

ACCEPTANCE CRITERIA

NSWC IHEODTD

DWG. 233AS600-233AS622

1 December 2016

PREPARED BY:

SYSTEMS ENGINEERING DEPARTMENT

AIR SYSTEMS BRANCH, CODE E11

INDIAN HEAD, MD 20640-5035

DISTRIBUTION C. Distribution authorized to U.S. Government Agencies and their contractors. Administrative or Operational Use, 1 Dec. 2016.

Other request for this document shall be referred to Commander, NSWC IHEODTD.

2 DISTRIBUTION STATEMENT C, U.S. Government Agencies & Contractors Only

1 Dec. 2016

1. PURPOSE

1.1 To provide acceptance criteria guidelines for the MK 706 Mod 0 Shipping

Container.

2. INSPECTION GUIDELINES

2.1 The MK 706 containers shall have been painted and shall also have

Performance Oriented Packaging (POP) marking and the warning

'REUSABLE CONTAINER – DO NOT DESTROY' applied to them in accordance with NAVAIR 233AS622. The Contractor shall also be responsible for assuring that the loaded containers meet the other marking requirements of NAVAIR 233AS600.

2.2 Likewise, the project engineer or designated alternate shall visually inspect the MK 706 MOD 0 Shipping Containers against the following guidelines:

Table 1. Accept/Reject Guidelines for MK 706 MOD 0 Shipping Containers

ACCEPT REJECT

1. Accept minor paint chips/scuffs not exposing bare metal (see Figure 1), except as defined below.

2. Bare metal exposure on MK 706 containers shall be allowed after motor pack-out and prior to shipping as long as it does not exceed one (1) square inch per occurrence and ten (10) square inches cumulative.

3. Accept dents (see Figure 3) in the thin-wall section of the Body Tube, e.g., within 37 inches from the Top’s stacking lugs, only if the inner diameter is greater than or equal to 3.109 inches. Inspection can be accomplished by inserting a calibrated diameter inspection cylinder

(length: 6 inches min.) machined to an outside diameter of 3.109 ± 0.005 inches.

1. Reject unit if major paint damage is exposing bare metal exceeding one (1) square inch per occurrence and ten (10) square inches cumulative (see Figure 2).

2. Reject unit if major Body Tube damage is impeding insertion of Rocket Motors.

3. Reject unit if a dent is in the thick-wall section of the Body Tube, e.g., within 6 inches from the bottom of the Base (see

Figure 4).

4. Reject unit if the inner diameter of the Body

Tube’s thin-wall section is less than 3.109 inches. Inspection can be accomplished by inserting a calibrated diameter inspection cylinder (length: 6 inches min.) machined to an outside diameter of 3.109 ± 0.005 inches.

3 DISTRIBUTION STATEMENT C, U.S. Government Agencies & Contractors Only

5. Reject unit if stencil markings are illegible

(see Figure 6).

6. Reject unit if Cover Assembly is missing

Gaskets, Buffers or Spacers (see Figure 7).

Likewise, reject for any discontinuity or deformity in the Gaskets.

7. Reject unit if Base is missing Buffers or

Acryl ic Spacers.

8. Reject unit if Cover Assembly is damaged or missing hardware.

9. Reject unit if there are holes or punctures in

Body Tubes.

10. Reject unit if stack-ability of containers is affected by:

a) Damaged stacking lugs, or

b) Top and Base surfaces are out of alignment, e.g., not on the same plane, crooked.

11. Body Tubes must be tight between Top and

Base; reject unit if Body Tubes can be turned by hand.

12. Reject unit if rivets (4 places) are missing on

Body Assembly’s Base.

4. Accept double stencil markings (see

Figure 5).

5. Accept some discoloration, dried water spots, and longitudinal deep scratches inside the Body Tubes.

Stains, light film of fine grit and/or trace amounts of tape stuck to the inner tube walls are also acceptable.

6. Accept if Buffers or Acrylic Spacers at the closed end have adhesive and/or small pieces of foreign material stuck to the adhesive around the edges.

7. Accept if Buffers are stained or discolored.

8. Accept covers with paint over-spray on the Gasket, Buffer and Acrylic

Spacer surfaces.

9. Accept if covers do not contain any paint on the underside of the cover.

10. Accept containers containing spots of white powdery residue on the exterior; the Contractor shall wipe the residue off the area to be stenciled prior to stenciling new markings.

11. Accept containers with bare metal exposure in the lug stacking area (as a result of typical shipping and handling damage) provided that no single instance is greater than one (1) square inch (see Figure 8).

12. Ensure that there is no excessive foreign material inside the Body

Tubes, e.g., less than 100 sand particles is acceptable.

4 DISTRIBUTION STATEMENT C, U.S. Government Agencies & Contractors Only

APPENDIX A

Figure 1. Minor Paint Damage (ACCEPT)

Figure 2. Major Paint Damage Exposing Bare Metal (REJECT*)

*Note: Bare metal exposure on MK 706 containers shall be allowed after motor pack-out and prior to shipping as long as it does not exceed one (1) square inch per occurrence and ten (10) square inches cumulative.

Figure 3. Minor Body Tube Damage (ACCEPT)

5 DISTRIBUTION STATEMENT C, U.S. Government Agencies & Contractors Only

Figure 4. Major Body Tube Damage (REJECT)

Figure 5. Double Stencil Markings (ACCEPT)

Figure 6. Illegible Stencil Markings (REJECT)

6 DISTRIBUTION STATEMENT C, U.S. Government Agencies & Contractors Only

Figure 7. Cover Plate with Missing Buffers/Acrylic Spacers (REJECT)

Figure 8. Bare Metal in Lug Stacking Area (ACCEPT)