VOL2.PDF

PDF 2 MB Posted

Attached to
Aircraft Maintenance Unit (AMU) and Weapons Hangar, Hurlburt Field, FL
Solicitation number
W9127820R0104
Issued by

About this file

This solicitation is for the construction of a new 105,041 square-foot aircraft maintenance hangar and weapons shop at Hurlburt Field, Florida. The project includes construction of a reinforced concrete foundation and floor slab, steel structure, masonry walls and standing seam metal roof. Supporting facilities include site utilities, pavements, communications and the demolition of seven existing buildings. Special site conditions require excavation, fill and soil stabilization. The facility will provide environmental control, fire detection and protection, and a mass notification system. Airfield pavements and roadway access are required. The work will result in a complete and usable facility. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Mobile.

View the file

Other files

File Type Posted
AM05 DRAWINGS.pdf PDF
AM05.pdf PDF
AM04.pdf PDF
AM04 DRAWINGS.pdf PDF
AM03.pdf PDF
Minutes-Pre-Bid site visit.pdf PDF
Minutes-Pre-Bid demo site visit.pdf PDF
AM03 DRAWINGS.pdf PDF
AM02.pdf PDF
APPENDIX F- As Builts of Demo Buildings- 1 of 3.zip ZIP file
APPENDIX F- As Builts of Demo Buildings- 2 of 3.zip ZIP file
APPENDIX F- As Builts of Demo Buildings- 3 of 3.zip ZIP file
AM01 Drawings.pdf PDF
AM01.pdf PDF
RTA DRAWINGS VOL 2.pdf PDF
VOL3.PDF PDF
VOL4.PDF PDF
RTA DRAWINGS VOL 1.pdf PDF
VOL6.PDF PDF
VOL1.PDF PDF
VOL5.PDF PDF
EM 385-1-1.pdf PDF
RTA DRAWINGS VOL 3.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

THIS PROJECT IS ADVERTISED ON AN UNRESTRICTED BASIS

VOLUME 2 OF 6

SOLICITATION NO: W9127820R0104

CADD NO: MEF20004

SPECIFICATIONS

FOR

FTEV153009 SOF AMU

AND

WEAPONS HANGAR FACILITY

HURLBURT FIELD, FLORIDA

(OKALOOSA COUNTY)

“GOOD ENGINEERING RESULTS IN A BETTER ENVIRONMENT”

U.S. ARMY ENGINEER DISTRICT, MOBILE

109 St. Joseph St

Mobile, Alabama 36602

FTEV153009 SOF AMU AND WEAPONS HANGAR FACILITY W9127820R0104

HURLBURT FIELD, FLORIDA MEF20004

Table of Contents Page 1

TABLE OF CONTENTS

VOLUME 1 OF 6

CHECKLIST FOR PREPARATION OF OFFERS

BIDDING REQUIREMENTS

STANDARD FORM 1442 - SOLICITATION, OFFER, AND AWARD

BIDDING SCHEDULE

EXPLANATION OF BID ITEMS

STANDARD FORM 24 - BID BOND

STANDARD FORM 28 - AFFIDAVIT OF INDIVIDUAL SURETY

STANDARD FORM LLL - DISCLOSURE OF LOBBYING ACTIVITIES

SMALL BUSINESS SUBCONTRACTING PLAN TEMPLATE

00 11 00 PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

00 12 00 EVALUATION CRITERIA AND BASIS OF AWARD

00 21 16 INSTRUCTIONS TO PROPOSERS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 70 00 CONDITIONS OF THE CONTRACT

SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 ADDITIONAL SPECIAL CONTRACT REQUIREMENTS

PROJECT SIGNS

DD FORM 1354

DD FORM 1354 CHECKLIST

WAGE RATES (BUILDING)

WAGE RATES (HEAVY)

01 00 01 GENERAL CONTRACT REQUIREMENTS

CESAM FORM 1151

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

SUBMITTAL REGISTER

FORM 4025

01 33 29 SUSTAINABILITY REPORTING

AIR FORCE SUSTAINABILITY REQUIREMENTS SCORESHEET

GUIDING PRINCIPLES ASSESSMENT

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

SAM FORM 696

01 45 35 SPECIAL INSPECTIONS

STATEMENT OF SPECIAL INSPECTIONS

SCHEDULE OF SPECIAL INSPECTIONS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS – HURLBURT STANDARD

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 TOTAL BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

Table of Contents Page 2

DIVISION 02 - EXISTING CONDITIONS (CONTINUED)

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 00 ASBESTOS REMEDIATION

02 83 00 LEAD REMEDIATION

02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs

AND MERCURY

DIVISION 03 - CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00.00 10 CAST-IN-PLACE CONCRETE

03 35 00.00 10 CONCRETE FINISHING

03 39 00.00 10 CONCRETE CURING

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION

DIVISION 04 – MASONRY

04 20 00 UNIT MASONRY

VOLUME 2 OF 6

DIVISION 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 11 13 BITUMINOUS DAMPPROOFING

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 22 00 ROOF AND DECK INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 42 13 METAL WALL PANELS

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

Table of Contents Page 3

DIVISION 07 - THERMAL AND MOISTURE PROTECTION (CONTINUED)

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 13 COILING COUNTER DOORS

08 34 16.10 STEEL SLIDING HANGAR DOORS

08 34 19.10 20 ROLLING SERVICE DOORS

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 51 13 ALUMINUM WINDOWS

08 51 23 STEEL WINDOWS

08 60 45 TRANSLUCENT PANELS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 67 23.15 FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DIVISION 10 - SPECIALTIES

10 11 00 VISUAL DISPLAY UNITS

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 13 WIRE MESH PARTITIONS

10 22 19 DEMOUNTABLE AND MOVABLE PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 51 13 METAL LOCKERS

DIVISION 11 - EQUIPMENT

11 01 50 FALL PROTECTION SYSTEMS

Table of Contents Page 4

VOLUME 3 OF 6

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

12 50 00.13 10 FURNITURE AND FURNITURE INSTALLATION

FFE ATTACHMENT

12 59 00 SYSTEMS FURNITURE

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00 BRACING FOR MISCELLANEOUS EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 13 17.00 10 DRY PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 13 25.00 10 HIGH EXPANSION FOAM (HI EX HEF) FIRE PROTECTION SYSTEM

21 30 00 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 48.19 BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 54 16.00 10 HEATING SYSTEM; GAS-FIRED HEATERS

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 CHILLED WATER PIPING SYSTEMS

23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 46.00 40 ELECTRIC UNIT HEATERS

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS ENERGY

MANAGEMENT CONTROL SYSTEM (EMCS) BUILDING LEVEL ONLY

25 05 11.02 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS FIRE

ALARM REPORTING SYSTEM/MASS NOTIFICATION SYSTEM BUILDING

LEVEL ONLY

25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END AND

INTEGRATION

Table of Contents Page 5

VOLUME 4 OF 6

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 PUBLIC ADDRESS SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 11 00 CLEARING AND GRUBBING

31 31 16.13 CHEMICAL TERMITE CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 16.71 COLD MILLING ASPHALT PAVING

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID

PAVEMENTS

32 11 23 GRADED CRUSHED AGGREGATE AND AGGREGATE BASE COURSES

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 15.13 ASPHALT PAVING FOR AIRFIELDS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS

32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

32 92 23 SODDING

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS

33 34 00 FORCE MAINS AND INVERTED SIPHONS; SEWER

33 40 00 STORM DRAINAGE UTILITIES

33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION

Table of Contents Page 6

DIVISION 33 – UTILITIES (CONTINUED)

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 34 – TRANSPORTATION

34 73 13 MOORING AND GROUNDING POINTS FOR AIRCRAFT

DIVISION 41 – MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.14 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING

41 22 13.15 BRIDGE CRANES, OVERHEAD ELECTRIC, UNDER RUNNING

VOLUME 5 OF 6

APPENDICES

APPENDIX A DRAFT SWPPP

APPENDIX B HAZARDOUS MATERIALS REPORTS

APPENDIX C EGLIN BORROW PIT GEOTECHNICAL DATA

VOLUME 6 OF 6

APPENDICES (CONTINUED)

APPENDIX D HAZARDOUS WASTE MANAGEMENT PLAN

APPENDIX E CAPA ERP

APPENDIX F AS-BUILTS OF DEMO BUILDINGS (PROVIDED ELECTRONICALLY ONLY)

APPENDIX G GEOTECHNICAL BORING LOGS

APPENDIX H HURLBURT ACM REPORT

APPENIDX I HURLBURT FIELD LEAD XRF AND CHIP SAMPLE REPORT

--End of Project Table of Contents--

SECTION 05 05 23.16

STRUCTURAL WELDING

05/14

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this Specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 360 (2016) Specification for Structural Steel Buildings

AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)

ANSI/ASNT CP-189 (2016) ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel (ANSI/ASNT CP-105-2006)

AMERICAN WELDING SOCIETY (AWS)

AWS A2.4 (2012) Standard Symbols for Welding, Brazing and Nondestructive Examination

AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel

AWS D1.3/D1.3M (2008; Errata 2008) Structural Welding Code - Sheet Steel

AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel

AWS D14.4/D14.4M (2012) Specification for Welded Joints for Machinery and Equipment

AWS Z49.1 (2012) Safety in Welding and Cutting and Allied Processes

ASTM INTERNATIONAL (ASTM)

ASTM E165/E165M (2012) Standard Practice for Liquid Penetrant Examination for General Industry

ASTM E709 (2015) Standard Guide for Magnetic Particle Examination

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office

SECTION 05 05 23.16 Page 1 that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Welding Quality Assurance Plan

SD-03 Product Data

Welding Procedure Qualifications; G

Welder, Welding Operator, and Tacker Qualification

Inspector Qualification

Previous Qualifications

Pre-Qualified Procedures

Welding Electrodes and Rods

SD-06 Test Reports

Non-Destructive Testing

SD-07 Certificates

Certified Welding Procedure Specifications (WPS)

Certified Brazing Procedure Specifications (BPS)

Certified Procedure Qualification Records (PQR)

Certified Welder Performance Qualifications (WPQ)

Certified Brazer Performance Qualifications (BPQ)

1.3 QUALITY ASSURANCE

Except for pre-qualified (in accordance with AWS D1.1/D1.1M ) and previously qualified procedures, each Contractor performing welding must record in detail and qualify the welding procedure specification for any welding procedure followed in the fabrication of weldments. Conform welding procedure qualifications to AWS D1.1/D1.1M and to the Specifications in this Section. Submit for approval copies of the Welding Procedure Specification and the results of the procedure qualification test records for each type of welding which requires procedure qualification and the welder, welding operator, or tacker qualification test records. Approval of any procedure, however, does not relieve the Contractor of the sole responsibility for producing a finished structure meeting all the specified requirements. Submit this information on the forms in Annex M of AWS D1.1/D1.1M . Individually identify and clearly reference on the Detail Drawings and Erection Drawings all Welding Procedure Specifications, or suitably key them to the Contract Drawings.

In case of conflict between this Specification and AWS D1.1/D1.1M , this Specification governs.

SECTION 05 05 23.16 Page 2

1.3.1 General Requirements

Fabricate Work in an AISC Certified Fabrication Plant, Category Std. Work must be erected by an AISC Certified Erector, Category CSE.

a. For Structural Projects, provide documentation of the following:

(1) Component Thickness 1/8 inch and greater: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D1.1/D1.1M .

(2) Component Thickness Less than 1/8 inch: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D1.3/D1.3M .

(3) Reinforcing Steel: Qualification documents (WPS, PWR, and WPQ) in accordance with AWS D1.4/D1.4M .

b. For other applications, provide documentation of the following:

(1) Submit two copies of the Certified Welding Procedure Specifications (WPS), Certified Brazing Procedure Specifications (BPS) and Certified Procedure Qualification Records (PQR) to the Contracting Officer.

(2) Submit two copies of the Certified Welder Performance Qualifications (WPQ)and Certified Brazer Performance Qualifications (BPQ) to the Contracting Officer within fifteen calendar days prior to any employee welding on the Project material.

(3) Machinery: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D14.4/D14.4M .

1.3.2 Previous Qualifications

Welding procedures previously qualified by test may be accepted for this Contract without re-qualification, upon receipt of the test results, if the following conditions are met:

a. Testing was performed by an approved testing laboratory, technical consultant, or the Contractor's approved quality control organization.

b. The qualified welding procedure conforms to the requirements of this Specification and is applicable to welding conditions encountered under this Contract.

c. The welder, welding operator, and tacker qualification tests conform to the requirements of this Specification and are applicable to welding conditions encountered under this Contract.

1.3.3 Pre-qualified Procedures

Welding procedures which are considered pre-qualified as specified in AWS D1.1/D1.1M will be accepted without further qualification. Submit for approval a listing or an annotated drawing to indicate the joints not pre-qualified. Procedure qualification is mandatory for these joints.

1.3.4 Retests

If welding procedure fails to meet the requirements of AWS D1.1/D1.1M , SECTION 05 05 23.16 Page 3 revise and re-qualify the procedure specification, or at the Contractor's option, welding procedure may be retested in accordance with AWS D1.1/D1.1M .

If the welding procedure is qualified through retesting, submit all test results, including those of test welds that failed to meet the requirements, with the welding procedure.

1.3.5 Welder, Welding Operator, and Tacker Qualification

Each welder, welding operator, and tacker assigned to work on this Contract must be qualified in accordance with the applicable requirements of AWS D1.1/D1.1M and as specified in this Section. Welders, welding operators, and tackers who make acceptable procedure qualification test welds will be considered qualified for the welding procedure used.

1.3.5.1 Previous Personnel Qualifications

At the discretion of the Contracting Officer, welders, welding operators, and tackers qualified by test within the previous 6 months may be accepted for this Contract without re-qualification if all the following conditions are met:

a. Copies of the Welding Procedure Specifications, the procedure qualification test records, and the welder, welding operator, and tacker qualification test records are submitted and approved in accordance with the specified requirements for Detail Drawings.

b. Testing was performed by an approved testing laboratory, technical consultant, or the Contractor's approved quality control organization.

c. The previously qualified welding procedure conforms to the requirements of this Specification and is applicable to welding conditions encountered under this Contract.

d. The welder, welding operator, and tacker qualification tests conform to the requirements of this Specification and are applicable to welding conditions encountered under this Contract.

1.3.5.2 Certificates

Before assigning any welder, welding operator, or tacker to work under this Contract, submit the names of the welders, welding operators, and tackers to be employed, and certification that each individual is qualified as specified. State in the certification the type of welding and positions for which the welder, welding operator, or tacker is qualified, the code and procedure under which the individual is qualified, the date qualified, and the name of the firm and person certifying the qualification tests. Keep the certification current, on file, and furnish 3 copies.

1.3.5.3 Renewal of Qualification

Re-qualification of a welder or welding operator is required under any of the following conditions:

a. It has been more than 6 months since the welder or welding operator has used the specific welding process for which he is qualified.

b. There is specific reason to question the welder or welding operator's ability to make welds that meet the requirements of these

SECTION 05 05 23.16 Page 4

Specifications.

c. The welder or welding operator was qualified by an employer other than those firms performing work under this Contract, and a qualification test has not been taken within the past 12 months. Submit as evidence of conformance all records showing periods of employment, name of employer where welder, or welding operator, was last employed, and the process for which qualified.

d. A tacker who passes the qualification test is considered eligible to perform tack welding indefinitely in the positions and with the processes for which he/she is qualified, unless there is some specific reason to question the tacker's ability. In such a case, the tacker is required to pass the prescribed tack welding test.

1.3.6 Inspector Qualification

Submit inspector qualifications that are in accordance with AWS D1.1/D1.1M .

Qualify all non-destructive testing personnel in accordance with the requirements of ANSI/ASNT CP-189 for Levels I or II in the applicable non-destructive testing method. The inspector may be supported by assistant welding inspectors who are not qualified to AWS D1.1/D1.1M , and assistant inspectors may perform specific inspection functions under the supervision of the qualified inspector, as allowed by AWS D1.1/D1.1M .

1.3.7 Symbols and Safety

Use symbols in accordance with AWS A2.4 , unless otherwise indicated.

Follow safe welding practices and safety precautions during welding in conformance with AWS Z49.1 .

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

Conform the design of welded connections to AISC 360 , unless otherwise indicated or specified. Material with welds will not be accepted unless the welding is specified or indicated on the Drawings or otherwise approved. Perform welding as specified in this Section, except where additional requirements are shown on the Drawings or are specified in other sections. Do not commence welding until welding procedures, inspectors, non-destructive testing personnel, welders, welding operators, and tackers have been qualified and the submittals approved by the Contracting Officer. Perform all testing at or near the Work Site.

Maintain records of the test results obtained in welding procedure, welder, welding operator, and tacker performance qualifications.

2.1.1 Pre-erection Conference

Hold a pre-erection conference prior to the start of the field welding, to bring all affected parties together and to gain a naturally clear understanding of the Project and the Welding Procedure Specifications (WPS) (submitted for all welding, including welding done using pre-qualified procedures). Mandatory attendance is required by all Contractor's welding production and inspection personnel and appropriate Government personnel. Include as items for discussion: Responsibilities of various parties; welding procedures and processes to be followed;

welding sequence (both within a joint and joint sequence within the building); inspection requirements and procedures, both visual and

SECTION 05 05 23.16 Page 5 nondestructive testing; welding schedule; and other items deemed necessary by the attendees.

2.2 WELDING EQUIPMENT AND MATERIALS

Provide all welding equipment, welding electrodes and rods, welding wire, and fluxes capable of producing satisfactory welds when used by a qualified welder or welding operator performing qualified welding procedures. Provide welding equipment and materials that comply with the applicable requirements of AWS D1.1/D1.1M . Submit product data on welding electrodes and rods.

PART 3 EXECUTION

3.1 WELDING OPERATIONS

3.1.1 Requirements

Conform workmanship and techniques for welded construction to the requirements of AWS D1.1/D1.1M and AISC 360 . When AWS D1.1/D1.1M and the AISC 360 Specification conflict, the requirements of AWS D1.1/D1.1M govern.

3.1.2 Identification

Identify all welds in one of the following ways:

a. Submit written records to indicate the location of welds made by each welder, welding operator, or tacker.

b. Identify all work performed by each welder, welding operator, or tacker with an assigned number, letter, or symbol to identify welds made by that individual. The Contracting Officer may require welders, welding operators, and tackers to apply their symbol next to the weld by means of rubber stamp, felt-tipped marker with waterproof ink, or other methods that do not cause an indentation in the metal. Place the identification mark for seam welds adjacent to the weld at 3 foot intervals. Identification with die stamps or electric etchers is not allowed.

3.2 QUALITY CONTROL

Perform testing using an approved inspection or testing laboratory or technical consultant; or if approved, the Contractor's inspection and testing personnel may be used instead of the commercial inspection or testing laboratory or technical consultant. Perform visual ultrasonic, magnetic particle, and liquid penetrant or dye penetrant inspections to determine conformance with Paragraph "Standards of Acceptance". Conform procedures and techniques for inspection with applicable requirements of AWS D1.1/D1.1M , ASTM E165/E165M , and ASTM E709. Submit a Welding Quality Assurance Plan and records of tests and inspections.

3.3 STANDARDS OF ACCEPTANCE

Conform dimensional tolerances for welded construction, details of welds, and quality of welds with the applicable requirements of AWS D1.1/D1.1M and the Contract Drawings. Perform non-destructive testing by visual inspection and ultrasonic, magnetic particle, or dye penetrant methods.

The minimum extent of non-destructive testing must be random 10 percent of welds or joints, as indicated on the Drawings. Submit all records of

SECTION 05 05 23.16 Page 6 non-destructive testing.

3.3.1 Nondestructive Testing

The welding is subject to inspection and tests in the mill, shop, and field. Inspection and tests in the mill or shop do not relieve the Contractor of the responsibility to furnish weldments of satisfactory quality. When materials or workmanship do not conform to the Specification Requirements, the Government reserves the right to reject material or workmanship or both at any time before final acceptance of the structure containing the weldment. Any indication of a defect is regarded as a defect, unless re-evaluation by non-destructive methods or by surface conditioning shows that no unacceptable defect is present. Submit all records of non-destructive testing in accordance with Paragraph "Standards of Acceptance".

3.3.2 Destructive Tests

Make all repairs when metallographic specimens are removed from any part of a structure. Employ only qualified welders or welding operators, and use the proper joints and welding procedures, including peening or heat treatment if required, to develop the full strength of the members and joints cut and to relieve residual stress.

3.4 GOVERNMENT INSPECTION AND TESTING

In addition to the inspection and tests performed by the Contractor for quality control, the Government will perform inspection and testing for acceptance to the extent determined by the Contracting Officer. The costs of such inspection and testing will be borne by the Contractor if unsatisfactory welds are discovered, or by the Government if the welds are satisfactory. The Work may be performed by the Government's own forces or under a separate contract for inspection and testing. The Government reserves the right to perform supplemental non-destructive and destructive tests to determine compliance with Paragraph "Standards of Acceptance".

3.5 CORRECTIONS AND REPAIRS

If inspection or testing indicates defects in the weld joints, repair defective welds using a qualified welder or welding operator as applicable. Conduct corrections in accordance with the requirements of AWS D1.1/D1.1M and the Specifications. Repair all defects in accordance with the approved procedures. Repair defects discovered between passes before additional weld material is deposited. Wherever a defect is removed and repair by welding is not required, blend the affected area into the surrounding surface to eliminate sharp notches, crevices, or corners. After a defect is thought to have been removed, and before re-welding, examine the area by suitable methods to ensure that the defect has been eliminated. Repaired welds must meet the inspection requirements for the original welds.

-- End of Section --

SECTION 05 05 23.16 Page 7

This page was intentionally left blank for duplex printing.

SECTION 05 12 00

STRUCTURAL STEEL

05/14

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this Specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 303 (2016) Code of Standard Practice for Steel Buildings and Bridges

AISC 325 (2017) Steel Construction Manual

AISC 326 (2009) Detailing for Steel Construction

AISC 360 (2016) Specification for Structural Steel Buildings

AISC DESIGN GUIDE 10 (1997) Erection Bracing of Low-Rise Structural Steel Buildings

AMERICAN WELDING SOCIETY (AWS)

AWS A2.4 (2012) Standard Symbols for Welding, Brazing and Nondestructive Examination

AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel

ASME INTERNATIONAL (ASME)

ASME B46.1 (2009) Surface Texture, Surface Roughness, Waviness and Lay

ASTM INTERNATIONAL (ASTM)

ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products

ASTM A143/A143M (2007; R 2014) Standard Practice for Safeguarding Against Embrittlement of Hot-Dip Galvanized Structural Steel Products and Procedure for Detecting Embrittlement

ASTM A29/A29M (2016) Standard Specification for General Requirements for Steel Bars, Carbon and Alloy, Hot-Wrought

ASTM A325 (2014) Standard Specification for

SECTION 05 12 00 Page 1

Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength

ASTM A36/A36M (2014) Standard Specification for Carbon Structural Steel

ASTM A490 (2014a) Standard Specification for Structural Bolts, Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength

ASTM A500/A500M (2018) Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes

ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A563 (2015) Standard Specification for Carbon and Alloy Steel Nuts

ASTM A6/A6M (2017a) Standard Specification for General Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling

ASTM A780/A780M (2009; R 2015) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings

ASTM A992/A992M (2011) Standard Specification for Structural Steel Shapes

ASTM C1107/C1107M (2017) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM C827/C827M (2016) Standard Test Method for Change in Height at Early Ages of Cylindrical Specimens of Cementitious Mixtures

ASTM F1554 (2018) Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi Yield Strength

ASTM F1852 (2014) Standard Specification for "Twist Off" Type Tension Control Structural Bolt/Nut/Washer Assemblies, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength

ASTM F2280 (2014) Standard Specification for “Twist Off” Type Tension Control Structural Bolt/Nut/Washer Assemblies, Steel, Heat Treated, 150 ksi Minimum Tensile Strength

ASTM F2329 (2013) Zinc Coating, Hot-Dip, Requirements for Application to Carbon and Alloy Steel Bolts, Screws, Washers, Nuts, and Special Threaded Fasteners

SECTION 05 12 00 Page 2

ASTM F436 (2011) Hardened Steel Washers

ASTM F844 (2007a; R 2013) Washers, Steel, Plain (Flat), Unhardened for General Use

ASTM F959/F959M (2017) Standard Specification for Compressible-Washer-Type Direct Tension Indicators for Use with Structural Fasteners, Inch and Metric Series

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC Paint 20 (2002; E 2004) Zinc-Rich Primers (Type I, Inorganic, and Type II, Organic)

SSPC SP 3 (1982; E 2004) Power Tool Cleaning

SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-301-01 (2013; with Change 3) Structural Engineering

UFC 3-310-04 (2016) Seismic Design for Buildings

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Erection Plan, Including Description of Temporary Supports; G, AE

Erection Drawings; G, AE

SD-02 Shop Drawings

Fabrication Drawings, Including Description of Connections; G, AE

SD-03 Product Data

Recycled Content; S

Shop Primer

Welding Electrodes and Rods

Direct Tension Indicator Washers

Non-Shrink Grout

SECTION 05 12 00 Page 3

Tension Control Bolts

SD-06 Test Reports

Class B Coating

Bolts, Nuts, and Washers

Weld Inspection Reports

Direct Tension Indicator Washer Inspection Reports

Bolt Testing Reports

Embrittlement Test Reports

SD-07 Certificates

Steel; G

Bolts, Nuts, and Washers

Galvanizing

AISC Fabrication Plant Quality Certification; G

AISC Erector Quality Certification; G

Welding Procedures and Qualifications

Welding Electrodes and Rods

1.3 AISC QUALITY CERTIFICATION

Work must be fabricated in an AISC Certified Fabrication Plant, Category Std. Submit AISC fabrication plant quality certification.

Work must be erected by an AISC Certified Erector, Category CSE. Submit AISC erector quality certification.

1.4 QUALITY ASSURANCE

1.4.1 Preconstruction Submittals

1.4.1.1 Erection Drawings

Submit Erection Drawings and Erection Plan for record purposes. Indicate the sequence of erection, temporary shoring and bracing. The Erection Drawings must conform to AISC 303 . Erection Drawings must be reviewed, stamped and sealed by a Registered Professional Engineer.

1.4.2 Fabrication Drawing Requirements

Submit Fabrication Drawings for approval prior to fabrication. Prepare in accordance with AISC 326 and AISC 325 . Fabrication Drawings must not be reproductions of Contract Drawings. Include complete information for the fabrication and erection of the structure's components, including the location, type, and size of bolts, welds, member sizes and lengths, connection details, blocks, copes, bearing plates, and cuts. Use AWS A2.4

SECTION 05 12 00 Page 4 standard welding symbols. Shoring and temporary bracing must be designed and sealed by a Registered Professional Engineer and submitted for record purposes, with calculations, as part of the Drawings. Any deviations from the details shown on the Contract Drawings must be clearly highlighted on the Fabrication Drawings. Explain the reasons for any deviations from the Contract Drawings.

1.4.3 Certifications

1.4.3.1 Welding Procedures and Qualifications

Prior to welding, submit certification for each welder stating the type of welding and positions qualified for, the code and procedure qualified under, date qualified, and the firm and individual certifying the qualification tests. If the qualification date of the welding operator is more than one-year old, the welding operator's qualification certificate must be accompanied by a current certificate by the welder attesting to the fact that he has been engaged in welding since the date of certification, with no break in welding service greater than 6 months.

Conform to all requirements specified in AWS D1.1/D1.1M .

PART 2 PRODUCTS

2.1 Recycled Content

Provide products with recycled content in accordance with Section 01 33 29

SUSTAINABILITY REPORTING.

2.2 SYSTEM DESCRIPTION

Provide the structural steel system, including shop primer and galvanizing, complete and ready for use. Structural steel systems including design, materials, installation, workmanship, fabrication, assembly, erection, inspection, quality control, and testing must be provided in accordance with AISC 360 , UFC 3-301-01 , and UFC 3-310-04 , except as modified in this Contract.

2.3 STEEL

2.3.1 Structural Steel

Wide flange and WT shapes, ASTM A992/A992M . Channels, ASTM A36/A36M.

2.3.2 Structural Steel Tubing

ASTM A500/A500M , Grade B.

2.3.3 Steel Pipe

ASTM A53/A53M, Type E or S, Grade B, weight class STD (Standard).

2.4 BOLTS, NUTS, AND WASHERS

Submit the certified manufacturer's mill reports which clearly show the applicable ASTM mechanical and chemical requirements together with the actual test results for the supplied fasteners.

SECTION 05 12 00 Page 5

2.4.1 High-Strength Bolts

2.4.1.1 Bolts

ASTM A325, Type 1. ASTM A490, Type 1 or 2.

2.4.1.2 Nuts

ASTM A563, Grade and Style as specified in the applicable ASTM bolt standard.

2.4.1.3 Direct Tension Indicator Washers

ASTM F959/F959M .

2.4.1.4 Washers

ASTM F436, plain carbon steel.

2.4.2 Tension Control Bolts

ASTM F1852 or ASTM F2280, Type 1, heavy-hex head assemblies consisting of steel structural bolts with splined ends, heavy-hex carbon steel nuts, and hardened carbon steel washers. Assembly finish must be plain.

2.4.3 Foundation Anchorage

2.4.3.1 Anchor Rods

ASTM F1554 Gr 55 Supplement 1 (weldable), Class 1A.

2.4.3.2 Anchor Nuts

ASTM A563, Grade A, hex style.

2.4.3.3 Anchor Washers

ASTM F844.

2.4.3.4 Anchor Plate Washers

ASTM A36/A36M.

2.5 STRUCTURAL STEEL ACCESSORIES

2.5.1 Welding Electrodes and Rods

AWS D1.1/D1.1M .

2.5.2 Non-Shrink Grout

ASTM C1107/C1107M , with no ASTM C827/C827M shrinkage. Grout must be non-metallic.

2.5.3 Welded Shear Stud Connectors

ASTM A29/A29M, Type B. AWS D1.1/D1.1M .

SECTION 05 12 00 Page 6

2.6 GALVANIZING

ASTM F2329 for threaded parts or ASTM A123/A123M for structural steel members, as applicable, unless specified otherwise galvanize after fabrication where practicable.

2.7 FABRICATION

Fabrication must be in accordance with the applicable provisions of AISC 325 . Fabrication and assembly must be done in the shop to the greatest extent possible. Punch, subpunch and ream, or drill bolt holes perpendicular to the surface of the member.

Compression joints depending on contact bearing must have a surface roughness not in excess of 500 micro inches as determined by ASME B46.1 , and ends must be square within the tolerances for milled ends specified in

ASTM A6/A6M.

Shop splices of members between field splices will be permitted only where indicated on the Contract Drawings. Splices not indicated require the approval of the Contracting Officer.

Do not splice truss top and bottom chords except as approved by the Contracting Officer. Chord splices must occur at panel joints at approximately the third point of the span. The center of gravity lines of truss members must intersect at panel points unless otherwise approved by the Contracting Officer. When the center of gravity lines do not intersect at a panel point, provisions must be made for the stresses due to eccentricity. Camber of trusses must be 1/8 inch in 10 feet unless otherwise indicated.

2.7.1 Markings

Prior to erection, members must be identified by a painted erection mark.

Connecting parts assembled in the shop for reaming holes in field connections must be match marked with scratch and notch marks. Do not locate erection markings on areas to be welded. Do not locate match markings in areas that will decrease member strength or cause stress concentrations. Affix embossed tags to hot-dipped galvanized members.

2.7.2 Shop Primer

SSPC Paint 20 (zinc rich primer). Shop prime structural steel in accordance with Section 09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES.

Do not prime steel surfaces embedded in concrete, galvanized surfaces, surfaces to receive epoxy coatings, or surfaces within 0.5 inch of the toe of the welds prior to welding (except surfaces on which metal decking is to be welded). If flash rusting occurs, re-clean the surface prior to application of primer.

Slip critical surfaces must be primed with a Class B coating in accordance with AISC 325 . Submit test report for Class B coating.

Prior to assembly, prime surfaces which will be concealed or inaccessible after assembly. Do not apply primer in foggy or rainy weather; when the ambient temperature is below 45 degrees F or over 95 degrees F; or when the primer may be exposed to temperatures below 40 degrees F within 48 hours after application, unless approved otherwise by the Contracting Officer. Repair damaged primed surfaces with an additional coat of primer.

SECTION 05 12 00 Page 7

2.7.2.1 Cleaning

SSPC SP 6/NACE No.3 , except steel exposed in spaces above ceilings, attic spaces, furred spaces, and chases that will be hidden to view in finished construction may be cleaned to SSPC SP 3 when recommended by the shop primer manufacturer. Maintain steel surfaces free from rust, dirt, oil, grease, and other contaminants through final assembly.

2.7.3 Epoxy Coated Surfaces

Surfaces to receive epoxy coatings must be cleaned and prepared in accordance with the manufacturer's recommendations, and as specified in Section 09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES.

2.8 DRAINAGE HOLES

Adequate drainage holes must be drilled to eliminate water traps. Hole diameter must be 1/2 inch and location must be indicated on the Detail Drawings. Hole size and location must not affect the structural integrity.

PART 3 EXECUTION

3.1 ERECTION

a. Erection of structural steel, except as indicated in item b. below, must be in accordance with the applicable provisions of AISC 325 .

b. For low-rise structural steel buildings (60 feet tall or less and a maximum of 2 stories), the structure must be erected in accordance with AISC DESIGN GUIDE 10 .

After final positioning of steel members, provide full bearing under base plates and bearing plates using non-shrink grout. Place non-shrink grout in accordance with the manufacturer's instructions.

3.1.1 STORAGE

Material must be stored out of contact with the ground in such manner and location as will minimize deterioration.

3.2 CONNECTIONS

Except as modified in this Section, connections not detailed must be designed in accordance with AISC 360 . Build connections into existing work. Do not tighten anchor bolts set in concrete with impact torque wrenches. Holes must not be cut or enlarged by burning. Bolts, nuts, and washers must be clean of dirt and rust, and lubricated immediately prior to installation.

3.2.1 High-Strength Bolts

Provide direct tension indicator washers in all ASTM A325 and ASTM A490 bolted connections. Bolts must be installed in connection holes and initially brought to a snug tight fit. After the initial tightening procedure, bolts must then be fully tensioned, progressing from the most rigid part of a connection to the free edges.

SECTION 05 12 00 Page 8

3.2.1.1 Installation of Direct Tension Indicator Washers (DTIW)

Where possible, the DTIW must be installed under the bolt head and the nut must be tightened. If the DTIW is installed adjacent to the turned element, provide a flat washer between the DTIW and nut when the nut is turned for tightening, and between the DTIW and bolt head when the bolt head is turned for tightening. In addition to the LIW, provide flat washers under both the bolt head and nut when ASTM A490 bolts are used.

3.2.2 Tension Control Bolts

Bolts must be installed in connection holes and initially brought to a snug tight fit. After the initial tightening procedure, bolts must then be fully tensioned, progressing from the most rigid part of a connection to the free edges.

3.3 GAS CUTTING

Use of gas-cutting torch in the field for correcting fabrication errors will not be permitted on any major member in the structural framing. Use of a gas cutting torch will be permitted on minor members not under stress only after approval has been obtained from the Contracting Officer.

3.4 WELDING

Welding must be in accordance with AWS D1.1/D1.1M . Provide AWS D1.1/D1.1M qualified welders, welding operators, and tackers.

Develop and submit the Welding Procedure Specifications (WPS) for all welding, including welding done using prequalified procedures.

Prequalified procedures may be submitted for information only; however, procedures that are not prequalified must be submitted for approval.

3.4.1 Removal of Temporary Welds, Run-Off Plates, and Backing Strips

Remove only from finished areas.

3.5 SHOP PRIMER REPAIR

Repair shop primer in accordance with the paint manufacturer's recommendation for surfaces damaged by handling, transporting, cutting, welding, or bolting.

3.5.1 Field Priming

Steel exposed to the weather, or located in building areas without HVAC for control of relative humidity must be field primed. After erection, the field bolt heads and nuts, field welds, and any abrasions in the shop coat must be cleaned and primed with paint of the same quality as that used for the shop coat.

3.6 GALVANIZING REPAIR

Repair damage to galvanized coatings using ASTM A780/A780M zinc rich paint for galvanizing damaged by handling, transporting, cutting, welding, or bolting. Do not heat surfaces to which repair paint has been applied.

SECTION 05 12 00 Page 9

3.7 FIELD QUALITY CONTROL

Perform field tests, and provide labor, equipment, and incidentals required for testing, except that electric power for field tests will be furnished as set forth in Division 1. The Contracting Officer must be notified in writing of defective welds, bolts, nuts, and washers within 7 working days of the date of the inspection.

3.7.1 Welds

See Section 05 05 23.16 STRUCTURAL WELDING.

3.7.2 Direct Tension Indicator Washers

3.7.2.1 Direct Tension Indicator Washer Compression

Direct tension indicator washers must be tested in place to verify that they have been compressed sufficiently to provide the 0.015 inch gap when the direct tension indicator washer is placed under the bolt head and the nut is tightened, and to provide the 0.005 inch gap when the direct tension indicator washer is placed under the turned element, as required by ASTM F959/F959M . Submit direct tension indicator washer inspection reports.

3.7.2.2 Direct Tension Indicator Gaps

In addition to the above testing, an independent testing agency as approved by the Contracting Officer, must test in place the direct tension indicator gaps on 20 percent of the installed direct tension indicator washers to verify that the ASTM F959/F959M direct tension indicator gaps have been achieved. If more than 10 percent of the direct tension indicators tested have not been compressed sufficiently to provide the average gaps required by ASTM F959/F959M , then all in place direct tension indicator washers shall be tested to verify that the ASTM F959/F959M direct tension indicator gaps have been achieved. Test locations must be selected by the Contracting Officer.

3.7.3 High-Strength Bolts

3.7.3.1 Testing Bolt, Nut, and Washer Assemblies

Test a minimum of 3 bolt, nut, and washer assemblies from each mill certificate batch in a tension measuring device at the Job Site prior to the beginning of bolting start-up. Demonstrate that the bolts and nuts, when used together, can develop tension not less than the provisions specified in AISC 360 , depending on bolt size and grade. The bolt tension must be developed by tightening the nut. A representative of the manufacturer or supplier must be present to ensure that the fasteners are properly used, and to demonstrate that the fastener assemblies supplied satisfy the specified requirements. Submit bolt testing reports.

3.7.3.2 Inspection

Inspection procedures must be in accordance with AISC 360 . Confirm and report to the Contracting Officer that the materials meet the Project Specification and that they are properly stored. Confirm that the faying surfaces have been properly prepared before the connections are assembled. Observe the specified Job Site testing and calibration, and confirm that the procedure to be used provides the required tension.

SECTION 05 12 00 Page 10

Monitor the Work to ensure the testing procedures are routinely followed on joints that are specified to be fully tensioned.

Inspection by the Government will include calibration of torque wrenches for high-strength bolts.

Inspect calibration of torque wrenches for high-strength bolts.

3.7.3.3 Testing

The Government has the option to perform non-destructive tests on 5 percent of the installed bolts to verify compliance with pre-load bolt tension requirements. Provide the required access for the Government to perform the tests. The non-destructive testing will be done in-place using an ultrasonic measuring device or any other device capable of determining in-place pre-load bolt tension. The test locations must be selected by the Contracting Officer. If more than 10 percent of the bolts tested contain defects identified by testing, then all bolts used from the batch from which the tested bolts were taken, must be tested at the Contractor's expense. Retest new bolts after installation at the Contractor's expense.

3.7.4 Testing for Embrittlement

ASTM A143/A143M for steel products hot-dip galvanized after fabrication.

Submit embrittlement test reports.

SECTION 05 12 00 Page 11

SECTION 05 21 00

STEEL JOIST FRAMING

05/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this Specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel

INTERNATIONAL CODE COUNCIL (ICC)

ICC IBC (2018) International Building Code

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals

SSPC Paint 15 (1999; E 2004) Steel Joist Shop Primer

SSPC SP 2 (1982; E 2000; E 2004) Hand Tool Cleaning

STEEL JOIST INSTITUTE (SJI)

SJI LOAD TABLES (2010; Errata 1 2011; Errata 2 2012) 42nd Edition Catalog of Standard Specifications Load Tables and Weight Tables for Steel Joists and Joist Girders

SJI MANUAL (2009) 80 Years of Open Web Steel Joist Construction

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.756 Steel Erection; Beams and Columns

29 CFR 1926.757 Steel Erection; Open Web Steel Joists

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to

SECTION 05 21 00 Page 1

Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Welder Qualification

SD-02 Shop Drawings

Steel Joist Framing; G, AE

SD-05 Design Data

Design Calculations; G, AE

SD-06 Test Reports

Erection Inspection

Welding Inspections

SD-07 Certificates

Certification of Compliance

SD-11 Closeout Submittals

Recycled Content of Steel Products; S

1.3 QUALITY ASSURANCE

Perform all work in compliance with the requirements set forth in

29 CFR 1926 .

1.3.1 Drawing Requirements

Submit drawings of steel joist framing including fabrication, Specifications for shop painting, and identification markings of joists.

Show joist type and size, layout in plan, all applicable loads, deflection criteria, and erection details including methods of anchoring, framing at openings, type, size, and location and connections for and spacing of bridging, requirements for field welding, and details of accessories as applicable. Show profiles for non-standard joist configurations. Show steel joist field splice locations and details.

1.3.2 Certification of Compliance

Prior to construction commencement, submit certification for welder qualification, in compliance with AWS D1.1/D1.1M , welding operation, and tacker, stating the type of welding and positions qualified for, the code and procedure qualified under, date qualified, and the firm and individual certifying the qualification tests. Submit certification of compliance for the following:

a. SJI MANUAL.

b. Steel Joist Institute Member Fabricator.

c. 29 CFR 1926 .

SECTION 05 21 00 Page 2

d. 29 CFR 1926.757 .

e. Statement from steel joist manufacturer, that work was performed in accordance with approved construction documents and with SJI standard specifications, in…